← Alberta data centre project list

Verified project profile

Beacon Indus Data Center Hub

Beacon proposes four 300 MW data halls and a 1.494 GW natural-gas power plant near Indus as part of its announced six-site Alberta portfolio. Rocky View County approved the area structure plan and land-use redesignation in June 2025. The federal early decision ended the Impact Assessment Act planning phase without requiring a further federal assessment, but it did not approve construction. The AUC has held its oral hearing on the power plant, and no final decision has been issued. The AUC has not stated that the proceeding is formally closed. Later municipal development permits are still required.

Beacon Data Centers / Indus Power Generation LP
How to read this profilePublic recordProponent statementProponent projectionADCW context

Project facts

Core scale, approval, employment, and schedule information, labelled by the type of evidence available.

Proponent statement

Proposed data centre load

1.2 GW

Four proposed data halls rated at 300 MW each.

Sources [7]
Public record

Proposed power plant

1.494 GW

The AUC application covers on-site natural-gas generation for the campus.

Sources [1]
ADCW context

Beacon Alberta portfolio

4.5 GW across six sites

Beacon announced up to CA$10 billion in Alberta investment and said sites could energize as early as 2027. These are portfolio-level claims, not a confirmed Indus funding or opening schedule.

Sources [14], [15]
ADCW context

Planning area

3.83 km² (383 ha)

The approved area structure plan covers about 946 acres. The federal filing describes a smaller 627.2-acre data-centre campus within the broader planning area.

Sources [4], [7]
Public record

AUC proceeding

30524

The proceeding reviews the proposed 1.494 GW power plant. The AUC has not issued a final decision.

Sources [1]
Public record

Federal assessment

No further assessment required

IAAC decided at an early stage that potential federal effects could be limited or addressed through existing laws. The decision is not project approval.

Sources [10], [8]
ADCW context

Employment estimates

About 300 permanent jobs

The company FAQ says more than 1,500 construction jobs, while the federal filing says up to 4,500. The reviewed records do not reconcile the construction estimates.

Sources [11], [7]
Proponent projection

Target operation

Third quarter of 2027

A proponent schedule that remains subject to approvals, construction and commercial decisions.

Sources [7]

Energy and emissions

The proposed 1.494 GW power plant is larger than the planned 1.2 GW data centre load. Both figures describe a proposal, not operating capacity.

Important distinction: AUC Proceeding 30524 reviews the power plant and related facilities. Municipal planning approval did not approve the plant or authorize construction of the data halls.
Proponent statement

Data hall demand

Approximately 1,200 MW

The power plant is intended to serve four 300 MW data halls under normal operations.

Sources [1], [7]
Proponent statement

Reciprocating generation

100 units totalling 460 MW

The filing describes 100 natural-gas engines rated at 4.6 MW each.

Sources [7]
Proponent statement

Combined-cycle generation

Four generating blocks

The proposed plant combines reciprocating engines with four combined-cycle gas-turbine blocks for 1.494 GW total capacity.

Sources [7]
Proponent projection

Projected annual generation

About 10,500 GWh

The proponent estimate assumes full campus operation.

Sources [7]
Proponent projection

Maximum annual GHG estimate

4.784 million tonnes CO₂e

The federal filing's maximum estimate assumes a 1.2 GW load at 100 per cent utilization. It is not a measured result.

Sources [7]
ADCW context

Carbon capture

Future-ready design claimed

The filing discusses possible future carbon capture, renewable gas, hydrogen and offsets, but does not commit to a capture system or operating date.

Sources [7]

Water

The federal filing projects approximately 1,500 m³/day (1.5 million L/day) of water demand. Supply agreements, final infrastructure capacity and measured use are not yet established in the public record. [7]

Proponent projection

Projected campus demand

About 1,500 m³/day (1.5 million L/day)

The filing says water would come from the regional or municipal system through Langdon Waterworks.

Sources [7], [11]
Proponent statement

Cooling design

Air-cooled and closed-loop systems

The filing says the power systems would not use cooling towers or evaporative cooling.

