Project directory

Alberta data centre project list

ADCW brings verified Alberta data centre records into one directory, including projects that companies may describe as Alberta data centers in their own materials. Records are published only after their identity, current status, location precision, and source base have been reviewed.

Publication scope

Verified records, not every lead

Alberta has no single authoritative registry for all data centre development. A missing listing does not prove that a project does not exist. It means ADCW has not yet published a record that meets its evidence standard.

Every record below has a checked public source trail. An evidence profile is the deeper, source-by-source review; a verified listing publishes the confirmed essentials while that fuller review has not yet been completed.

Public records
61
Evidence profiles
21
Verified listings
40
Operating20 projects

Facilities confirmed to be in service. Some may still be expanding or operating below their announced full capacity.

4WEB Edmonton Data Centre

Verified listing

4WEB · City of Edmonton · Commercial colocation

Not disclosed
Alberta grid · EPCOR
Not disclosed
Not disclosedNo project-specific values found
Overview

A small operating northwest Edmonton data centre providing colocation, hosting, backup, and cloud services.

Current status
OperatingOperating local colocation and hosting facility
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-01
Location precision
Exact operator-listed address
Treaty geography
Treaty 6 territory
In service since
January 2008

Power source: Alberta interconnected grid through EPCOR's Edmonton distribution system; 4WEB discloses a three-phase utility feed.

Backup power: Operator-listed backup equipment includes a 130 kW generator connected by automatic transfer switch and an 80 kW APC UPS. These equipment ratings are not facility capacity.

Cologix CGY1

Verified listing

Cologix · City of Calgary · Commercial colocation

400 kW facility capacity
Alberta grid · ENMAX
Fault-tolerant air conditioning with N+1 redundancy
Not disclosedNo project-specific values found
Overview

An operating downtown carrier-neutral interconnection facility formerly known as DataHiveOne.

Current status
OperatingOperating carrier hotel acquired from DataHive in October 2025
Capacity context
400 kW facility capacityOperator-listed capacity for the current facility.
Cooling and water
Fault-tolerant air conditioning with N+1 redundancyCologix says temperature, airflow, and humidity are monitored and regulated. It does not identify the heat-rejection method or disclose routine cooling-water use.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-01
Location precision
Exact operator-listed address
Treaty geography
Treaty 7 territory
In service since
Not publicly confirmed

Federal principles: Cologix is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Power source: Alberta interconnected grid through ENMAX Power's Calgary distribution system, based on the published facility address.

DataHiveTwo

Verified listing

DataHive · City of Calgary · Commercial colocation

Not disclosed
Alberta grid · ENMAX
Not disclosed
Not disclosedNo project-specific values found
Overview

An operating downtown Calgary facility offering private cloud, colocation, security, and archival data services.

Current status
OperatingOperating downtown data centre retained by DataHive after the sale of DataHiveOne
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-07-31
Location precision
Exact operator-listed address
Treaty geography
Treaty 7 territory
In service since
Not publicly confirmed

Power source: Alberta interconnected grid through ENMAX Power's Calgary distribution system, based on the published facility address.

Equinix Calgary CL1

Verified listing

Equinix · City of Calgary · Commercial colocation

Not disclosed
Alberta grid · ENMAX
N+20% cooling redundancy
Not disclosedNo project-specific values found
Overview

An operating Equinix interconnection and colocation facility in downtown Calgary.

Current status
OperatingOperating carrier-neutral colocation facility
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
N+20% cooling redundancyEquinix discloses cooling redundancy but not the equipment type, heat-rejection method, or routine cooling-water use on the CL1 facility page.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-01
Location precision
Exact operator-listed address
Treaty geography
Treaty 7 territory
In service since
Not publicly confirmed

Federal principles: Equinix is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Power source: Alberta interconnected grid through ENMAX Power's Calgary distribution system, based on the published facility address.

Equinix Calgary CL2

Verified listing

Equinix · City of Calgary · Commercial colocation

Not disclosed
Alberta grid · ENMAX
Free cooling with N+2 redundancy
Not disclosedNo project-specific values found
Overview

An operating Equinix interconnection and colocation facility on Maynard Road in Calgary.

Current status
OperatingOperating carrier-neutral colocation facility
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Free cooling with N+2 redundancyEquinix lists free cooling but does not identify the heat-rejection design or disclose routine cooling-water use on the CL2 facility page. Free cooling does not by itself establish waterless operation.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-01
Location precision
Exact operator-listed address
Treaty geography
Treaty 7 territory
In service since
Not publicly confirmed

Federal principles: Equinix is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Power source: Alberta interconnected grid through ENMAX Power's Calgary distribution system, based on the published facility address.

Equinix Calgary CL3

Verified listing

Equinix · City of Calgary · Commercial colocation

Not disclosed
Alberta grid · ENMAX
Free cooling with N+1 redundancy
Not disclosedNo project-specific values found
Overview

An operating Equinix interconnection and colocation facility in southeast Calgary.

Current status
OperatingOperating carrier-neutral colocation facility
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Free cooling with N+1 redundancyEquinix also lists hot/cold-aisle containment, efficient humidity control, and decoupled dehumidification. It does not identify the heat-rejection design or disclose routine cooling-water use on the CL3 facility page.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-01
Location precision
Exact operator-listed address
Treaty geography
Treaty 7 territory
In service since
Not publicly confirmed

Federal principles: Equinix is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Power source: Alberta interconnected grid through ENMAX Power's Calgary distribution system, based on the published facility address.

eStruxture CAL-1

Verified listing

eStruxture Data Centers · City of Calgary · Commercial colocation

9 MW facility capacity
Alberta grid · ENMAX
Redundant cooling modules with hot/cold-aisle containment
Not disclosedNo project-specific values found
Overview

An operating high-density, Tier III certified commercial colocation facility in southeast Calgary.

Current status
OperatingOperating carrier-neutral colocation facility
Capacity context
9 MW facility capacityCurrent operator-listed facility capacity.
Cooling and water
Redundant cooling modules with hot/cold-aisle containmenteStruxture describes high-density redundant cooling modules, raised-floor airflow design, and N+1 cooling. It does not identify the heat-rejection method or disclose routine cooling-water use.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-01
Location precision
Exact operator-listed address
Treaty geography
Treaty 7 territory
In service since
2015 (first data hall)

Federal principles: eStruxture is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Power source: Alberta interconnected grid through ENMAX Power's Calgary distribution system, based on the published facility address.

eStruxture CAL-2

Verified listing

eStruxture Data Centers · Rocky View County · Commercial colocation

26 MW current capacity
Alberta grid · Multiple feeds
Waterless free cooling
No receptor value published12 MW backup plant approved
Overview

An operating Tier III designed commercial colocation facility in the Balzac area.

Current status
OperatingOperating carrier-neutral colocation facility
Capacity context
26 MW current capacityThe current operator page lists 26 MW; the 2023 opening announcement described a 30 MW design.
Cooling and water
Waterless free coolingThe operator says the cooling system does not consume water for routine heat rejection.
Noise details
No receptor value publishedAUC Decision 27614-D01-2022 approved CAL-2's 12 MW diesel backup plant, consisting of four generators intended for monthly testing and outages. ADCW did not identify a published project-specific receptor prediction or operating measurement in the August 29 review.
Verified
2026-07-31
Location precision
Exact operator-listed address
Treaty geography
Treaty 7 territory
In service since
2023

Federal principles: eStruxture is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Power source: Alberta interconnected grid through multiple utility feeds; the operator does not publicly name the local wires provider, retailer, or generating plant.

Fire Technology Torrington Cryptomining Facility

Verified listing

Fire Technology Corp. · Kneehill County · Cryptocurrency / Bitcoin mining

9.5 MW facility name in Alberta's carbon registry
The original municipal approval paired the cryptocurrency-mining facility with micropower generation. Public records reviewed by ADCW do not establish the current generator configuration, fuel use, or measured electricity consumption.
Not disclosed
Not disclosedNo project-specific values found
Overview

An operating 9.5 MW cryptomining facility near Torrington. Its 2022 municipal approval covered micropower generation and cryptocurrency mining, and an April 2026 permit added two units to the existing data centre.

Current status
OperatingKneehill County approved two additional units in April 2026 for the existing data centre; the provincial carbon registry lists the 9.5 MW cryptomining facility
Capacity context
9.5 MW facility name in Alberta's carbon registryThe registry identifies the facility as the Torrington 9.5 MW cryptomining facility. This is a registered facility label, not a measurement of continuous electricity use.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-16
Location precision
Legal subdivision midpoint (ATS)
Treaty geography
Treaty 7 territory
In service since
Not publicly confirmed

Original municipal file: Permit 4010-22-D covered a micropower-generation and cryptocurrency-mining facility at SE 28-32-26-W4M.

2026 expansion: Kneehill County's April 2026 approvals list APPN-2026-0020 for two additional units at the existing data centre.

Registry evidence: Alberta's carbon registry lists the facility at LSD 8-28-32-26-W4M and shows 2023 emissions-performance credits. The registry does not establish the present number of mining units or operating load.

Power source: The original municipal approval paired the cryptocurrency-mining facility with micropower generation. Public records reviewed by ADCW do not establish the current generator configuration, fuel use, or measured electricity consumption.

Hut 8 Drumheller

Evidence profile

Hut 8 Corp. · Drumheller · Cryptocurrency / ASIC compute

42 MW listed site capacity
The current public sources identify the site capacity but do not publish its present electricity contract, supply mix or site-specific emissions.
Not disclosed in the reviewed current sources
Not disclosedNo project-specific values found
Overview

Hut 8's 42 MW Drumheller ASIC-compute facility, returned to service in March 2026 after a two-year shutdown.

Current status
OperatingRe-energized in March 2026 and operating as ASIC colocation
Capacity context
42 MW listed site capacityHut 8 lists 42 MW for Drumheller. This is site capacity, not a measurement of continuous electricity use.
Cooling and water
Not disclosed in the reviewed current sourcesADCW did not find a current public figure for cooling-water withdrawal, consumption or discharge.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-21
Location precision
Municipality centre
Treaty geography
Treaty 7 territory
In service since
Not publicly confirmed

Power source: The current public sources identify the site capacity but do not publish its present electricity contract, supply mix or site-specific emissions.

Hut 8 Medicine Hat

Evidence profile

Hut 8 Corp. · Medicine Hat · Cryptocurrency / ASIC compute

67 MW listed site capacity
The facility was developed with municipal electricity supply
Not disclosed in the reviewed current sources
Not disclosedNo project-specific values found
Overview

Hut 8's operating 67 MW Medicine Hat data centre, where American Bitcoin operates Bitcoin miners under Hut 8 service agreements.

