
Armada Nowlit Data Centre Southeast of Clive
A proposed modular data-processing facility and gas power plant southeast of Clive.
Rezoning must be decided before a development-permit application can proceed. No municipal approval is confirmed in this record, and the developer's claim of an AUC application under review has not been verified for Clive.
Where it stands
Separate approval tracks, not a construction progress bar. Record last verified 2026-09-29.
The existing record lists a September 30, 2026 developer meeting and an October 1–15, 2026 survey. Those dates have passed. Separate County engagement has no confirmed date in this record, and December 10, 2026 is only the developer's hearing estimate, not a final notice. See the approval and participation record ↓
Power and emissionsCampus demand, electricity supply, and emissions evidence
The current concept pairs nine natural-gas generator sets with nine co-located miner containers. The developer proposes to consume all electricity on site and not export power to the Alberta grid.
Important distinction: The 19.8 MW figure is proposed gross generation capacity, not a published data-centre load. The Council package says an AUC application is under review, but the AUC's current application list identifies no active Clive proceeding. Earlier ADCW references to proceedings 30385, 30476, and 30709 under Clive were incorrect; those filings concern Gayford.
Proposed generation: Approximately 19.8 MW. Nine proposed 2.2 MW MWM TCG3020-series natural-gas generator sets, subject to final equipment selection. This is gross installed generation capacity, not a verified compute load. The units would be enclosed. Final equipment remains subject to design and procurement. [2][4] Proponent statement
Grid export: None proposed. The developer says all electricity would be consumed by the co-located data-processing equipment, with no export to the Alberta Interconnected Electric System. [2][4] Proponent statement
Natural-gas supply: Existing distribution tie-in proposed. The developer proposes a pipeline tie-in to existing gas distribution infrastructure. The supplier, route, capacity, connection design, and approvals remain unconfirmed. [4] Proponent statement
Emissions controls: Selective catalytic reduction proposed. The current concept includes SCR systems. Final equipment, permit limits, monitoring, and operating conditions are not confirmed in the reviewed record. [2][4] Proponent statement
Short-term nitrogen dioxide: Below Alberta air-quality objective in model. The revised model predicts a maximum one-hour ground-level concentration of 183.7 µg/m³, including estimated background and nearby sources, compared with Alberta's 300 µg/m³ objective. Nitrogen dioxide comes from burning fuel and can increase the risk of breathing problems. This is a prediction, not measured emissions or a regulatory finding. [2][11] Proponent projection
Annual greenhouse-gas emissions: Not found. The developer publishes local air-dispersion results but not a project-specific annual CO₂e estimate in the sources reviewed by ADCW. [2][4] ADCW context
What remains unresolved
The final natural-gas supplier, connection route, contracted capacity, and required pipeline or utility approvals are not disclosed.
A project-specific annual greenhouse-gas estimate, final emissions limits, and monitoring requirements were not found.
Water, cooling, and drainageSupply, demand, wastewater, and servicing
The developer proposes sealed-loop liquid coolingLiquid coolingLiquid carries heat away from computing equipment, for example through cold plates at the chips.This describes how heat leaves the equipment. It does not identify how heat is ultimately released outside, or establish the site's water demand.Learn more → with dry coolersDry coolingDry cooling releases heat to the air without relying on water evaporation for that heat rejection.Fans and other equipment still use electricity and can produce sound. Check whether the design also uses wet or water-assisted equipment during hot weather.Learn more →, a roughly 1,500 L service-water tank, and a separate wastewater holding tank. Wastewater would be removed for off-site servicing with no discharge to land. Earlier application materials describe an initial 250–300 L water-glycol fill per unit and minor trucked top-ups, but do not define the unit or quantify annual water use. No municipal water connection or groundwater well is proposed. Tank capacity is not projected consumption. [2][4]
Cooling system: Closed-loopClosed-loop coolingCooling fluid circulates repeatedly through a contained loop instead of being routinely discharged after one pass.That describes the loop, not the whole site's water use. A separate heat-rejection system can still use water, and filling, maintenance, and leaks also matter.Learn more → dry cooling proposed. The developer proposes a sealed water-glycol loop with dry coolers that recirculates cooling fluid. Final equipment and operating performance are not independently verified. [2][4] Proponent statement
