AHI Red Deer / Blindman Industrial Park AI Data Centre
Red Deer County approved the Phase 1 discretionary use in October 2025. Havenz reports that the first 10 MW natural-gas power block and supporting infrastructure are under construction. The installed engines are described as hydrogen-ready, but the reviewed sources do not establish current hydrogen blending or hydrogen-fuelled operation.
Project facts
Core scale, approval, employment, and schedule information, labelled by the type of evidence available.
Site
48.5 hectares (about 120 acres)The Phase 1 buildings occupy only part of the parcel.
Sources [1]Municipal decision
Approved October 7, 2025Red Deer County approved the discretionary use with conditions. The motion carried with one councillor opposed.
Sources [2]Phase 1 buildings
1,000 m² data centre; 471 m² administrationSources [1]Construction status
Phase 1 power block underwayHavenz reports foundations, mechanical and electrical work, and supporting infrastructure underway. Alberta Major Projects separately categorizes the project as under construction.
Sources [5], [3]Expected on-site employment
Approximately 5 to 7 peopleApplicant estimate recorded in the County report, not an observed employment count.
Sources [1]Energy and emissions
The current Phase 1 disclosure, later campus ambitions, and possible grid export are separate claims. Only the initial 10 MW power block is included as the current project capacity.
Phase 1 generation
10 MWThe first modular on-site power block is intended to scale with customer demand. This is generation capacity, not a verified IT load.
Sources [5], [4]Current fuel configuration
Natural gasThe installed reciprocating engines are described as hydrogen-ready. No source reviewed by ADCW establishes that hydrogen is currently being supplied or burned.
Sources [5], [6]Hydrogen blending
Proposed future stepEnergy Haven describes blending hydrogen with natural gas, but does not publish a blend percentage, supply contract, implementation date, or operating record.
Sources [6], [4]Full hydrogen transition
Long-term roadmapThe developer describes conversion as dependent on future feasibility. It is not current operation or an approved schedule.
Sources [6], [4]Longer-term campus power
200 MW+ claimedHavenz markets the broader mixed-use campus at more than 200 MW. This is a future campus ambition, not the approved Phase 1 data-centre load or current generation.
Sources [4]Grid relationship
Export and interface capability proposedHavenz and Energy Haven discuss future export opportunities and grid-interface capability while describing the campus as off-grid. No AESO connection project, export approval, final substation design, or operating export was verified.
Sources [4], [5], [6]Air emissions and GHGs
Not quantified publiclyNo project-specific public air-quality assessment, annual fuel demand, tonnes CO₂e estimate, or AUC power-plant decision was identified for the current Phase 1 system.
Sources [1], [5]Water
The registry's waterless description does not establish zero site water demand. The County requires confirmation of consumption and use, and the public record does not quantify domestic, fire-protection, process, cooling, wastewater, or make-up water. [3], [1], [4]
Cooling
Waterless design reportedThe provincial registry uses this description. Equipment details and operating water records are not published.
Sources [3]Water demand and source
Confirmation required; volume not publishedThe County requires written confirmation from applicable authorities for project water consumption and use.
Sources [1], [2]Water recycling
Broader campus claimHavenz describes on-site recycling as part of the larger innovation-campus concept. It does not provide a Phase 1 design, balance, or operating result.
Sources [4], [6]Wastewater
Not publicly confirmedNo discharge route, sanitary demand, wastewater volume, treatment design, or agreement was identified in the reviewed sources.
Sources [1]Stormwater
Prior plans referenced as approvedThe County development engineer said access, grading, and stormwater-management plans had been approved under a previous development permit. The report does not reproduce their design or establish operating performance.
Sources [1]Noise
The County summarized the applicant's findings but did not publish the assessment's numerical receptor tables. The approval makes mitigation and later receptor validation enforceable conditions.
Applicant assessment
22 residential properties within 1.5 kmThe County says the assessment included the associated heat and power plant and cumulative noise from nearby regulated facilities, and predicted compliance for day and night. Numerical predictions are not reproduced in the report.