Current status
OperatingOperating ASIC-compute facility listed by Hut 8 at 67 MW
Capacity context
67 MW listed site capacityHut 8 lists 67 MW for Medicine Hat. This is site capacity, not a measurement of continuous electricity use.
Cooling and water
Not disclosed in the reviewed current sourcesADCW did not find a current public figure for cooling-water withdrawal, consumption or discharge.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-22
Location precision
Exact site
Treaty geography
Treaty 7 territory
In service since
2018

Power source: The facility was developed with municipal electricity supply; current site-specific supply terms and electricity mix were not found in the reviewed sources.

Qu Calgary CGY1

Verified listing

Qu Data Centres · City of Calgary · Commercial colocation

2.6 MW utility capacity
Alberta grid · ENMAX
Powered mechanical cooling with one redundant unit (N+1)
Not disclosedNo project-specific values found
Overview

An operating 25,649-square-foot carrier-neutral Qu facility serving Calgary enterprise workloads.

Current status
OperatingOperating commercial colocation facility
Capacity context
2.6 MW utility capacityCurrent utility capacity disclosed by Qu, not measured electricity consumption.
Cooling and water
Powered mechanical cooling with one redundant unit (N+1)Capacity: 510 refrigeration tons. Qu does not identify the heat-rejection method or disclose routine cooling-water use in the facility spec sheet.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-07-31
Location precision
Exact address corroborated by industry directories
Treaty geography
Treaty 7 territory
In service since
Not publicly confirmed

Power source: Utility power from Alberta's interconnected grid through ENMAX Power's Calgary distribution system.

Backup power: One 1.5 MW and one 2 MW generator (3.5 MW combined nameplate), with on-site fuel for 24 hours at full load.

Qu Calgary CGY2

Verified listing

Qu Data Centres · City of Calgary · Commercial colocation

1.8 MW utility capacity
Alberta grid · ENMAX
Powered mechanical cooling with one redundant unit (N+1)
Not disclosedNo project-specific values found
Overview

An operating 39,470-square-foot Qu facility in downtown Calgary.

Current status
OperatingOperating commercial colocation facility
Capacity context
1.8 MW utility capacityQu says the utility capacity is upgradeable to 6 MW. These are capacity figures, not measured electricity consumption.
Cooling and water
Powered mechanical cooling with one redundant unit (N+1)Capacity: 960 refrigeration tons. Qu does not identify the heat-rejection method or disclose routine cooling-water use in the facility spec sheet.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-07-31
Location precision
Exact address corroborated by industry directories
Treaty geography
Treaty 7 territory
In service since
Not publicly confirmed

Power source: Utility power from Alberta's interconnected grid through ENMAX Power's Calgary distribution system.

Backup power: Ten 375 kW generators, including one redundant unit beyond the required capacity (N+1). Combined nameplate capacity is 3.75 MW, with on-site fuel for 24 hours at full load.

Qu Calgary CGY3

Verified listing

Qu Data Centres · City of Airdrie · AI-ready colocation

9 MW full-design capacity
Alberta grid · FortisAlberta
Powered mechanical cooling with one redundant unit (N+1)
Not disclosedNo project-specific values found
Overview

Qu's operating 80,000-square-foot Airdrie facility, built for high-density AI, HPC, and enterprise workloads.

Current status
OperatingOperating Tier III certified colocation facility with AI and high-density workload support
Capacity context
9 MW full-design capacityQu's expandable full-design capacity, not measured electricity consumption.
Cooling and water
Powered mechanical cooling with one redundant unit (N+1)Capacity: 1,450 refrigeration tons. Qu does not identify the heat-rejection method or disclose routine cooling-water use in the facility spec sheet.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-07-31
Location precision
Exact address corroborated by industry directories
Treaty geography
Treaty 7 territory
In service since
Not publicly confirmed

Power source: Utility power from Alberta's interconnected grid through FortisAlberta's Airdrie distribution system.

Backup power: Two 1 MW and two 2 MW generators, with one redundant unit beyond the required capacity (N+1). Combined nameplate capacity is 6 MW, with on-site fuel for 24 hours at full load.

Qu Edmonton EDM1

Verified listing

Qu Data Centres · City of Edmonton · Commercial colocation

2.5 MW facility capacity
Alberta grid · EPCOR
Powered mechanical cooling with one redundant unit (N+1)
Not disclosedNo project-specific values found
Overview

An operating 18,000-square-foot downtown Edmonton colocation facility. Wolfpaw markets a dedicated restricted-access suite here as Wolfpaw EDM2.

Current status
OperatingOperating commercial colocation facility in Edmonton's financial core
Capacity context
2.5 MW facility capacityCurrent capacity disclosed by Qu, not measured electricity consumption.
Cooling and water
Powered mechanical cooling with one redundant unit (N+1)Capacity: 248 refrigeration tons. Qu does not identify the heat-rejection method or disclose routine cooling-water use in the facility spec sheet.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-14
Location precision
Exact address corroborated by industry directories
Treaty geography
Treaty 6 territory
In service since
Not publicly confirmed

Power source: Utility power from Alberta's interconnected grid through EPCOR's Edmonton distribution system.

Backup power: Three 1 MW generators, including one redundant unit beyond the required capacity (N+1). Combined nameplate capacity is 3 MW, with on-site fuel for 24 hours at full load.

Qu Edmonton EDM2

Verified listing

Qu Data Centres · City of Edmonton · AI-ready colocation

3 MW Tier III capacity
Alberta grid · EPCOR
Powered mechanical cooling with one redundant unit (N+1)
Not disclosedNo project-specific values found
Overview

Qu's larger Edmonton facility, with 35,000 square feet across two expandable phases. Wolfpaw markets a dedicated restricted-access suite here as Wolfpaw EDM3.

Current status
OperatingOperating Tier III certified colocation facility with AI and high-density workload support
Capacity context
3 MW Tier III capacityQu also lists 2.5 MW at Tier II. These are capacity figures, not measured electricity consumption.
Cooling and water
Powered mechanical cooling with one redundant unit (N+1)Capacity: 1,450 refrigeration tons. Qu does not identify the heat-rejection method or disclose routine cooling-water use in the facility spec sheet.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-14
Location precision
Exact address corroborated by industry directories
Treaty geography
Treaty 6 territory
In service since
Not publicly confirmed

Power source: Utility power from Alberta's interconnected grid through EPCOR's Edmonton distribution system.

Backup power: Five 1 MW generators across two phases, with one redundant unit beyond the required capacity in each phase (N+1). Combined nameplate capacity is 5 MW. The spec sheet does not disclose fuel autonomy.

The Internet Centre

Verified listing

The Internet Centre Canada Inc. · City of Edmonton · Commercial colocation

Not disclosed
Alberta grid · EPCOR
Not disclosed
Not disclosedNo project-specific values found
Overview

An independently owned 3,000-square-foot south Edmonton data centre offering colocation, cloud hosting, and connectivity services.

Current status
OperatingOperating locally owned colocation and hosting facility
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-14
Location precision
Exact operator-listed address
Treaty geography
Treaty 6 territory
In service since
Not publicly confirmed

Power source: Alberta interconnected grid through EPCOR's Edmonton distribution system, based on the published facility address.

Backup power: The operator confirms redundant power systems but does not publish equipment ratings or fuel autonomy.

ThinkTel Edmonton

Verified listing

ThinkTel Communications · City of Edmonton · Commercial colocation

Not disclosed
Alberta grid · EPCOR
Redundant HVAC climate control
Not disclosedNo project-specific values found
Overview

An operating downtown Edmonton colocation facility offering server housing, power, bandwidth, and connectivity services.

Current status
OperatingOperating telecommunications and colocation facility
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Redundant HVAC climate controlThinkTel does not disclose Edmonton-specific cooling equipment or routine water use.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-14
Location precision
Exact address corroborated by current industry directories
Treaty geography
Treaty 6 territory
In service since
Not publicly confirmed

Power source: Alberta interconnected grid through EPCOR's Edmonton distribution system, based on the published facility address.

Backup power: ThinkTel says its colocation service includes generator-backed redundant power. Edmonton-specific equipment and fuel autonomy are not publicly disclosed.

Whipcord LDC01

Verified listing

Whipcord Edge · City of Lethbridge · Commercial colocation

2.5 MW original Phase 1 utility power
Alberta grid · Lethbridge
Chilled-glycol system with chillers and dry coolers
Not disclosedNo project-specific values found
Overview

Whipcord's operating Alberta data centre in Lethbridge, distinct from its Calgary network point of presence.

Current status
OperatingOperating Tier III designed colocation and managed-infrastructure facility
Capacity context
2.5 MW original Phase 1 utility powerWhipcord's facility specification lists 2.5 MW for Phase 1. It also identifies a future additional 2.5 MW Phase 2, but ADCW has not confirmed that expansion or the site's current total capacity.
Cooling and water
Chilled-glycol system with chillers and dry coolersThe original facility specification lists two 160-ton Daikin/McQuay chillers, two dry coolers, in-row cooling, and hot-aisle containment. It does not disclose routine water use.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-01
Location precision
Exact address corroborated by network registries
Treaty geography
Treaty 7 territory
In service since
June 2011 (original facility completion)

Power source: Whipcord's original facility specification lists 2.5 MW of City of Lethbridge utility power for Phase 1. It identifies another 2.5 MW as a future Phase 2, which ADCW has not confirmed as completed or current capacity.

Backup power: The original Phase 1 specification lists one 1.5 MW Cummins generator and two 800 kW APC Symmetra MW UPS units in a 2(N+1) arrangement. Current equipment configuration has not been independently confirmed.

Wolfpaw EDM1

Verified listing

Wolfpaw Data Centres Inc. · City of Edmonton · Commercial colocation

Not disclosed
Alberta grid · EPCOR
Fully redundant HVAC
Not disclosedNo project-specific values found
Overview

Wolfpaw's independently operated downtown Edmonton facility, connected by dark fibre to its restricted suites within Qu's two Edmonton data centres.

Current status
OperatingOperating Wolfpaw-owned colocation facility
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Fully redundant HVACWolfpaw does not disclose EDM1's heat-rejection method or routine cooling-water use.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-14
Location precision
Exact address corroborated by current industry directories
Treaty geography
Treaty 6 territory
In service since
Not publicly confirmed

Power source: Alberta interconnected grid through EPCOR's Edmonton distribution system, based on the published facility address.

Backup power: Wolfpaw lists redundant UPS backup and on-site backup generation for EDM1. Equipment ratings and fuel autonomy are not fully disclosed in current operator materials.

Under construction4 projects

Projects with physical construction confirmed. Announced capacity and completion dates may still change by phase.