Initial coolant fill: 250–300 L per unit. The developer says the initial water-glycol fill would be trucked to site. The package does not define the unit clearly enough to calculate a reliable project total. [2][4] Proponent statement
Municipal water connection: Not proposed. The developer says the current design would not connect to municipal water. [2][4] Proponent statement
Groundwater well: Not proposed. The developer says the current design would not use an on-site groundwater well. [2][4] Proponent statement
Routine top-up demand: Minor trucked top-ups claimed. The package describes occasional maintenance top-ups but does not quantify their expected frequency, annual volume, leakage, or replacement demand. [2] Proponent statement
Service water and wastewater: Tank and off-site servicing proposed. The developer describes a roughly 1,500 L service-water tank and separate holding tank. It says wastewater would be removed off site with no dischargeWithdrawal, consumption, and dischargeWithdrawal is water taken from a source. Consumption is the portion not returned to the same water system. Discharge is water released after use or treatment.These are different quantities. Check which one a water figure describes before comparing projects.Learn more → to land. Tank capacity is not annual water use; a complete operating water balance and final approvals remain unpublished. [4] Proponent statement
What remains unresolved
Routine cooling-water top-up, total coolant inventory, wastewater volume, off-site servicing arrangements, and emergency spill-management volumes are not quantified.
Sound at nearby communitiesAssessment evidence, controls, and remaining questions
Sound at nearby communities: 36.0 dBA predicted at closest assessed home. The developer's current page reports a 36.0 dBA modelledModelled versus measuredA modelled result is a prediction based on inputs and assumptions. A measured result comes from observations or instruments under particular conditions.A prediction is not verified operating performance. Check the location, period, operating scenario, and what the reported number actually represents.Learn more → nighttime total at the closest assessed residence, about 970 m north, against a stated 40 dBA limit. The earlier application-case assessment reports 35.3–35.9 dBA across receptors with assumed ambient sound; its cumulative case reports 35.4–36.2 dBA. These are different model summaries, not operating measurements. The consultant identified possible low-frequency tonal characteristics but concluded they were unlikely to be an issue because predicted project levels excluding ambient sound were 30 dBA or lower. [4][2] Proponent projection
Land and site layoutSite footprint and the planning information in the record
Rezoning area: 4.40 acres. The application seeks to redesignate 4.40 acres of SE-16-40-24 W4M from Agricultural to Heavy Industrial. The package describes a 4.28-acre facility area and a 0.12-acre access area, leaving approximately 155.60 acres agricultural. [2] Public record
What remains unresolved
The final drainage design, emergency-response arrangements, and cumulative-effects assessment remain unresolved in the reviewed public record.
Indigenous contextTreaty geography, engagement, and consultation evidence
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty geography: Treaty 6 territory. The federal historical treaty-boundary dataset places the project area within Treaty 6. This is geographic context, not evidence of project-specific consultation. [12] ADCW context
Project-specific consultation: Not found. The reviewed public sources do not identify potentially affected First Nations or Métis communities, engagement completed, concerns raised, or accommodation measures for the Clive proposal. [4][2] ADCW context
What remains unresolved
Project-specific Indigenous consultation participants, concerns, outcomes, and accommodation measures were not found.
Approvals and participationSeparate decisions, public participation, and the recorded timeline
Armada Nowlit Energy Ltd., on behalf of landowner Arkham Estates Corporation and Iceline Energy Inc., seeks to redesignate 4.40 acres of SE-16-40-24 W4M from Agricultural to Heavy Industrial. The County says a development-permit application can follow only if rezoning succeeds; the data processing centre would be a discretionary use at that stage. No municipal approval is confirmed. The developer meeting is September 30, 2026, with a survey scheduled for October 1–15, 2026; separate County engagement and a formal hearing would follow the County process. December 10, 2026 remains the developer's unconfirmed hearing estimate.