Sources [1]Generator exhaust
Hospital-plus-grade silencers requiredFinal silencer design must be verified and results validated at receptor locations.
Sources [1], [2]Backup generators
Acoustic enclosures requiredThe County condition applies to the 1.5 MW backup generation described in its report.
Sources [1], [2]Indigenous context
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. This section brings together the public record on treaty geography, Indigenous ownership, consultation, and community concerns. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty geography
Near the mapped Treaty 6 / Treaty 7 boundaryGeographic context only. It does not establish consultation, consent, or any community's position.
Sources [7]Equity-partner claim
Turning Stone identified by HavenzHavenz calls Turning Stone an Indigenous equity partner. The reviewed public sources do not identify a Nation or community, ownership percentage, agreement terms, or consultation outcome.
Sources [5]Approval and public process
The October 2025 decision approved a discretionary land use subject to 17 conditions. Permit issuance, building permits, and compliance with other municipal and provincial requirements remain distinct steps.
Approval
Discretionary use approved with 17 conditionsConditions cover approved plans, nuisance, landscaping security, visual screening, noise mitigation, roads, water confirmation, emergency response, remediation, and repair of damaged public property.
Sources [1], [2]Permit transparency
Condition-clearance records not locatedThe County required non-continuing conditions to be met before the development permit could issue or construction could begin. Later sources report construction underway, but ADCW did not locate the issued permits or records showing when the conditions were cleared. This gap does not establish that construction began early.
Sources [1], [5]Road and traffic
Road Use Agreement requiredThe applicant must enter a County-approved road-use agreement. Expansion beyond Phase 1 requires an updated traffic-impact assessment for Highway 2A intersections.
Sources [1], [2]Setbacks and visual impacts
Escarpment setbacks and screening applyThe Blindman plan identifies 30 m escarpment setbacks. Loading, storage, exterior mechanical equipment, and cooling towers must be screened from roads and adjacent sites.
Sources [1]Environmental conditions
Development outside mapped sensitive areaThe County places the buildings outside the Red Deer Canyon Environmentally Significant Area and requires any contamination caused by the applicant to be remediated at the developer's cost.
Sources [1], [2]Timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
What we still don't know
Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.
- The issued development permit, building permit, approved-plan revisions, and satisfaction of pre-construction conditions were not located in the reviewed public record.
- The final data-centre IT load, tenant commitments, server deployment, and operations start are not confirmed.
- No current hydrogen use, hydrogen supply, blend percentage, conversion date, or hydrogen-specific approval was verified.
- The make, unit count, efficiency, annual gas demand, air emissions, greenhouse-gas emissions, and regulatory status of the current power system remain incompletely disclosed.
- No public AESO project, final grid-interface design, export authorization, or operating power export was confidently matched.
- Water demand, source, wastewater arrangements, and the details of the previously approved stormwater plan are not public.
- The numerical noise predictions, receptor table, baseline measurements, and post-construction validation results are not public.
- The identity and terms behind the Turning Stone equity-partner claim and any project-specific Indigenous consultation outcomes are not disclosed.
Source record
Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.
- Request for decision: Data Processing Centre, file D-25-212
Red Deer County · Municipal record · 2025-10-07
- Municipal Planning Commission minutes
Red Deer County · Municipal record · 2025-10-07
- Blindman Industrial Park AI Data Centre
Government of Alberta Major Projects · Government database · Accessed 2026-09-07
- AHI Red Deer Sustainable Innovation Campus
Havenz Smart Communities · Company disclosure · Accessed 2026-09-07
- Construction accelerates at AI data centre near Red Deer
Havenz Smart Communities · Company disclosure · 2026-02-24
- Energy Haven partnership with AHI Red Deer Sustainable Innovation Campus
Energy Haven · Company disclosure · Accessed 2026-09-07
- Treaty Boundary dataset
Government of Canada Open Government Portal · Government database · Modified 2026-06-29