AHI Red Deer / Blindman Industrial Park AI Data Centre

Evidence profile

Havenz Smart Communities · Red Deer County · AI / High-performance computing

10 MW Phase 1 on-site generation
10 MW Phase 1 on-site generation using natural gas. Future hydrogen blending is proposed, not current operation.
Waterless cooling design reported in the provincial project listing
22 receptors assessedValues not published
Overview

A Phase 1 modular AI data centre on a roughly 120-acre Blindman Industrial Park parcel. The first 10 MW power block is being built around natural-gas-fuelled, hydrogen-ready engines; hydrogen blending and conversion remain future plans.

Current status
Under constructionRed Deer County approved the discretionary use on October 7, 2025, subject to conditions. Havenz says Phase 1 construction is underway, and the provincial registry lists the project as under construction
Capacity context
10 MW Phase 1 on-site generationHavenz describes the first power block as 10 MW. It is on-site generation capacity for the initial modular build, not a verified data-centre IT load.
Cooling and water
Waterless cooling design reported in the provincial project listingThe provincial registry describes a waterless design, while the County requires written confirmation of water consumption and use. No project-specific demand, source, wastewater volume, or operating water record has been published.
Noise details
22 receptors assessedThe County report says the applicant's assessment considered 22 residential properties within 1.5 km and predicted compliance with AUC Rule 012. The approval requires hospital-plus-grade exhaust silencers, acoustic enclosures for the 1.5 MW backup generators, and validation at receptor locations. Numerical tables were not included in the public report.
Verified
2026-09-07
Location precision
Exact site
Treaty geography
Near the mapped Treaty 6 / Treaty 7 boundary

Phase 1 footprint: A 1,000 m² (10,765 sq. ft.) modular data centre and a 471 m² (5,071 sq. ft.) administration building.

Environmental siting: Part of the parcel overlaps the Red Deer Canyon Environmentally Significant Area, but the County report places the development outside that area and the escarpments.

Traffic condition: A new traffic-impact assessment is required if development expands beyond Phase 1.

Bitdeer Fox Creek

Evidence profile

Bitdeer Technologies Group · Municipal District of Greenview No. 16 · Cryptocurrency / HPC-capable

Approximately 100 MW computing capacity
Direct supply from an approved 101.133 MW on-site natural-gas plant, with a 99 MW AESO grid interconnection.
Closed-loop dry cooling proposed
Values not publishedPreliminary studies disclosed
Overview

An approximately 100 MW computing facility under construction near Fox Creek, paired with a 101.133 MW natural-gas power plant.

Current status
Under constructionPower-plant construction began in June 2026; latest company schedule targets Q4 2027 energization
Capacity context
Approximately 100 MW computing capacityBitdeer currently lists cryptocurrency as the planned use while designing the facility to accommodate both cryptocurrency and AI data centre workloads.
Cooling and water
Closed-loop dry cooling proposedBitdeer says the project will not withdraw water from nearby surface-water bodies; other construction and facility water volumes are not disclosed.
Noise details
Values not publishedBitdeer says preliminary studies are guiding design toward Alberta nighttime limits and promises active monitoring after operations begin. It has not published receptor predictions or monitoring results.
Verified
2026-08-23
Location precision
Approximate area
Treaty geography
Treaty 8 territory

Site area: 7.7 hectares (19 acres)

Latest planned use: Cryptocurrency, with a design intended to accommodate AI data centre workloads

eStruxture CAL-3

Evidence profile

eStruxture Data Centers · Rocky View County · AI-ready colocation

90 MW total facility power
Alberta grid · FortisAlberta
Closed-loop water-based air and direct-to-chip liquid cooling
43–45 dBAModelled nighttime normal operation
Overview

A 90 MW total-power, 70 MW critical-power AI-ready colocation facility under construction in Rocky View County.

Current status
Under constructionUnder construction at 200 High Plains Common; eStruxture targets fall 2026 service and names CoreWeave as the Phase 1 anchor tenant
Capacity context
90 MW total facility powereStruxture's current data sheet lists 90 MW of total power and 70 MW of critical power. The 90 MW figure is design capacity, not measured operating demand.
Cooling and water
Closed-loop water-based air and direct-to-chip liquid coolingeStruxture says it has moved away from public water for cooling, but CAL-3 withdrawal, fill, top-up, consumption, and discharge volumes are not published.
Noise details
43–45 dBAA March 20, 2025 assessment predicted 43–45 dBA at four residential receptors during normal operation and 47–53 dBA during daytime generator testing. It modelled an earlier 72-generator design. The current 21-generator application claims a lower cumulative sound level but does not provide a new receptor table. These are modelled values, not operating measurements or an AUC finding.
Verified
2026-09-14
Location precision
Exact site
Treaty geography
Treaty 7 territory

Phase 1 building: 205,000 sq. ft., including 51,750 sq. ft. of data-hall whitespace across six halls.

Announced investment: More than CA$750 million for the full CAL-3 build, according to eStruxture and Alberta Major Projects.

Anchor tenant: CoreWeave has committed to an undisclosed portion of Phase 1; eStruxture separately says first-phase capacity is sold out.

AUC proceeding: Proceeding 31020 seeks approval for already-installed emergency standby generators; the filing is not an approval or operating authorization.

Federal principles: eStruxture is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

K-Tech and Aurora AZ Energy Compute Facility

Verified listing

K-Tech Solutions / Aurora AZ Energy · City of Calgary · Mixed AI / High-density compute

5 MW proof of concept under construction
Dedicated wellhead natural-gas generation supplied by Aurora. The parties say the model may use gas that would otherwise be flared, but project-specific fuel volumes and emissions are not disclosed.
Not disclosed
Not disclosedNo project-specific values found
Overview

A reported 5 MW Alberta proof of concept combining wellhead natural-gas generation with AI, high-performance, and cryptocurrency computing. The exact site has not been publicly identified.

Current status
Under constructionK-Tech reported construction and on-site testing in progress on a 5 MW proof of concept; the 100 MW flagship plan and potential 500 MW expansion remain prospective
Capacity context
5 MW proof of concept under constructionK-Tech's June 2026 SEC filing says construction and on-site technical testing are in progress on the first 5 MW. This is the only portion currently identified as under construction.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-23
Location precision
Calgary-level marker; exact site undisclosed
Treaty geography
Treaty 7 territory

Current construction: K-Tech reported a 5 MW proof of concept under construction and undergoing on-site technical testing in June 2026.

Published roadmap: A 100 MW flagship site, with potential expansion toward 500 MW across additional power and land.

Joint venture ownership: The supplemental agreement assigns 75% of the proposed joint venture to K-Tech and 25% to Aurora.

Who is responsible for what: Aurora is responsible for the sites, land rights, wellhead generation, gas handling, electrical infrastructure, and related permits. K-Tech is responsible for data centre design, construction management, computing equipment, and operations.

Approved5 projects

Projects with a major approval in place, but not yet confirmed as under construction. Other permits may still be required.

2661707 Alberta Ltd. Greenview Data Processing Centres

Verified listing

2661707 Alberta Ltd. · Municipal District of Greenview No. 16 · AI / General-purpose computing

Kaybob North area, M.D. of Greenview No. 16
Not disclosed
Proposed on-site natural-gas generation at each location. Greenview's March 2026 reports describe each generator as less than 1 MW
Not disclosed
Not disclosedEight approved sites; one deferred
Overview

Greenview approved eight modular data processing centres for 2661707 Alberta Ltd. on existing gas-well footprints in the Kaybob North area. ADCW groups them as one distributed-compute program because the applicant, facility design, setting, and power model are shared. A ninth application, D25-183, remains deferred.

Current status
ApprovedEight discretionary municipal development permits are effective; a ninth application is deferred, and construction, provincial land authorization, Safety Codes permits, and operation remain unconfirmed
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedGreenview's permit conditions require compliance with municipal noise rules, but the reviewed records do not publish predicted receptor levels or a project-specific noise assessment. D25-183 was deferred while Council requested more information, including noise levels and impacts on recreational users.
Verified
2026-09-13
Location precision
Multiple legal land descriptions; no single representative map point
Treaty geography
Treaty 8 territory

Effective permits: D25-175 at SE-20-64-19-W5M, D25-176 at SW-35-64-19-W5M, D25-177 at SE-16-64-20-W5M, D25-178 at NE-14-64-20-W5M, and D25-179 at NE-24-64-20-W5M became effective March 4, 2026. D25-180 at NW-06-65-18-W5M, D25-181 at NW-01-65-19-W5M, and D25-182 at NW-19-64-19-W5M became effective April 1, 2026.

Deferred application: D25-183 at NW-23-64-19-W5M was deferred on March 11, 2026, pending more information on environmental impacts, noise levels, impacts on recreational users, and circulation to other users such as trap-line holders. ADCW found no later decision in the reviewed 2026 Greenview meeting records.

Shared design: Municipal reports describe modular facilities using a 40-foot server container and a 40-foot natural-gas generator container within existing disturbed gas-well sites for artificial-intelligence and general-purpose computing.

Approval limits: The municipal permits do not establish that construction or operation has started. The applicant remains responsible for Safety Codes permits and other provincial authorizations. Greenview's reports say Alberta Forestry and Parks was not accepting Public Lands Act applications for this activity while provincial policy work was underway.

Athill Carbon-Area Data Centre

Verified listing

Athill Tech Solution Ltd. · Kneehill County · Data centre / Workload undisclosed

9.97 MW approved natural-gas generation
AUC Approval 29239-D02-2024 authorizes a 9.97 MW natural-gas power plant. The record establishes generation capacity, not the data centre's computing load or continuous electricity use.
Not disclosed
Not disclosedNo project-specific values found
Overview

An approved data-centre development approximately 10 kilometres southwest of Carbon, paired with a 9.97 MW natural-gas power plant. The newest AUC decision records construction underway in 2025, but ADCW did not find a current commissioning or operating notice.

Current status
ApprovedMunicipal and AUC approvals are documented; Athill reported construction underway in June 2025, but current construction or operating status is not confirmed
Capacity context
9.97 MW approved natural-gas generationThe AUC approved the power plant and later extended its construction deadline to November 30, 2025. ADCW found no newer direct evidence confirming completion or operation.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-16
Location precision
Legal quarter-section midpoint (ATS)
Treaty geography
Treaty 7 territory

Municipal approval: Kneehill County approved file 4152-24-D for a power plant and data centre on part of SE 24-28-24-W4M in April 2024.

AUC record: Proceeding 30144 extended the construction deadline for facilities first approved in Proceeding 29239. Athill said pipeline work, civil work, fencing, and equipment procurement were substantially advanced in June 2025.

