Independent. Publicly sourced. Alberta focused.

See where Alberta's data centre buildout is happening.

Explore an interactive map and verified directory of proposed, approved, under-construction, and operating data centres across Alberta.

ADCW Weekly

WHAT'S NEW

StratGrid Project Wheatland

An SEC-filed Jet.AI disclosure identifies a proposed Wheatland County campus designed around approximately 200 MW of on-site natural-gas generation.

Why it matters: No parcel or public project application has been verified. Published company and investment-material figures differ, so ADCW preserves the approximately 200 MW, 240 MW, and approximately 250 MW claims separately.

View project →

Gayford and Clive record correction

Gayford is now a separate proposed record. AUC proceedings 30385, 30476, and 30709 were removed from Clive and assigned to the 19.95 MW Gayford facility.

Why it matters: The proceedings identify a site near Gayford in Rocky View County. All three applications closed without merits decisions, while the County's proposed master site development plan remains not final.

View project →

eStruxture CAL-3

AUC Proceeding 31020 seeks approval for 21 diesel emergency standby generators totalling 66.75 MW at CAL-3.

Why it matters: The applicant says the generators were procured and installed before the required filing, but had not been tested or operated as of August 28, 2026. The application is not an approval.

View project →

2661707 Alberta Ltd. Greenview sites

Municipal records show eight effective permits for modular data processing centres on existing gas-well footprints. A ninth application remains deferred.

Why it matters: The shared applicant, design, setting, and power model support one distributed-program record. Municipal approval does not confirm construction, provincial land authorization, or operation.

View project →

Project explorer

Data centre projects across Alberta

Verified project dataEvery record with a verifiable site is mapped. Treaty geography is a best-effort match between available boundary information and each project's published location. It provides geographic context only and does not identify affected communities or consultation.

Use +/− or your keyboard to zoom. Hold Ctrl while scrolling, or use two fingers on touchscreens.

Verified records
57
35 active + 19 operating + 3 inactive
Active buildout
35
Used for the forward-looking totals below
Municipalities
27
Across all verified records in 10 Alberta regions
Verified records5735 active + 19 operating + 3 inactivePublished daily water volume13.8 million L/dayFrom 5 of 35 active projects. Includes related power-plant water where published. Not province-wide use.
Transmission lines across a rural landscape at sunset.

Why should I care?

Large data centre campuses create new electricity demand. Meeting it can require dedicated power plants, gas pipelines, substations, cooling systems, and water infrastructure built alongside the server buildings.

Why scale matters →

Why focus on 35 projects? This graphic measures what Alberta may add next: proposed, approved, and under-construction projects. The 19 operating facilities and 3 inactive proposals remain in the full directory, but are excluded here so existing use is not mixed with proposed new demand.

Power

What the new demand could mean

Published data centre demand equals 127% of Alberta's 2025 average electricity demand.

Alberta demand comparison: AESO 2025 Annual Market Statistics.

Read the label, not just the number. Data centre load, grid capacity, and on-site generation describe different things and are tracked separately.

Why scale matters

Alberta's existing data centres are typically measured in megawatts. Some proposed data centre campuses exceed one gigawatt. The difference is not incremental. It is hundreds of times larger.

About 10.5 terawatt-hours (TWh) in one year

If a facility drew 1.2 GW continuously for a year, it would use slightly more electricity than was delivered across Calgary in all of 2025.

This illustrates the proposed maximum at full demand every hour, not the project's expected or actual use.ENMAX reports 9.8 TWh delivered in Calgary in 2025.

One portfolio: 4.5 GW. Beacon's announced six-site Alberta portfolio alone equals about 44% of Alberta's 2025 average demand.

Portfolio announcement, not operating demand or a guarantee that every site will be built.

The data centres are only part of the picture.

Large data centre campuses create new electricity demand. Meeting it can require dedicated power plants, gas pipelines, substations, cooling systems, and water infrastructure built alongside the server buildings.

Putting water demand in human terms

What does 13.8 million L/day mean?

1 m³1,000 L

This total comes from only 5 of 35 active projects.It combines comparable projected or proposed daily water volumes, including water published for related power plants. It is not measured province-wide use.

This comparison uses Alberta's 2021 residential average of 195 litres per person per day, the latest province-wide figure published by Statistics Canada. It compares volume only and does not mean the project water is potable, comes from a municipal system, or is entirely consumed.View the Statistics Canada data.

Read the label, not just the number. Water licensed, withdrawn, consumed, and returned describe different things.

Explore ADCW

Start with the question you have.

Take informed action

Find the right public body, write a focused message, and participate on the official record.

Use the action guide →

About the project

Evidence before rhetoric.

Alberta Data Centre Watch is an independent public-interest project that makes fragmented information about Alberta data centre development easier to find, compare, and understand.

ADCW is not affiliated with any government, regulator, municipality, political party, or project proponent. It tracks material data centre infrastructure across AI, hyperscale, high-performance computing, colocation, cryptocurrency, and other workloads, plus directly related power infrastructure when the connection can be documented. Ordinary internal server rooms fall outside the current scope.

Primary sources come first. Company and government claims are attributed to the people making them. Unknown information stays visible, and every material summary should lead back to an original record.

Read how ADCW verifies Alberta data centre projects →