Sources [7]
Proponent projection

Power-plant and site use

About 750 m³/day (750,000 L/day)

The estimate covers heat-recovery steam-generator makeup, fire protection, domestic use and maintenance within the overall campus projection.

Sources [7]
Proponent statement

Wastewater

Regional system proposed

The proponent proposes the East Rocky View regional system if feasible, with approved disposal alternatives if capacity or connection is unavailable.

Sources [7]

Noise

The federal filing says a model was completed, but ADCW did not identify the numerical receptor table in the public summary.

ADCW context

Noise-impact assessment

Numerical receptor table not identified

The public summary says the completed model evaluated cumulative daytime and nighttime sound and low-frequency characteristics at assessed receptors. It identifies engines and generators, exhausts, ventilation openings, coolers, compressors, pumps, and transformers as operational sources, but ADCW did not identify the numerical receptor table in the summary reviewed. The assessment remains a prediction under active AUC review, not an operating measurement.

Sources [7], [1]

Indigenous context

Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. This section brings together the public record on treaty geography, Indigenous ownership, consultation, and community concerns. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.

ADCW context

Treaty geography

Treaty 7 territory

The federal historical treaty-boundary dataset places the project area within Treaty 7. This is geographic context and does not by itself establish project-specific consultation, effects or positions.

Sources [12]
Public record

Federal participation

Indigenous input informed the issues list

IAAC says its Summary of Issues reflected input from Indigenous groups, the public and government authorities. The registry page does not treat that input as a completed Crown consultation determination for all other approvals.

Sources [9], [10]
Public record

Issues identified

Rights, water, cumulative effects and engagement

IAAC asked the proponent to clarify meaningful engagement, impacts on Section 35 rights and traditional land use, clean drinking water and food security, cumulative effects and Indigenous economic benefits.

Sources [9]
ADCW context

Final consultation outcomes

Not found

The reviewed federal, AUC and municipal sources do not provide one complete public record of communities consulted, concerns resolved, accommodation measures or final Crown determinations across all approvals.

Sources [9], [10], [1]

Approval and public process

The federal early decision, provincial power review and Rocky View County's later development-permit process are separate. The federal decision means no further assessment is required under the Impact Assessment Act; it does not approve the project or replace AUC, provincial environmental or municipal authorizations.

Public record

Municipal planning

Area structure plan and redesignation approved

Rocky View County Council approved the planning framework and Special, Data Centre district on June 17, 2025.

Sources [3], [4]
Public record

Municipal construction approval

Development permits still required

The County states that municipal development permits are required even if the AUC approves the power plant.

Sources [3]
Public record

County policy update

Later permits are now discretionary

On July 21, 2026, Council made data-centre campuses discretionary uses and reserved those permit decisions for Council. The separate pause on new S-DAT rezoning decisions does not reverse Beacon's June 2025 redesignation.

Sources [5], [6]
Public record

Federal early decision

No further Impact Assessment Act review

IAAC decided on March 9, 2026 that a further federal impact assessment was not required because potential federal effects could be limited or addressed through existing federal and provincial laws. The notice does not authorize construction.

Sources [10], [8]
Public record

AUC review

Oral hearing held; decision pending

Proceeding 30524 covers the proposed 1.494 GW thermal power plant. The AUC says it held the oral hearing, but has not issued a final decision or stated that the proceeding is formally closed.

Sources [1]
ADCW context

Cumulative-effects evidence

Beacon's review challenged by intervener expert

Dr. Brad Stelfox, retained by the Indus and Area Residents Group and appearing as an independent expert witness, says Beacon and Stantec's review leaves out relevant regional land uses, does not model how effects could build over time, and considers only the Indus data centre despite other operating and proposed projects in the region. This is expert evidence filed by an intervener, not an AUC finding.

Sources [2], [1]
Public record

County participation

Rocky View County is participating

The County identifies noise, emissions, water, agricultural land and rural quality of life among its areas of concern.

Sources [3]
Public record

Public engagement

Open house held April 15, 2025

The event formed part of the area structure plan process. Later regulatory processes have separate participation rules.