What remains unknown: The data-centre workload and electrical load, final commissioning date, and current operating status are not confirmed in the reviewed direct sources.

Fire Technology Ewing Lake Data Processing Centre

Verified listing

Fire Technology Corp. · County of Stettler No. 6 · Cryptocurrency / Bitcoin mining

9.9 MW conditionally approved on-site generation
Nine proposed natural-gas generator sets totalling 9.9 MW would serve nine on-site Bitcoin-mining containers. The permit is municipal approval, not evidence the equipment was installed or commissioned.
Not disclosed
36.0 to 37.0 dBA cumulative at three existing residencesModelled, not measured operation
Overview

A conditionally approved 9.9 MW gas-powered Bitcoin-mining development at Ewing Lake. The County approved nine generators and nine mining containers in December 2024, but ADCW did not find current evidence that construction or operation began.

Current status
ApprovedDevelopment Permit DP 24097 conditionally approved nine generators and nine Bitcoin-mining containers; current construction and operating status are not confirmed
Capacity context
9.9 MW conditionally approved on-site generationCounty permit DP 24097 authorizes nine gas-driven generator sets and nine Bitcoin-mining containers. Construction and operation remain unconfirmed.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
36.0 to 37.0 dBA cumulative at three existing residencesThe permit package's noise assessment predicts 36.0 to 37.0 dBA cumulative sound at three existing residences under the proposed configuration. Permit conditions require post-construction and twice-yearly third-party assessments if the facility becomes operational.
Verified
2026-09-16
Location precision
Legal quarter-section midpoint (ATS)
Treaty geography
Treaty 6 territory

Permit term: The data-processing use expires on December 18, 2029. That expiry does not confirm that construction or operation began.

Current-status boundary: The reviewed public record contains the approval and applicant assessment, but no notice confirming construction, commissioning, or operation.

Pathfinder Rocky 5 Bitcoin Mining Project

Verified listing

Pathfinder Energy Ltd. under court-appointed receivership · Clearwater County · Cryptocurrency / Bitcoin mining

60 MW approved natural-gas generation
The AUC approval covers fifty 1.2 MW natural-gas generators for 60 MW total. Ten megawatts had been installed when Pathfinder sought its 2025 extension
Not disclosed
Operating measurement not foundAUC approval conditions
Overview

A 60 MW approved gas-powered Bitcoin-mining project near Rocky Mountain House. The AUC recorded 10 MW installed in 2025, but Pathfinder and MCK later entered receivership, and ADCW did not find current evidence that the compute facility remains active.

Current status
ApprovedAUC approval remains documented, but Pathfinder and MCK entered receivership in October 2025; current ownership, construction, and operating status are unresolved
Capacity context
60 MW approved natural-gas generationApproval 29846-D02-2025 authorizes fifty 1.2 MW generators. This is approved generation capacity, not evidence of completed construction or operating load.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Operating measurement not foundThe approval requires specified mitigation and a comprehensive post-construction sound survey, including low-frequency noise at two residences, within one year after operations begin. ADCW did not find a current operating survey.
Verified
2026-09-16
Location precision
Legal half-section midpoint (ATS)
Treaty geography
Treaty 6 territory

Receivership: A court-appointed receiver took control of Pathfinder Energy Ltd. and MCK Energy Inc. effective October 15, 2025. The receiver's sale and investment process includes the companies' assets and operations.

Current-status boundary: The AUC approval is not transferable without Commission approval. ADCW did not find a current ownership transfer, construction-completion notice, or evidence that Bitcoin-mining operations continue.

Sturgeon Data Centre

Evidence profile

Meta Platforms, Inc. · Sturgeon County · Hyperscale / AI

1 GW announced data centre capacity
250 MW Capital Power supply agreement, plus an approved 932 MW dedicated natural-gas plant planned for later service.
Closed-loop liquid cooling with dry cooling
50.4 day / 43.1 night dBAModelled at residence; power plant only
Overview

Meta's first Canadian data centre: an approved 1 GW AI-focused project whose master permit is now before the Land and Property Rights Tribunal.

Current status
ApprovedMaster site development permit effective; preliminary appeal proceeding underway; site preparation reported
Capacity context
1 GW announced data centre capacityMeta announces 1 GW. Clark Builders reports approximately 1.6 GW of compute capacity; the difference is unresolved. ADCW retains Meta's figure, not a measured operating load.
Cooling and water
Closed-loop liquid cooling with dry coolingMeta says no water will be used for routine cooling; other facility water needs remain.
Noise details
50.4 day / 43.1 night dBAGreenlight's filed Rule 012 model predicts 50.4 dBA daytime and 43.1 dBA nighttime cumulative sound at the only residence within 1.5 km of the power-plant boundary. Meta's data-centre equipment is not separately quantified.
Verified
2026-09-19
Location precision
Approximate area
Treaty geography
Treaty 6 territory

Builder-reported project size: Clark Builders lists 2.9 million sq. ft. This is a company disclosure, not confirmation of the approved building area or final campus footprint.

Site work: Clark Builders reports early planning, purchasing, crew and equipment mobilization, and site preparation. Main facility construction is not confirmed by this disclosure.

Associated power-plant ownership: Greenlight is owned by Pembina (47.5%), Morgan Stanley Infrastructure Partners (47.5%), and Kineticor (5%).

Associated power-plant cost: Greenlight reports an approximately CA$4.0 billion capital-cost estimate and an approximately CA$4.6 billion total project cost including CA$0.6 billion in interest during construction and other financing costs.

County development principles: Sturgeon County has published seven principles covering dedicated power, minimized water use, no municipal incentives, developer-funded infrastructure, heavy-industrial locations, reduced community impacts, and expected annual public reporting. The page does not identify every principle as a condition of this project's permit.

Annual public reporting: The County expects operators to report water use, noise levels, and nitrogen oxide emissions each year. This is a published expectation, not confirmation that reports exist or that it is an enforceable permit condition.

Federal principles: Meta is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Proposed29 projects

Projects that are announced, in planning, consulting, or under review. A proposal is not permission to build.

Armada Nowlit Wabasca / Hoole Data Centre

Evidence profile

Armada Nowlit Energy Ltd. · Municipal District of Opportunity No. 17 · Cryptocurrency mining

19.8 MW on-site natural-gas generation under AUC review
A 19.8 MW behind-the-fence natural-gas facility is under AUC review. The application proposes no Alberta Interconnected Electric System connection or power export.
Closed-loop cooling proposed
35.6 dBA vs 40 dBA limitFull-build nighttime model at 1,500 m
Overview

Armada Nowlit proposes nine co-located data-centre units supplied by a 19.8 MW behind-the-fence natural-gas power facility near Hoole. The municipal development permit has been issued, while the AUC power-plant application and required Crown-land disposition remain unresolved.

Current status
ProposedDevelopment Permit 26-DP-001 issued; AUC Proceeding 31058 and the required Crown-land disposition remain unresolved
Capacity context
19.8 MW on-site natural-gas generation under AUC reviewApplication 31058-A001 proposes nine 2.2 MW engines in two phases. This is proposed generation capacity for co-located data infrastructure, not an approved plant or a measured data-centre load.
Cooling and water
Closed-loop cooling proposedThe application says the cooling system would not withdraw or discharge process water. Other site water needs and any separate Water Act approvals remain distinct.
Noise details
35.6 dBA vs 40 dBA limitThe full-build model predicts cumulative nighttime sound of 35.3 to 35.6 dBA at theoretical 1,500 m receptors, below the 40 dBA permissible level. These are not operating measurements at nearby communities. The report's conclusion conflicts with its tables on possible low-frequency tonality: the tables show differences of about 21 to 22 dB and the body labels the tonal component possible.
Verified
2026-09-15
Location precision
Exact site
Treaty geography
Treaty 8 territory; regional context only

Municipal permit: Development Permit 26-DP-001 has been issued by the Municipal District of Opportunity No. 17. The separate AUC power-plant application remains under review.

Site and footprint: The filing places the project at 16-36-080-25 W4M on Crown land within an existing oil-and-gas leasehold. The environmental evaluation uses a conservative 4.7-hectare footprint and says 92.6% is previously disturbed.

Data-centre configuration: The noise assessment models nine enclosed data centres, each with cooling fans and transformers, operating with the nine proposed engines.

Requested schedule: Armada requests AUC approval in the fourth quarter of 2026, construction in the first quarter of 2027, and service in the third quarter of 2027. These are applicant targets, not regulator deadlines or confirmed milestones.

Draft environmental approval: The EPEA document filed as Appendix H is marked Draftv2. ADCW does not treat it as an issued Environmental Protection and Enhancement Act approval.

Air modelling: The applicant's model, using selective catalytic reduction on all nine engines, predicts nitrogen-dioxide concentrations below the applicable objectives. This is a modelled applicant result, not operating measurement data.

Other approvals: The application says Historical Resources Act clearance has been obtained. A Crown-land disposition remains required before construction, and the filed EPEA document is still a draft.

Closure security proposal: The filed estimate proposes financial assurance based on approximately CA$2.05 million for decommissioning and reclamation. Its amount, form, timing, and beneficiaries remain subject to final approval requirements.

Earlier filing deficiencies: In closing Application 30253-A001, the AUC identified inaccurate Crown-land information, incorrect distances to nearby First Nations communities, and an incomplete record on whether appropriate consultation had occurred. Both earlier closures allowed a future application and were not a permanent ban.

Gas-asset purchase and record: A court order approved Armada's asset purchase from Sequoia Resources, and the trustee certificate says the sale closed on April 1, 2025. Alberta's air-data portal separately lists Hoole South Sour Gas Plant, approval 10135, under Armada. These records establish an asset connection, not permission to build the data centre.

Larger ambitions: The 2025 council presentation described a 200 MW data-centre goal and a 1 GW power-generation goal. These remain expansion ambitions, not confirmed Hoole capacity, and are excluded from current totals.

Bantry Data Site

Verified listing

AVAX One Technology Ltd. · Bantry region · AI / High-performance computing

Bantry area, southern Alberta
Not disclosed
Not disclosed
Not disclosed
Not disclosedNo project-specific values found
Overview

A proposed modular AI and HPC development at an energy-advantaged site in the Bantry area.

Current status
ProposedSubject to a non-binding acquisition letter of intent; closing and development are not confirmed
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-07-31
Location precision
Region only
Treaty geography
Not yet verified

Beacon Chestermere AI Data Center Hub

Evidence profile

Beacon Data Centers · City of Chestermere · AI / High-performance computing

Approximately 400 MW proposed at full build
Grid supply through a transmission extension and dedicated substation is proposed. Backup generation details are not confirmed.
Not disclosed
No project value publishedPermit-stage controls
Overview

Beacon's proposed phased 400 MW data centre campus on approximately 310 acres in southern Chestermere. The site is redesignated and the use is permitted, but the reviewed record does not establish permission to build.