AUC status conflict: No active Clive application identified. The Council presentation says an AUC application is submitted and under review. The AUC's current application list identifies Armada Nowlit's Proceeding 30983 for a separate 4.88 MW Red Deer County facility, not Clive. Proceedings 30385, 30476, and 30709 are tied to Gayford in Rocky View County and are now tracked separately. [2][7] ADCW context
Power-plant regulator: Alberta Utilities Commission. The AUC reviews power generation, transmission, and grid connections. Lacombe County says the AUC is the primary approval authority for a natural-gas power plant. [8] Public record
Rezoning before permit: 4.40 acres to Heavy Industrial. Lacombe County says Armada Nowlit Energy Ltd. seeks redesignation on behalf of landowner Arkham Estates Corporation and Iceline Energy Inc. The data processing centre would be a discretionary use in a later development-permit application, possible only after successful rezoning. Rezoning itself would not authorize construction. [3] Public record
AEPA approval claim: Draft approval claimed; instrument not identified. The presentation lists Alberta Environment and Protected Areas at 'Draft Approval' but provides no approval number, authorization type, conditions, or copy. ADCW did not identify a project-specific approval in the reviewed official record. [2][8] ADCW context
Developer meeting: September 30, 2026, 6–8 p.m.. Tees Community Hall. Lacombe County confirms this developer-hosted public information meeting. [1] Public record
Developer feedback survey: October 1–15, 2026. The developer says its survey opens October 1 and closes October 15, 2026, at 11:59 p.m. This is separate from the County's required public hearing. [4] Proponent statement
Separate County engagement: Late 2026 or early 2027. County-led public engagement is separate from the developer meeting and from a formal rezoning hearing. A specific date has not been announced. [1] Public record
Estimated public hearing: December 10, 2026. The date appears in the developer's proposed schedule. It is not a final hearing notice or evidence that Council has advanced the application. [2] Proponent projection
Recorded timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
April 2025. The federal Investment Canada Act index records a new-business notification by Armada Nowlit HK Limited, associated with Armada Nowlit Power Ltd., Armada Nowlit Energy Ltd., and Armada Nowlit Canada Holding Limited. [10] Public record
July 20, 2026. The revised air-dispersion model described the nine data buildings as miner containers MC1 to MC9. [2] Proponent statement
August 27, 2026. The County confirms that no municipal approvals have been granted and announces public engagement opportunities. [1] Public record
September 30, 2026. Confirmed developer meeting, 6–8 p.m., Tees Community Hall. [3] Public record
October 1–15, 2026. Developer feedback survey scheduled following the public meeting; this is separate from County engagement. [4] Proponent statement
Late 2026 or early 2027. Separate County-led engagement is planned; no specific date has been announced. [1] Public record
December 10, 2026. The developer's schedule estimates a municipal public hearing. This is not a final hearing notice. [2] Proponent projection
March–April 2027. The developer targets an approximately one-month construction period, subject to engineering and required approvals. [2][4] Proponent projection
April–May 2027. The developer targets commercial operation. No approved or binding in-service date was found. [2][4] Proponent projection
What remains unresolved
Whether Armada Nowlit will submit a Clive-specific AUC application. ADCW could not verify the package's claim that one is currently under review.
Whether Lacombe County will approve the requested redesignation and any later development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more →, road-use agreement, or other municipal authorization.
What the presentation's 'Draft Approval' from Alberta Environment and Protected Areas refers to, including the authorization type, number, conditions, and current status.