Sources [4]

Timeline

Observed decisions and future dates are kept distinct; projected milestones may change.

  1. Public record

    Beacon held a public open house during the area structure plan process. [4]

  2. Public record

    Rocky View County Council approved the area structure plan and land-use redesignation. [3][4]

  3. Public record

    The federal Initial Project Description was accepted into the public registry. [7]

  4. Public record

    The AUC issued notice for Proceeding 30524. [1]

  5. Public record

    IAAC decided that no further federal impact assessment was required. Its notice was published March 10 and did not approve the project. [10][8]

  6. Public record

    Rocky View County made data-centre campuses discretionary uses decided by Council and paused decisions on new S-DAT rezoning applications while it develops an Emerging Sector Strategy and regulatory framework. Beacon's existing redesignation was not reversed. [5][6]

  7. Public record

    The AUC held its oral hearing on the proposed 1.494 GW power plant. No final decision has been issued, and the AUC has not stated that the proceeding is formally closed. [1]

  8. Proponent projection

    The proponent targets initial operation, subject to approvals and construction. [7]

What we still don't know

Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.

  • The AUC has not issued a final decision on the proposed power plant.
  • The federal early decision ended the Impact Assessment Act planning phase without a further assessment. It did not replace project-specific AUC, provincial environmental, water, municipal or other authorizations.
  • Municipal development permits for the data halls and related site construction were not confirmed in the reviewed public record.
  • How Rocky View County's new discretionary permit framework will affect Beacon's later development-permit applications remains unresolved.
  • A final investment decision, committed customers, financing structure and binding construction schedule were not found in the reviewed sources.
  • The reviewed records do not reconcile the 946-acre municipal planning area with the 627.2-acre data-centre campus described in the federal filing.
  • The reviewed records do not reconcile the construction employment estimates of more than 1,500 and up to 4,500 workers.
  • Final water-service agreements, available system capacity, wastewater routing and phase-level demand have not been published.
  • The filing describes carbon-capture readiness and other future mitigation options, but no capture facility, capture rate or operating commitment is established.
  • Final gas-supply infrastructure, grid interconnection arrangements and any export of surplus generation remain unresolved.

Source record

Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.

  1. Proceeding 30524: Beacon AI Centers Indus Project thermal power plant

    Alberta Utilities Commission · Regulator · Updated through 2026-09-09

  2. Exhibit 30524-X0359: Assessment of Beacon's cumulative-effects review

    Dr. Brad Stelfox for the Indus and Area Residents Group, filed with the Alberta Utilities Commission · Intervener evidence · 2026; exact filing date not independently confirmed

  3. Beacon AI Hub Area Structure Plan

    Rocky View County · Municipal record · Updated through July 2026

  4. Beacon AI Hub Area Structure Plan

    Rocky View County · Municipal record · 2025-06-17

  5. Council Decisions: July 21, 2026

    Rocky View County · Municipal record · 2026-07-21

  6. Emerging Sector Strategy

    Rocky View County · Municipal record · Updated through July 2026

  7. Indus Data Center Hub Initial Project Description summary

    Impact Assessment Agency of Canada · Federal filing · 2025-12-29

  8. Beacon AI Centers Indus Project registry

    Impact Assessment Agency of Canada · Federal filing · Updated through 2026-03-10

  9. Summary of Issues

    Impact Assessment Agency of Canada · Federal filing · 2026-02-05

  10. Notice of Early Decision with Reasons

    Impact Assessment Agency of Canada · Regulator · 2026-03-10

  11. Indus data centre frequently asked questions

    Beacon Data Centers · Company disclosure · 2026-02

  12. Treaty Boundary dataset

    Government of Canada Open Government Portal · Government database · Modified 2026-06-29

  13. Beacon Indus Data Center Hub

    Government of Alberta Major Projects · Government database · Accessed 2026-07-28

  14. Beacon commits to an initial 4.5 GW Alberta portfolio

    Beacon AI Centers / Business Wire · Company disclosure · 2025-05-15

  15. Calgary firm eyes $10B AI data centre building blitz

    The Logic · News reporting · 2025-05-15