Current status
ProposedProposed with land-use approval in place. Chestermere passed Bylaw 014-25 on April 1, 2025, but no project-specific development permit, construction approval, or construction start has been verified
Capacity context
Approximately 400 MW proposed at full buildBeacon described phased development to approximately 400 MW. This is a proponent plan, not an approved connection or operating load.
Cooling and water
Not disclosedNo project-specific cooling design, daily or annual water demand, supply source, wastewater volume, or operating water record has been published. A future development agreement must address municipal servicing.
Noise details
No project value publishedBylaw 014-25 requires appropriate controls for heat, noise, and emissions. The Development Authority may require a professional noise-attenuation study, mitigation plan, and monitoring system. No completed project-specific assessment or predicted receptor level was identified.
Verified
2026-09-07
Location precision
Exact site
Treaty geography
Treaty 7 territory

Land-use approval: Bylaw 014-25 redesignated approximately 310 acres and added Data Centre Campus as a permitted use in the Business Park / Light Industrial district.

Approval boundary: The bylaw is land-use approval. It is not a development permit, servicing agreement, building permit, grid approval, or construction approval.

Municipal agreement: A comprehensive development agreement for municipal services and other matters is required as a condition of any development permit.

Federal principles: Beacon Data Centers is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Beacon Foothills AI Data Center Hub

Evidence profile

Beacon Data Centers · Foothills County · AI / High-performance computing

400 MW proposed data centre campus
400 MW on-site generation proposed
Not disclosed
Study requiredDevelopment-permit stage
Overview

A proposed 400 MW data centre campus on 279.5 acres east of High River. Foothills County approved the planning framework in February 2025, but a project-specific development permit and utility approvals remain outstanding.

Current status
ProposedMunicipal planning bylaws are approved, but the campus remains a discretionary use and a project-specific development permit has not been verified
Capacity context
400 MW proposed data centre campusThe municipal planning record describes a 400 MW campus. This is a planning-stage capacity, not approved or operating demand.
Cooling and water
Not disclosedNo project-specific cooling design or routine water volume was found. The area plan discusses future County piped servicing and interim on-site options, not an approved campus water supply.
Noise details
Study requiredFoothills County requires a later development-permit application to include noise mitigation and monitoring where AUC Rule 012 does not apply. No project-specific noise model was found.
Verified
2026-09-11
Location precision
Approximate area
Treaty geography
Treaty 7 territory

Environmental review: Site and habitat assessments were submitted. The amended plan records wetlands and mapped wildlife survey areas; further assessment and mitigation remain part of later approvals.

Planning decision: Foothills County passed Bylaws 05/2025, 06/2025, and 07/2025 on February 26, 2025, amending the area plan and land-use rules and redesignating the subject lands.

Development permit: The data centre campus remains a discretionary use. A complete application must address noise mitigation and monitoring, fire prevention, and emergency response.

Published building concepts differ: The municipal application and provincial registry describe the building program differently. ADCW does not publish a definitive building count pending a current project-specific design filing.

Federal principles: Beacon Data Centers is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Beacon Harry Smith AI Data Center Hub

Verified listing

Beacon Data Centers · Parkland County · AI / High-performance computing

400 MW AESO connection request
Proposed 400 MW connection to Alberta's interconnected grid
Not disclosed
Not disclosedNo project-specific values found
Overview

One of six Alberta sites in Beacon's announced 4.5 GW portfolio, this early-stage AI campus is proposed in Parkland County, west of Edmonton; AESO currently lists a 400 MW data-load connection request under the project name.

Current status
ProposedThe provincial project registry identifies the proposal; AESO lists a 400 MW data-load connection request, while current municipal approvals remain unclear
Capacity context
400 MW AESO connection requestAESO lists P2927 Beacon Harry Smith A.I. Hub Load with a 400 MW DTS request. This is a grid-connection request, not an approved or operating data centre load.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-04
Location precision
Reported project-road intersection
Treaty geography
Treaty 6 territory

Federal principles: Beacon Data Centers is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Beacon Heartland AI Data Center Hub

Evidence profile

Beacon Data Centers / Heartland Power Generation LP · Sturgeon County · AI / High-performance computing

800 MW proposed data centre load
Proposed 920 MW on-site natural-gas generation
Air-cooled power generation; data-centre cooling design not final
46 day / 40 night dBAModelled cumulative at nearest receptor
Overview

A proposed four-building, 800 MW AI and high-performance-computing campus east of Gibbons, paired with a 920 MW natural-gas power plant now awaiting an AUC decision.

Current status
ProposedAUC record closed July 31; a decision on the proposed 920 MW power plant is due by October 29, 2026
Capacity context
800 MW proposed data centre loadFour proposed 200 MW data halls at full build, not operating demand.
Cooling and water
Air-cooled power generation; data-centre cooling design not finalThe proponent projects up to 1,500 m³/day (1.5 million L/day) for the full campus, including about 100 m³/day for power-generation ancillary uses.
Noise details
46 day / 40 night dBAAt R1, approximately 200 metres north of the project area, the filed model predicts 46 dBA daytime and 40 dBA nighttime cumulative sound. Proposed controls include exhaust and ventilation silencers, acoustic louvers, and a barrier north of the northern data hall. These are modelled results, not operating measurements.
Verified
2026-08-23
Location precision
Exact site
Treaty geography
Treaty 6 territory

Federal principles: Beacon Data Centers is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Beacon Indus Data Center Hub

Evidence profile

Beacon Data Centers / Indus Power Generation LP · Rocky View County · AI / High-performance computing

1.2 GW proposed data centre load
Proposed 1.494 GW on-site natural-gas generation
Air-cooled and closed-loop systems proposed
Values not summarizedModelled receptor assessment filed
Overview

One of six Alberta sites in Beacon's announced 4.5 GW portfolio, this proposed four-building, 1.2 GW campus near Indus is paired with a 1.494 GW natural-gas power plant now under AUC review.

Current status
ProposedThe AUC has held its oral hearing for Proceeding 30524, and the power-plant decision remains pending; municipal planning is approved, but later permits are still required
Capacity context
1.2 GW proposed data centre loadFour proposed 300 MW data halls at full build.
Cooling and water
Air-cooled and closed-loop systems proposedNo cooling towers or evaporative cooling are proposed; total campus demand is projected at about 1,500 m³/day (1.5 million L/day).
Noise details
Values not summarizedThe proponent says its completed model evaluated cumulative daytime and nighttime sound at assessed receptors and low-frequency noise. ADCW did not identify the numerical receptor table in the public summary. These are modelled findings in an active AUC proceeding, not operating measurements.
Verified
2026-09-09
Location precision
Exact site
Treaty geography
Treaty 7 territory

Federal principles: Beacon Data Centers is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Beacon Saunders Lake AI Data Center Hub

Evidence profile

Beacon Data Centers · Leduc County · AI / High-performance computing

400 MW AESO connection request
400 MW grid connection requested
Not disclosed
Not disclosedNo project-specific values found
Overview

Land-use changes are approved for Beacon's 160-acre proposal near Saunders Lake. A development permit has not been verified, and the 400 MW grid request does not authorize construction.

Current status
ProposedProposed: land redesignation approved; no development permit verified in the September 11, 2026 review
Capacity context
400 MW AESO connection requestSeptember 2026: P2935 remains at Stage 2 with its in-service date under review. This is requested grid capacity, not approved or operating demand.
Cooling and water
Not disclosedCooling design, water source, and daily or annual water demand remain unconfirmed.
Noise details
Not disclosedNo project-specific sound model or levels at nearby communities were found. Leduc County identifies noise as a permit-review consideration.
Verified
2026-09-11
Location precision
Approximate area
Treaty geography
Treaty 6 territory

Planning decision: Council unanimously passed Bylaw 18-24 on December 10, 2024, changing 160 acres from Agricultural to Light Industrial.

Permit status: Leduc County's June 26, 2026 update said no data-centre development permits had been approved. No later project-specific approval was located.

Federal principles: Beacon Data Centers is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Crusoe Alsike Energy Park Data Centre

Verified listing

Crusoe / KALiNA Distributed Power · Brazeau County · AI / High-performance computing

170 MW related power plant
Planned 170 MW co-located natural-gas plant, with Crusoe expected to buy power under a minimum 15-year power purchase agreement.
Not disclosed
Not disclosedNo project-specific values found
Overview

One of three proposed Crusoe compute sites paired with a planned 170 MW gas power plant at a KALiNA energy park.

Current status
ProposedNamed in a three-site development framework; AESO's August 2026 list shows the separate 280 MW Alsike data-load request as recently cancelled, and site-specific data centre approvals are not confirmed
Capacity context
170 MW related power plantThis is the planned gas plant capacity, not a verified data centre load.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-03
Location precision
Approximate project area
Treaty geography
Treaty 6 territory

AESO queue status: AESO lists the 280 MW Alsike data-load request, P3153, as recently cancelled. The separate gas-generation request remains in the connection process, and the corporate development framework has not been publicly withdrawn.

Location evidence: KALiNA identifies Alsike with the Warburg area, and AESO assigns the related requests to Brazeau County. The provincial map point is approximate, so it should not be read as a confirmed parcel or street address.

Crusoe Myers Energy Park Data Centre

Verified listing

Crusoe / KALiNA Distributed Power · Red Deer County · AI / High-performance computing

170 MW related power plant
Planned 170 MW co-located natural-gas plant, with Crusoe expected to buy power under a minimum 15-year power purchase agreement.
Not disclosed
Not disclosedNo project-specific values found
Overview

One of three proposed Crusoe compute sites paired with a planned 170 MW gas power plant at a KALiNA energy park.

Current status
ProposedNamed in a three-site development framework; AESO's August 2026 list shows the separate 280 MW Myers data-load request as recently cancelled, and site-specific data centre approvals are not confirmed
Capacity context
170 MW related power plantThis is the planned gas plant capacity, not a verified data centre load.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-03
Location precision
Approximate project area
Treaty geography
Near the mapped Treaty 6 / Treaty 7 boundary

AESO queue status: AESO lists the 280 MW Myers data-load request, P3155, as recently cancelled. The separate gas-generation request remains in the connection process, and the corporate development framework has not been publicly withdrawn.

Location evidence: KALiNA identifies Myers with the Lacombe area, and AESO assigns the related requests to Red Deer County. The provincial map point is approximate, so it should not be read as a confirmed parcel or street address.