Company and commitmentsScale, projected benefits, and delivery commitments
Data-processing buildings: Nine miner containers. The revised July 20, 2026 air-dispersion model labels the nine data buildings as miner containers MC1 to MC9. The package does not identify a customer, installed computing hardware, a specific cryptocurrency, or the share of capacity intended for mining. [2] Proponent statement
Workload evidence: Digital-asset mining and AI marketed. Armada Nowlit says its data centres support digital-asset and AI computing, and Nowlit markets ASIC and GPU infrastructure, blockchain, and mining services. Together with the miner-container description, this is direct evidence of mining-oriented infrastructure, but it does not confirm a specific coin or workload split at Clive. [2][5][6][9] ADCW context
Construction period: Approximately one month. The developer targets a March 2027 start and April 2027 completion, subject to approvals. The traffic assessment estimates 250–450 loaded truck events, or 500–900 one-way heavy-vehicle movements, with no night hauling proposed. [2] Proponent projection
On-site workforce: Proponent documents conflict. The presentation projects 20–50 temporary construction jobs and 10–20 ongoing operations and service roles. The submitted traffic assessment instead assumes about 10 people on site on a typical construction day, no more than 15 at peak, and a normally unstaffed operating facility with one to three maintenance or service visits per month. [2] ADCW context
Clive investment: Approximately US$2 million claimed. The developer's presentation describes private infrastructure investment at Clive. ADCW did not independently verify the estimate, and it should not be confused with broader company-wide investment claims. [2] Proponent projection
Foreign investment record: Hong Kong new-business notification. The federal Investment Canada Act index records an April 2025 new-business notification by Armada Nowlit HK Limited, Central, Hong Kong SAR, China, associated with Armada Nowlit Power Ltd., Armada Nowlit Energy Ltd., and Armada Nowlit Canada Holding Limited. The index lists the ultimate controller's country of origin as Hong Kong SAR, China. It does not disclose an ownership percentage, investment amount, Chinese state ownership, or ownership of the Clive land. [10] Public record
Target operation: April–May 2027. A developer schedule subject to engineering, approvals, and construction. It is not a regulatory deadline or confirmed in-service date. [2][4] Proponent projection
Who pays for cleanup?: C$1.96 million estimated; no security confirmed. The developer estimates cleanup at about C$1.96 million and proposes arranging a bond or similar guarantee later. The package does not show that this money is secured, who could access it if the company failed to clean up, or whether the estimate would keep pace with rising costs over the project's life. [2] ADCW context
Project overview
Armada Nowlit Energy Ltd. seeks rezoning on behalf of landowner Arkham Estates Corporation and Iceline Energy Inc. for an approximately 19.8 MW modular data-processing facility and natural-gas power plant at 40205 Range Road 243, southeast of Clive. The submitted package calls the data buildings miner containers, and company materials market digital-asset and AI computing, providing direct evidence of mining-oriented infrastructure without identifying a customer, installed hardware, specific cryptocurrency, or workload split. Lacombe County must decide the rezoning before a development-permit application can be made. The package says an AUC application is under review, but ADCW found no active Clive application.
What remains unresolved
The separate data-centre electrical load, customer, installed computing hardware, specific cryptocurrency, and expected split between digital-asset mining and AI workloads.
Why the presentation projects 10–20 ongoing roles while the traffic assessment describes a normally unstaffed facility with one to three maintenance or service visits per month.
Whether cleanup security will be required before construction, who would hold or enforce it, and how the amount would be adjusted as costs rise.
Final equipment procurement, customer commitments, project financing, and a binding construction schedule are not publicly confirmed.
Unresolved questions are retained within each relevant topic above.
SourcesOriginal documents and publication details
Source record
Company disclosures establish what the company said, not independent verification of projected outcomes.
- Lacombe County expands public information as Natural Gas Power Plant/Data Centre proposal enters review processLacombe County · Municipal record · 2026-08-27
- August 27, 2026 Council agenda: Armada Nowlit Energy Ltd. Clive FacilityLacombe County · Municipal record · Meeting scheduled 2026-08-27
- Armada Nowlit Energy Ltd. | Proposed Clive FacilityLacombe County · Municipal record · Accessed 2026-09-29
- Proposed Clive FacilityNowlit Solutions Corp. · Company disclosure · Accessed 2026-09-29
- Armada Nowlit corporate siteArmada Nowlit · Company disclosure · Accessed 2026-08-25
- Infrastructure and computing servicesNowlit · Company disclosure · Accessed 2026-08-25
- Current applicationsAlberta Utilities Commission · Regulator · Accessed 2026-08-25
- Data Centre & Natural Gas Power Generation Projects FAQsLacombe County · Municipal record · Accessed 2026-09-27
- Data Center, CliveGovernment of Alberta Major Projects · Government database · Accessed 2026-08-25
- Investment Canada Act: index of decisions and notificationsInnovation, Science and Economic Development Canada · Government database · April 2025 notification; accessed 2026-08-25
- Air indicators – Nitrogen dioxideGovernment of Alberta · Government database · Updated February 2026
- Treaty Boundary datasetGovernment of Canada Open Government Portal · Government database · Modified 2026-06-29