Bitdeer Fox Creek

Bitdeer is constructing a 101.133 MW natural-gas power plant and an approximately 100 MW computing facility near Fox Creek. Its latest infrastructure table lists cryptocurrency as the planned use, while saying the data centre design is being developed to accommodate both AI data centre and cryptocurrency workloads.

Bitdeer Technologies Group
How to read this profilePublic recordProponent statementProponent projectionADCW context

Project facts

Core scale, approval, employment, and schedule information, labelled by the type of evidence available.

Proponent statement

Computing capacity

Approximately 100 MW

Current planned use is cryptocurrency; the design is intended to retain future AI/HPC capability.

Sources [1], [2]
Public record

Power plant

101.133 MW natural gas

The AUC transferred the existing approval to Bitdeer in 2025.

Sources [3]
Public record

Project status

Under construction

Bitdeer held a groundbreaking in June 2026; Alberta Major Projects also lists the project as under construction.

Sources [1], [4]
Proponent projection

Latest energization target

Fourth quarter of 2027

The August 2026 update replaced the earlier second-quarter 2027 target.

Sources [2]
Proponent statement

Site area

7.7 hectares (19 acres)Sources [1]
Proponent projection

Employment estimate

300 construction; 30 permanent

Company projections, not binding local-employment commitments.

Sources [1]

Energy and emissions

The data centre is intended to receive power directly from a new natural-gas plant. The plant can also connect to Alberta's grid, and Bitdeer says compute could be curtailed so electricity can be exported during grid stress.

Important distinction: The 101.133 MW plant exists principally to supply the co-located computing facility. A 99 MW grid interconnection does not mean the data centre will normally draw 99 MW from the grid.
Public record

Purpose-specific generation

101.133 MW

A flexible natural-gas plant approved by the AUC and now under construction.

Sources [3], [1]
Proponent statement

Computing capacity

Approximately 100 MW

A facility-capacity claim, not measured operating demand.

Sources [1]
Proponent statement

Grid interconnection

99 MW approved

Bitdeer says the plant can export to the grid when computing is curtailed. The reviewed sources do not promise a fixed amount or frequency of grid support.

Sources [1]
Proponent statement

Primary fuel

Natural gas

Bitdeer says it plans carbon-capture-and-use equipment, but ADCW did not find a final design, capture rate, operating commitment or verified emissions reduction.

Sources [1]

Water

Bitdeer describes closed-loop dry cooling and says no nearby surface-water withdrawal is planned. The reviewed sources do not publish other construction, domestic or process-water volumes. [1]

Proponent statement

Cooling

Closed-loop dry cooling proposed

The company says the system will not withdraw water from nearby bodies of water.

Sources [1]
ADCW context

Other water needs

Not quantified

No comparable daily figure for construction, domestic use, fire protection or other site needs was found.

Sources [1]

Noise

Bitdeer says preliminary work is being used to design for Alberta's nighttime limits and promises monitoring after operations begin. It has not published the receptor predictions or monitoring results.

Proponent statement

Preliminary noise work

Receptor values not published

Bitdeer says preliminary studies are being used to design the facility to meet applicable Alberta nighttime noise limits. The published update does not provide the assessed receptors, predicted levels, or a complete mitigation schedule.

Sources [1]
Proponent projection

Operating monitoring

Promised after commissioning

The company says active monitoring will occur once the facility operates. No measured operating results exist yet because construction is still underway.

Sources [1]

Indigenous context

Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. This section brings together the public record on treaty geography, Indigenous ownership, consultation, and community concerns. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.

ADCW context

Treaty geography

Treaty 8 territory

Bitdeer says earlier development included consultation with First Nations, but the reviewed public materials do not identify participating communities, issues raised, outcomes or current positions.

Sources [1], [5]

Approval and public process

The underlying power project was approved before Bitdeer acquired it, and the approval was transferred to Bitdeer in 2025. Construction is now underway, but environmental compliance and final data centre design work continue.

Public record

Power-plant approval

Approval transferred to Bitdeer

AUC Approval 29843-D02-2025 authorizes the 101.133 MW Opal Power Plant under Bitdeer's project company.

Sources [3]
Proponent statement

Environmental approval

EPEA industrial approval reported

Bitdeer reports that the project holds an industrial approval. ADCW has not yet linked the complete approval record in this profile.

Sources [1]
Proponent statement

Current work

Power construction and data centre design

The latest company update says the design is being developed for both AIDC and cryptocurrency use.

Sources [2]

Timeline

Observed decisions and future dates are kept distinct; projected milestones may change.

  1. Public record

    The AUC issued the original approval for the Opal Power Plant. [3]

  2. Proponent statement

    Bitdeer announced acquisition of the licensed and permitted site. [1]

  3. Public record

    The AUC transferred the 101.133 MW approval to Bitdeer's project company. [3]

  4. Proponent statement

    Bitdeer held a groundbreaking and described the project as entering construction. [1]

  5. Proponent statement

    Bitdeer moved its expected energization from Q2 to Q4 2027 and listed cryptocurrency as the planned use. [2]

  6. Proponent projection

    Latest company target for energization. [2]

What we still don't know

Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.

  • The final split between cryptocurrency, AI/HPC and other computing workloads at commissioning.
  • The final data centre design, equipment count and measured operating demand.
  • Project-specific greenhouse-gas, NOx and other emissions totals for the current design.
  • The design, capture rate and operating commitment for the proposed carbon-capture-and-use system.
  • Other water sources and volumes beyond the no-surface-water-withdrawal cooling claim.
  • The complete EPEA approval, monitoring requirements and public compliance record.
  • The frequency and quantity of possible electricity exports to the Alberta grid.
  • A detailed project-specific Indigenous consultation record.

Source record

Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.

  1. Bitdeer breaks ground on Fox Creek facility

    Bitdeer Technologies Group · Company disclosure · 2026-06-02

  2. Second-quarter 2026 results and infrastructure summary

    Bitdeer Technologies Group · Company disclosure · 2026-08-10

  3. Power Plant Approval 29843-D02-2025

    Alberta Utilities Commission · Regulator · 2025

  4. Bitdeer Crypto Mining Facility - Fox Creek

    Government of Alberta Major Projects · Government database · Accessed 2026-08-21

  5. Treaty Boundary dataset

    Government of Canada Open Government Portal · Government database · Modified 2026-06-29