Data Centre West of Clive

Evidence profile

Armada Nowlit Energy Ltd. · Lacombe County · Mixed AI / Cryptocurrency

19.8 MW proposed on-site generation
Proposed 19.8 MW on-site natural-gas generation with biofuel capability. No active project-specific Clive AUC proceeding was identified
Closed-loop liquid cooling proposed
35.3–35.9 dBAModelled nighttime application case
Overview

A proposed approximately 19.8 MW natural-gas-powered modular facility west of Clive. The project is marketed for AI and digital-asset computing, while its submitted air model describes nine miner containers.

Current status
ProposedRezoning application under review. Lacombe County confirmed on August 27, 2026 that no municipal approvals have been granted; the developer meeting is September 30 and separate County engagement is planned for late 2026 or early 2027
Capacity context
19.8 MW proposed on-site generationNine proposed 2.2 MW generator sets. This is gross generation capacity, not a verified data-centre load.
Cooling and water
Closed-loop liquid cooling proposedThe developer says each unit would receive an initial 250–300 L water-glycol fill trucked to site, followed by minor maintenance top-ups. The package does not define the unit clearly enough to calculate a reliable project total.
Noise details
35.3–35.9 dBAThe developer predicts 35.3–35.9 dBA for its application case and 35.4–36.2 dBA cumulatively at assessed receptors. These are modelled results, not operating measurements.
Verified
2026-09-14
Location precision
Exact site
Treaty geography
Treaty 6 territory

Data District Bonnyville Region Facility

Verified listing

Data District Inc. / Technologies New Energy · Bonnyville region · AI / High-performance computing

Bonnyville region
Not disclosed
Not publicly confirmed for the Bonnyville site.
Not disclosed
Not disclosedNo project-specific values found
Overview

The Government of Alberta lists the Bonnyville region as the expected second site in a four-project Data District and Technologies New Energy program. The provincial record gives a combined 240 MW capacity and CA$1.26 billion budget for all four sites, but no Bonnyville-specific capacity, parcel, permit, or municipal application.

Current status
ProposedNamed as the expected second site in a four-project Alberta program; site, capacity, land control, permits, and municipal applications have not been publicly identified
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-13
Location precision
Region only; municipality and site not confirmed beyond the provincial listing
Treaty geography
Treaty 6 territory

Province-wide program: Alberta Major Projects identifies four Phase 1 regions: Olds, Bonnyville, Calgary, and Edmonton, with about 240 MW and CA$1.26 billion combined. It does not assign a capacity or investment amount to Bonnyville.

Schedule claim: The provincial listing says construction on the Bonnyville facility is expected in 2027. This is a projected schedule, not evidence of an approved site or construction start.

Calgary and Edmonton: The same program also names Calgary and Edmonton regions. ADCW is retaining those as research leads until a site-level identity, capacity, land record, permit, or municipal application is found.

Data District Olds Facility

Verified listing

Data District Inc. / Technologies New Energy · Town of Olds · AI / High-performance computing

55 MW announced Olds facility
Alberta grid · FortisAlberta
Not disclosed
Not disclosedNo project-specific values found
Overview

Data District has purchased land in Olds and is working with Invest Olds on early planning and site readiness for a proposed 55 MW facility. No formal development or regulatory application has been submitted.

Current status
ProposedLand purchased; early planning and site-readiness work underway with Invest Olds; no formal development or regulatory application submitted
Capacity context
55 MW announced Olds facilityA company-announced target, not an approved or operating load.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-13
Location precision
Approximate point in provincial project listing
Treaty geography
Treaty 7 territory

Municipal status: Data District Inc. has purchased land in Olds and is working with Invest Olds on early planning and site readiness. As of August 28, 2026, the Town reports that no formal development or regulatory application has been submitted.

Phase 1 program: Alberta Major Projects describes Olds as the first of four Phase 1 regional projects, followed by Bonnyville, Calgary, and Edmonton, with about 240 MW and CA$1.26 billion combined. The 55 MW figure in this record applies to Olds; ADCW does not divide the remaining program capacity among the other regions without site-level evidence.

FingerMotion Brooks Campus Zone

Verified listing

FingerMotion, Inc. / BlueFlare Group Holdings Inc. · County of Newell · AI / High-performance computing

County of Newell
9.9 MW proposed on-site generation
FingerMotion proposes separate 9.9 MW behind-the-meter generation systems for each site. The company reports 99 MW of planned gross generation across campuses in Brooks, Coronation, Fox Creek, and Vulcan, but has not disclosed how the ten sites are distributed among those campuses or confirmed a power-plant or industrial-system approval.
Not disclosed
Not disclosedNo project-specific values found
Overview

FingerMotion identifies Brooks as one of four Alberta campuses in a company-announced program of ten separate 9.9 MW behind-the-meter generation and data-hall sites. Its earlier binding agreement covers the first Brooks site, which has not been permitted and remains subject to closing conditions.

Current status
ProposedFirst 9.9 MW site under a binding agreement; broader four-campus program announced; permits, customer contracts, construction, and operation remain unconfirmed
Capacity context
9.9 MW proposed on-site generationFingerMotion's development target for the first power-and-compute site, not permitted or operating capacity. The company says later energization would require contracted customer demand and a funded deposit.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-17
Location precision
Municipality only; parcel not disclosed
Treaty geography
Treaty 7 territory

What the agreement covers: FingerMotion says the binding memorandum covers acquiring land rights and permitting. Completion remains subject to closing conditions, and the company says no site has been permitted.

Broader Alberta program: On September 15, 2026, FingerMotion said it was advancing ten separate 9.9 MW sites across Brooks, Coronation, Fox Creek, and Vulcan. The company reports 99 MW of gross generation and approximately 72 MW of aggregate continuous critical IT capacity, but does not say how many sites are assigned to each campus.

Development sequence: FingerMotion targets permits for all ten sites by the end of the first quarter of 2027, first energization beginning in late fourth quarter 2026, and data-hall turnover about 18 months after each permit. These are company targets, not completed milestones.

Ownership and customer status: FingerMotion says each site has a dedicated Alberta project company that would hold the land, permits, and site agreements, while BlueFlare would develop, build, and operate the sites. FingerMotion also says no customer offtake agreement has been executed.

Gayford Integrated Energy and Data Facility

Verified listing

Armada Nowlit Energy Ltd. · Rocky View County · Data processing / Workload undisclosed

19.95 MW proposed on-site generation
The municipal plan proposes up to 20 MW of natural-gas generation for exclusive on-site use, with no connection or export to the Alberta grid.
Not disclosed
Not independently confirmedMunicipal and AUC filing record
Overview

A proposed integrated facility near Gayford pairing up to 20 MW of natural-gas generation with modular on-site data processing. Three earlier 19.95 MW AUC applications were closed for filing deficiencies.

Current status
ProposedA proposed municipal master site development plan is not final. No active AUC power-plant application was identified after proceedings 30385, 30476, and 30709 were closed without merits decisions.
Capacity context
19.95 MW proposed on-site generationThe three closed AUC applications each described a 19.95 MW gas-fired plant near Gayford. The current municipal plan sets a 20 MW maximum. This is proposed generation, not a verified data-centre load, and is excluded from headline totals while no active AUC application is identified.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not independently confirmedThe municipal plan says a noise-impact assessment demonstrates compliance with AUC Rule 012. The three AUC applications closed without merits decisions, so this is not a regulator finding or an operating measurement.
Verified
2026-09-14
Location precision
Legal subdivision midpoint (ATS)
Treaty geography
Treaty 7 territory

Municipal proposal: The plan seeks to redesignate a 1.8-hectare part of LSD 12, SE 35-26-25-W4M from Agricultural, General to a site-specific Direct Control District. Rocky View County lists the plan as proposed and not final.

AUC filing history: Proceedings 30385, 30476, and 30709 each concerned a 19.95 MW plant near Gayford. The AUC closed all three without prejudice after identifying numerous Rule 007 information deficiencies; it did not decide the project merits.

Third application: Application 30709-A001 was registered on April 8, 2026 and closed on May 7, 2026. The regulator cited deficiencies involving environmental evaluation, wildlife, emergency response, Indigenous consultation information, and participant involvement.

Data-processing scope: The municipal plan describes co-located modular data containers but does not identify a customer, installed computing hardware, specific workload, or data-centre electrical load.

Genesee Data Centre Site

Verified listing

Capital Power · Leduc County · Data centre / Workload undisclosed

1.5 GW across two AESO connection requests
Existing 1,857 MW Genesee natural-gas generation site
Not disclosed
Not disclosedNo project-specific values found
Overview

An early data centre opportunity at the operating Genesee generating station near Warburg. AESO lists 1.5 GW across two connection requests, while Capital Power markets approximately 500 MW as available and says the project is not advancing immediately.

Current status
ProposedAESO lists 1.5 GW across two data-load requests, but Capital Power says the site is not advancing immediately and no tenant or active build is confirmed
Capacity context
1.5 GW across two AESO connection requestsAESO lists P2942 at 1,000 MW and P2946 at 500 MW. Capital Power says the site is not advancing immediately, so ADCW treats this as queue context rather than an active build commitment.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-20
Location precision
Exact generating-station address
Treaty geography
Treaty 6 territory

Why the figures differ: The 1.5 GW figure describes requested grid-load stages. The approximately 500 MW figure describes existing generation Capital Power says could be available. They measure different things and cannot be added together.

Goldfinch Technology Park Data Centre

Evidence profile

Diode Ventures · Wheatland County · Data centre / Workload undisclosed

950 MW AESO connection request
Proposed Alberta grid supply through AESO P3102
Final cooling design not selected
Study requiredDevelopment-permit stage
Overview

Diode Ventures' proposed approximately 576-acre data centre park west of Carseland. The final County plan adopts the project's area concept plan, but permission to build is not verified. AESO lists 650 MW and 300 MW grid-load stages, not operating demand.

Current status
ProposedThe final Goldfinch plan records adoption of the Diode area concept plan on August 11, 2026; no project-specific development permit is verified. AESO's 950 MW request has in-service dates under review
Capacity context
950 MW AESO connection requestP3102 has 650 MW and 300 MW DTS stages at Stage 2. Both in-service dates are under review in AESO's August 2026 list. This is one campus request, not 950 MW of approved or operating load.
Cooling and water
Final cooling design not selectedDiode says local aquifer water will not be used for cooling. Final demand and supply are not confirmed. The County's separate raw-water line currently serves CGC; no Diode connection or allocation is confirmed.
Noise details
Study requiredWSP's June submission says a noise-impact assessment is required at each development-permit stage. Diode proposes mitigation, but ADCW did not find numerical receptor predictions or operating measurements in the reviewed package and project updates.
Verified
2026-09-09
Location precision
Approximate area
Treaty geography
Treaty 7 territory

HubOne AI and BTC High Density Compute Park

Verified listing

Elemental Developments / HubOne · Wheatland County · Mixed AI / Cryptocurrency

At least 750 MW of planned AI capacity
Up to 3 GW of planned on-site generation is described for the mixed AI and Bitcoin park
Not disclosed
Not disclosedNo project-specific values found
Overview

A proposed mixed AI and Bitcoin high-density compute park in Wheatland County. Alberta's Major Projects registry describes at least 750 MW of planned AI data centre capacity and up to 3 GW of power across the mixed-use development.

Current status
ProposedAnnounced mixed AI and Bitcoin proposal; the published capacity figures are early full-build claims, and approvals and committed capacity are not confirmed
Capacity context
At least 750 MW of planned AI capacityThe provincial registry describes capacity for 15 private AI data facilities starting at 50 MW each. This is an early full-build claim, not approved or operating capacity.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-20
Location precision
Approximate point in provincial project listing
Treaty geography
Treaty 7 territory

Mixed-use limitation: The 3 GW power claim covers both AI and Bitcoin operations. ADCW does not treat it as 3 GW of data centre demand or add it to province-wide AI totals.

Keephills Data Centre Development

Evidence profile

TransAlta / CPP Investments / Brookfield · Parkland County · Data centre / Workload undisclosed

230 MW initial grid-load contract
TransAlta would provide the site and electricity. The final mix of grid power, existing generation, and any new equipment is not confirmed.
Not disclosed
Study not foundNo project-specific values found
Overview

A proposed data centre at TransAlta's Keephills power-station site. An initial 230 MW stage could grow to 1 GW, but that expansion is not committed. The final design, water needs, and noise effects on neighbours are not public.

Current status
ProposedLand-use changes approved; development approval and final business agreements still outstanding in the reviewed sources
Capacity context
230 MW initial grid-load contractAESO, Alberta's grid operator, has allocated 230 MW to P3083 under a signed load contract. Connection work remains; this does not mean the data centre is built or using power.
Cooling and water
Not disclosedExisting water infrastructure does not tell us how much water the data centre would use. Its cooling design, water allocation, and wastewater arrangements are not confirmed.
Noise details
Study not foundADCW did not find a project-specific noise study or predicted sound levels at nearby communities in the sources reviewed on August 31, 2026. The County identifies noise and other effects on neighbours as matters for development-permit review.
Verified
2026-08-31
Location precision
Approximate area
Treaty geography
Treaty 6 territory

Permission to build: The County's page, last updated March 4 and checked August 31, 2026, still says it has not received development-stage applications. Land-use approval is not a development permit.

Timing: The August grid list shows two 115 MW stages for P3083, dated January 1, 2027, and March 27, 2028. These are connection-planning dates, not confirmed opening dates. Dates for the other two requests are under review.

Existing power plant: TransAlta lists 861 MW of existing gas-fired generation at Keephills. That is not new generation for this proposal, and the reviewed sources do not commit all of it to the data centre.

Malachite One Data Centre

Evidence profile

Emerald Energy Technologies Corp. (Tourmaline Oil Corp. subsidiary) · Yellowhead County · AI / High-performance computing

930 MW proposed on-site generation at full build
The concept combines up to 930 MW of on-site natural-gas generation with AESO's active 74.9 MW P3114 grid-load request.
Primarily closed-loop air-based cooling, with supplementary evaporative cooling proposed
Not disclosedNo project-specific values found
Overview

A proposed AI and high-performance-computing campus on Crown land beside the Banshee Gas Plant, pairing up to 930 MW of on-site natural-gas generation with a 74.9 MW AESO grid-load request.

Current status
ProposedYellowhead County received the concept for information; AESO lists an active 74.9 MW Stage 2 data-load request, but project-specific construction approvals are not confirmed
Capacity context
930 MW proposed on-site generation at full buildA proponent projection, not approved or operating generation. The presentation's separate 1,104 MW full-build total does not reconcile with its listed 930 MW generation and 74 MW grid components.
Cooling and water
Primarily closed-loop air-based cooling, with supplementary evaporative cooling proposedMost proposed water demand is associated with power-plant steam generation. No complete project water balance or project-specific Water Act authorization was identified.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-27
Location precision
Approximate area
Treaty geography
Treaty 6 territory

Full-build concept: Up to 7.1 million square feet across three phases, with a projected 30-year operating life.

Proposed investment: Up to CA$15 billion for the data centre and CA$5 billion for associated power generation.

Employment claims: Emerald projects data-centre staffing beginning around 300 and growing to 700, while Alberta Major Projects reports 300 to 500 long-term data-centre jobs.

Mihta Askiy Data Centre

Evidence profile

Mihta Askiy Datacenter LP / Cree Ative Datacenter Corp GP · Northern Sunrise County · AI / High-performance computing

650 MW proposed data centre load at full build
Proposed 650 MW on-site natural-gas generation with a planned grid connection
Closed-loop data-centre cooling proposed
Not disclosedNo project-specific values found
Overview

A majority Woodland Cree First Nation-owned proposal to reuse the former Carmon Creek industrial site for a 650 MW data centre and natural-gas power plant.

Current status
ProposedThe proposed power plant and substation remain under AUC review. The federal decision did not approve construction.
Capacity context
650 MW proposed data centre load at full buildThe filing describes an initial 400 MW data centre followed by a 250 MW expansion.
Cooling and water
Closed-loop data-centre cooling proposedThe related power plant is expected to use evaporative cooling; initial-phase project demand is projected at up to 5,000 m³/day (5 million L/day).
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-23
Location precision
Approximate area
Treaty geography
Treaty 8 territory

Federal principles: Sovereign Digital Infrastructure, identified in the project's federal filing as its 49 per cent owner, is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Newell Data Center MPC Load

Verified listing

Not publicly disclosed · County of Newell · Data centre / Workload undisclosed

Brooks / County of Newell area
1.2 GW AESO connection request
Proposed Alberta grid connection through AESO Project P3109
Not disclosed
Requirement proposedNo project application filed
Overview

An unnamed developer's 1.2 GW grid-load connection request in AESO's Brooks planning area. County-wide data centre rules are proposed, but the reviewed municipal record does not approve this project or identify its developer.

Current status
ProposedAESO Project P3109 is active in connection-process Stage 2 with three 400 MW stages, all with in-service dates under review; no County development application or project approval has been confirmed
Capacity context
1.2 GW AESO connection requestAESO lists three 400 MW data-load stages, each with its in-service date under review. This is a request in the connection process, not construction approval, committed service, or operating demand.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Requirement proposedThe County's proposed data-centre bylaw would require project-specific noise information and mitigation, but the County says no development application for P3109 has been confirmed. ADCW did not identify a project-specific assessment in the August 29 review.
Verified
2026-08-26
Location precision
Regional location only; project parcel unverified
Treaty geography
Treaty 7 territory

Municipal status: The County's proposed data centre rules are a framework for future applications. The County says the policy would not approve or authorize a data centre, and ADCW has not confirmed a project-specific development application for P3109.

Location lead: Local reporting places the prospective site near Highway 36 and Silver Sage Road on approximately 500 hectares of Eastern Irrigation District land. ADCW has not found a primary project record confirming the parcel, so no map marker is published.

Workload gap: AESO identifies a data-load request but does not disclose the intended computing workload. No public source reviewed by ADCW identifies an AI, high-performance computing, cryptocurrency, or mixed-use allocation.

Prairie Sky Strathmore Campus

Verified listing

Prairie Sky Data Solutions · Town of Strathmore · AI-ready colocation

50 MW full-build roadmap
Company says expansion depends on securing additional power and infrastructure.
Prairie Sky says direct liquid cooling is designed for rack densities up to 150 kW
Not disclosedNo project-specific values found
Overview

A phased AI-ready colocation campus beginning with a 2 MW retrofit and targeting 50 MW across five phases.

Current status
ProposedCompany describes a retrofit, but construction and operation are not independently verified; Alberta Major Projects still classifies Phase 1 as Proposed
Capacity context
50 MW full-build roadmapPrairie Sky's roadmap lists a 2 MW first phase; a 4 MW expansion to 6 MW total; then 14 MW, 36 MW, and 50 MW total capacity. Later phases are company targets and include a nearby second site.
Cooling and water
Prairie Sky says direct liquid cooling is designed for rack densities up to 150 kWPrairie Sky promotes direct liquid cooling, but routine water withdrawal and consumption are not publicly quantified.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-11
Location precision
Approximate point in provincial project listing
Treaty geography
Treaty 7 territory

Opening date remains unconfirmed: The company website still carries a Q2 2026 opening target in its page description. That date has passed. No municipal permit, energization record, or direct operating announcement was located in the September 11 review; the target is not evidence that Phase 1 opened.

What 50 MW means: The company's current roadmap starts with a 2 MW retrofit and expands across five phases, including a nearby second site. The 50 MW total is a future target, not capacity verified in service.

Community benefit discussions: Strathmore's Q3 2025 report records discussions about Phase 3 and a possible annual community donation versus a special tax. This establishes municipal engagement, not a signed benefit agreement, permit, or proof that earlier phases opened.

StratGrid Project Wheatland

Verified listing

StratGrid Inc. · Wheatland County · AI / High-performance computing

Wheatland County
Approximately 200 MW designed generation capacity
Proposed on-site, behind-the-meter natural-gas generation. The reported capacity is a company design, not approved or operating generation.
Closed-loop immersion-ready design proposed
Not disclosedNo receptor values found
Overview

StratGrid proposes an AI data centre campus in Wheatland County powered by on-site natural gas. Jet.AI reports approximately 200 MW of designed generation capacity, while other published figures differ. No public project application or approval has been verified.

Current status
ProposedCompany development and regulatory preparation announced; no parcel, municipal development application, AUC application, environmental authorization, construction, or operation has been verified
Capacity context
Approximately 200 MW designed generation capacityJet.AI's SEC-filed release and current project page describe approximately 200 MW of on-site natural-gas generation for Project Wheatland. This is proposed design capacity, not an approval or operating output.
Cooling and water
Closed-loop immersion-ready design proposedStratGrid says the design is intended to use minimal water. A project water balance, supply source, wastewater plan, and authorization have not been verified.
Noise details
Not disclosedStratGrid says equipment selection, layout, acoustic treatment, screening, and setbacks will be developed through engineering and regulatory review. No project-specific noise-impact assessment or numerical predictions for nearby communities were found.
Verified
2026-09-14
Location precision
Municipality only; parcel not disclosed
Treaty geography
Treaty 7 territory

Investment structure: Jet.AI's SEC financial statement says it invested US$1.75 million through SG Canada InvestCo LLC. Jet.AI owns 60% of InvestCo, and the investment implies InvestCo holds approximately 26% of StratGrid on a fully vested basis.

Land control: Jet.AI says StratGrid controls several hundred acres of freehold land across Project Wheatland and a second Southern Alberta site. The Wheatland parcel, civic address, legal land description, and municipal planning file have not been disclosed.

Larger scale claims: The companies describe Project Wheatland as expandable beyond 1 GW and the two-site Alberta platform as capable of more than 2 GW over time. These are long-term company ambitions, not approved capacity, and are excluded from ADCW's headline totals.

Regulatory stage: StratGrid says AUC and Alberta Environment and Protected Areas pre-application work has begun and lists future provincial filings in its development schedule. ADCW has not verified a filed project application or authorization.

Teton Digital Black Bear Campus

Verified listing

Teton Digital · Swan Hills region · AI / High-performance computing

466 MW proposed gas generation
Proposed 466 MW behind-the-meter natural-gas combined-cycle generation
Not disclosed
40.3 dBA nighttimeModelled at 1.5 km boundary
Overview

A proposed Tier-compatible compute campus about 19 km south of Swan Hills, paired with the previously approved Black Bear power plant.

Current status
ProposedThe underlying power plant has approvals, but the data centre campus remains a proponent proposal
Capacity context
466 MW proposed gas generationThe operator links this power capacity to a proposed compute campus; it is not an approved data centre load.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
40.3 dBA nighttimeThe Black Bear power-plant model predicts 40.3 dBA nighttime cumulative sound at the most affected 1.5 km boundary receptors. The AUC requires stack mitigation plus near-field and comprehensive post-construction surveys, including low-frequency noise. The assessment does not cover a future compute campus.
Verified
2026-08-19
Location precision
Project coordinates in federal filing
Treaty geography
Treaty 8 territory

Teton Digital Northern Forge Campus

Verified listing

Teton Digital · Municipal District of Greenview No. 16 · AI / High-performance computing

200 MW proposed gas-to-compute capacity
Proposed 200 MW behind-the-meter natural-gas generation
Not disclosed
No values foundAUC review underway
Overview

A proposed 200 MW behind-the-meter gas-to-compute campus on a 155-acre Greenview site.

Current status
ProposedProponent says permits are largely in hand while AUC review remains under evaluation
Capacity context
200 MW proposed gas-to-compute capacityA proponent full-build figure; the first planned phase is 30 MW.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
No values foundTeton says the power-plant application is under AUC evaluation. ADCW's August 29 noise review did not identify a public noise-impact assessment, receptor prediction, or mitigation schedule for Northern Forge.
Verified
2026-08-19
Location precision
Approximate point in provincial project listing
Treaty geography
Treaty 8 territory

Travers AI Data Centre Campus

Evidence profile

Palliser Grid · Vulcan County · Hyperscale / AI

Up to 2,000 MW planning target
A new 500 kV substation and two transmission feeds are proposed
Closed-loop liquid cooling and heat rejection under study
Not disclosedNo project-specific values found
Overview

Palliser Grid's concept for up to 2 GW of IT load across a multi-building campus near Travers Reservoir in Vulcan County.

Current status
ProposedIndustrial rezoning approved and challenged through judicial review; a data centre development permit and utility approvals have not been issued
Capacity context
Up to 2,000 MW planning targetThe submitted concept plan describes four potential 500 MW phases. This is a planning ceiling, not approved or contracted operating demand.
Cooling and water
Closed-loop liquid cooling and heat rejection under studyThe concept proposes a BRID/Travers Reservoir supply and on-site wastewater reuse, but no final water balance, licence amendment or allocation was found.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-09-17
Location precision
Approximate area
Treaty geography
Treaty 7 territory

Concept footprint: About 8 million square feet across 20 to 30 data centre buildings

Phasing concept: Four potential 500 MW phases

Judicial review: A July 22, 2026 application challenges the rezoning process. The allegations have not been adjudicated, and the matter is scheduled for September 29, 2026.

Wild Rose Power Hub Data Centre

Evidence profile

BHE Canada / Chinook Development LP · Rocky View County · Data centre / Workload undisclosed

1.3 GW AESO connection request
Alberta grid proposed
Closed-loop dry cooling proposed
65 day / 55 evening dBLocation and weighting unspecified
Overview

A proposed 479-acre data centre southwest of Langdon with a 1.3 GW grid request. Planning review continues; published job estimates disagree, and no development permit has been verified.

Current status
ProposedProposed: area structure plan under review; no final plan adoption or development permit verified
Capacity context
1.3 GW AESO connection requestSeptember 2026: P3108 lists 300 MW and 1,000 MW stages, with service dates under review. Requested capacity is not approved or operating demand.
Cooling and water
Closed-loop dry cooling proposedBHE Canada claims virtually no water use for core cooling. Total site water demand is not quantified.
Noise details
65 day / 55 evening dBWild Rose’s developer states operational sound targets of 65 dB during the day and 55 dB in the evening. It does not say where these targets apply or how the sound would be measured. These figures do not establish sound levels at nearby communities.
Verified
2026-09-11
Location precision
Approximate area
Treaty geography
Treaty 7 territory

Job estimates conflict: The developer projects 200–300 ongoing jobs and 975–2,100 construction jobs. Alberta Major Projects labels the larger range as operations jobs; the difference remains unresolved.

Public review: The County says a Council public hearing remains part of the planning process. Approval of terms of reference did not approve the data centre.

Wonder Valley AI Data Centre Park

Evidence profile

O'Leary Digital Limited · Municipal District of Greenview No. 16 · Hyperscale / AI

Up to 1 GW of Phase 1 data centre IT load
Proposed off-grid on-site natural-gas generation. The current FAQ describes up to 2 GW for Phase 1 and 7.5 GW over the long term
Reuse and recirculation under study
Study in preparationNo published receptor values
Overview

A proposed off-grid AI data centre industrial park south of Grande Prairie. O'Leary Digital now describes a Phase 1 build of up to ten approximately 100 MW data centre facilities supported by up to 2 GW of on-site power.

Current status
ProposedPlanning and regulatory preparation underway; required approvals are not complete
Capacity context
Up to 1 GW of Phase 1 data centre IT loadO'Leary Digital says Phase 1 could support up to ten data centre facilities, each designed for approximately 100 MW of IT load. This is a proponent plan, not approved or operating capacity.
Cooling and water
Reuse and recirculation under studyFinal cooling design and operating water balance are not publicly confirmed.
Noise details
Study in preparationThe proponent's consultation filing says project-specific noise work is still being prepared. No final noise-impact assessment or receptor prediction was found.
Verified
2026-09-03
Location precision
Approximate area
Treaty geography
Treaty 8 territory
Inactive3 projects

Cancelled, withdrawn, or refused projects retained because they remain part of Alberta's public development record.

Crusoe Crossfield / Lone Pine Energy Park Data Centre

Verified listing

Crusoe / KALiNA Distributed Power · Rocky View County · AI / High-performance computing

170 MW related power plant in the former proposal
The withdrawn proposal paired the data centre with a planned 170 MW natural-gas plant. AESO lists the related 178 MW gas-generation request as recently cancelled.
Not disclosed
Not disclosedNo project-specific values found
Overview

A former Crusoe and KALiNA proposal for a co-located data centre and gas power plant near Crossfield. The site-specific municipal proposal and both related AESO requests have been withdrawn or cancelled.

Current status
InactiveKALiNA withdrew the Lone Pine data centre proposal at the mapped Crossfield site; AESO also lists the related data-load and gas-generation requests as recently cancelled
Capacity context
170 MW related power plant in the former proposalThis was the proponent's planned gas-plant capacity, not a verified data centre load. AESO lists the related 178 MW generation request as recently cancelled.
Cooling and water
Not disclosedProject-specific cooling technology and routine water use have not been publicly disclosed.
Noise details
Not disclosedProject-specific noise details were not found in the public sources reviewed.
Verified
2026-08-20
Location precision
Approximate project area
Treaty geography
Treaty 7 territory

Municipal status: Rocky View County says KALiNA withdrew the Lone Pine Energy Centre data centre proposal, ending the County's work on the area structure plan terms of reference.

AESO queue status: AESO lists the 280 MW Lone Pine data-load request, P3154, and the related 178 MW gas-generation request, P2980, as recently cancelled.

Broader framework: The original three-site Crusoe and KALiNA framework remains part of the historical record, but ADCW found no confirmed replacement site for the withdrawn Crossfield / Lone Pine proposal.

Kineticor Data Centre Campus

Verified listing

Kineticor Asset Management · Rocky View County · AI / High-performance computing

Not disclosed
Not disclosed
Low-water cooling concept
Study was not filedProposal refused before permit stage
Overview

A refused 1,107-acre AI data centre and technology park proposal in northeast Rocky View County.

Current status
InactiveRocky View County refused the area structure plan on September 9, 2025; the proposal cannot proceed under that plan
Capacity context
Not disclosedNo additional capacity context published.
Cooling and water
Low-water cooling conceptThe former proposal projected a 4,000 to 6,000 m³ initial fill (4 to 6 million L) and comparatively small routine cooling use.
Noise details
Study was not filedThe County's review said a later development-permit application would need a noise-impact assessment covering predicted boundary levels, mitigation, and monitoring. Council refused the area structure plan before that stage, and ADCW did not identify a completed project-specific assessment.
Verified
2026-07-31
Location precision
Approximate former planning area
Treaty geography
Treaty 7 territory

Synapse Olds Data Centre

Evidence profile

Synapse Real Estate Corp. · Town of Olds · Hyperscale / AI

1 GW proposed data centre capacity
No approved power source identified
Closed-loop data-centre cooling proposed
75 dBA optionProposed emergency-generator rating
Overview

A former proposal for a 1 GW AI data centre campus in Olds. Synapse says the project will not proceed as proposed after the AUC denied the proposed 1.4 GW supporting power plant.

Current status
InactiveSynapse says the Olds project will not proceed as proposed after the AUC denied its supporting power-plant application
Capacity context
1 GW proposed data centre capacityTen proposed 100 MW data centre blocks at full build.
Cooling and water
Closed-loop data-centre cooling proposedDeveloper estimate: approximately 60 m³/day (60,000 L/day) across the filed site design; not an approved allocation or measured demand.
Noise details
75 dBA optionThe historical proposal included a noise-impact assessment and municipal peer review. The proposed 75 dBA emergency-generator option produced Rule 012 exceedances at several nearby receptors; the associated power plant was later refused.
Verified
2026-08-25
Location precision
Exact site
Treaty geography
Treaty 7 territory