Grassland and rolling hills beneath a cloudy blue sky
Evidence profile · Rocky View County

eStruxture CAL-3

An AI-ready colocation facility under construction in Rocky View County.

Illustrative landscape · Sevgi Gümüş / Pexels
← Alberta data centre project list
Developer eStruxture Data CentersView on project map ↗

200 High Plains Common, Rocky View County · Map precision: Exact site

County development and building permits are issued. Commercial service is not confirmed, and the installed diesel backup generators remain subject to a separate AUC decision in this record.

Facility power90 MWDesign rating; includes 70 MW for computing equipment [7]
Water allocation2,560 L/dayProperty allocation, not actual use or cooling demand [1]
Normal-operation sound43–45 dBAEarlier design model with generators off and barriers in place [4]
Permanent jobsNot confirmedJob numbers and binding local benefits remain unknown
Backup CO₂ emissions32 tonnes/hourEstimate for 19 generators; annual total not published [3]
Site area12.6 acresCompany data sheet; Phase 1 building is 205,000 sq. ft. [7]

Where it stands

Municipal permitsPermits issuedDevelopment and building permits; conditions remain separate [1][13][14]
Backup generatorsAUC decision pendingProceeding 31020; installed before the application [12]
Commercial serviceNot confirmedCommissioning and occupancy permission remain unverified [5][8]

Separate approval tracks, not a construction progress bar. Record last verified 2026-10-06.

Want to get involved?

The recorded municipal appeal deadline was July 8, 2025. The backup-generator application has a separate participation record; these sources do not establish a current submission window. See the approval history and official sources below. See the approval and participation record ↓

Federal principles: eStruxture is listed as a signatory to Canada's five responsible data-centre development principles. This is a company commitment, not a project approval or permit condition. What the five principles mean →

Power and emissionsCampus demand, electricity supply, and emissions evidence

eStruxture plans 90 MW of total facility power, including 70 MW for computing equipment. These are design ratings. Actual electricity use will depend on how much of the facility is operating.

Important distinction: The first 45 MW of data-centre load would be served by three FortisAlberta distribution lines. Diesel generators would provide backup during outages. Their combined 66.75 MW rating includes spare capacity for reliability and is counted separately from data-centre demand.

Total facility power: 90 MW. The current data sheet's total-power rating for the completed design, not measured demand. [7] Proponent statement

Power for computing equipment: 70 MW. This is the computing portion of the 90 MW total facility rating, not another 70 MW on top of it. [7] Proponent statement

Utility service: Multiple FortisAlberta lines. The data sheet identifies multiple 15 MW utility lines serving dedicated electrical lineups and lists Fortis as the power provider. [7] Proponent statement

Rack density: Up to 125 kW+ per cabinet. A maximum design capability for selected deployments, not the average density of every rack. [7][5] Proponent statement

Diesel backup powerBackup generationBackup generators provide electricity when the normal supply is unavailable. They may also run for testing or maintenance.Installed capacity does not establish continuous operation, annual fuel use, or emissions. Operating hours and permit conditions are separate evidence.Learn more →: 21 generators / 66.75 MW. The application covers twenty 3.25 MW units and one 1.75 MW unit for life-safety systems. Up to 19 would run together during an outage. Their combined rated capacity includes redundancy and is separate from the data centre's electricity demand. [12] Proponent statement

Generators installed before filing: AUC application submitted afterwards. eStruxture says it missed the AUC approval requirement because of an administrative oversight. It had already bought and installed the generators when it applied. The company said they had not been tested or operated as of August 28, 2026. [12] Proponent statement

Generator testing: Monthly, one unit at a time. eStruxture proposes daytime tests of up to 30 minutes per generator. Its submitted policy prefers weekdays from 9 a.m. to 4 p.m., excluding statutory holidays. The policy is still marked for approval and leaves minimum test duration and load blank. [12][2] Proponent statement

Reliability design: Tier III designed. The design aims to allow maintenance without interrupting service. eStruxture lists Uptime Institute Tier III by Design as a planned certification; ADCW has not confirmed that certification has been issued. [7][5] ADCW context

Diesel use and carbon emissions: 11,920 L/hour and 32 tonnes CO₂/hour. These are eStruxture's estimates for 19 generators running at the loads listed in its filing. They show the scale of that backup-power scenario. Actual fuel use and annual emissions will depend on how often, how long, and at what load the generators run; those totals are not published. [3] Proponent projection

Other diesel emissions: Hourly estimates for 19 generators. The same scenario estimates 310 kg of nitrogen oxides and non-methane hydrocarbons combined, 170 kg of carbon monoxide, 9.7 kg of particulate matter, and 0.30 kg of sulphur dioxide per hour. These are amounts released by the generators. They do not show what people would breathe at nearby homes. [3] Proponent projection

Backup power during an outage: Several generators may run overnight. The submitted policy allows generators to run together, at high load, for as long as needed during a loss of utility power, including overnight. The weekday testing schedule does not limit that emergency response. The policy is marked for approval, so these provisions are not confirmed AUC approval conditions. [2] Proponent statement

Air quality at nearby homes: Supporting results not included. eStruxture says the generators would meet Alberta's nitrogen dioxide air-quality objectives. The supplied attachment lists hourly emissions, but does not show how pollutants would spread or their predicted concentrations near the ground. It therefore does not provide the results needed to assess that claim. [12][3] ADCW context

What remains unresolved

How much electricity CAL-3 actually uses over a day or year, and the details of its utility contract and electricity supply mix.

How often and how long the generators will run, their annual emissions, and predicted air quality at nearby locations.

Whether the four extra unallocated generators listed in the operating policy are intended for this application or a later stage.

Water, cooling, and drainageSupply, demand, wastewater, and servicing

Water and wastewater servicing: 2,560 L/day allocated to the property. The permit requires demand calculations and connections to High Plains Industrial Park's drinking-water and wastewater systems, with extra water capacity to be purchased if needed. This is an allocation, not measured use or a confirmed cooling-water requirement. [1] Public record

Cooling design and water needs: Air cooling and closed-loopClosed-loop coolingCooling fluid circulates repeatedly through a contained loop instead of being routinely discharged after one pass.That describes the loop, not the whole site's water use. A separate heat-rejection system can still use water, and filling, maintenance, and leaks also matter.Learn more → liquid coolingLiquid coolingLiquid carries heat away from computing equipment, for example through cold plates at the chips.This describes how heat leaves the equipment. It does not identify how heat is ultimately released outside, or establish the site's water demand.Learn more →. eStruxture describes air cooling combined with liquid delivered directly to computer chips, with the mix varying by deployment density. Closed-loop cooling recirculates fluid. The company says it has moved away from public water for cooling, but initial fill and ongoing top-up needs are not disclosed. The site's servicing requirements still apply; total actual water use, wastewater, and dischargeWithdrawal, consumption, and dischargeWithdrawal is water taken from a source. Consumption is the portion not returned to the same water system. Discharge is water released after use or treatment.These are different quantities. Check which one a water figure describes before comparing projects.Learn more → volumes remain unknown. [7][18][1] ADCW context

What remains unresolved

How much water is needed to fill and top up the cooling system, total site water use, and wastewater and discharge volumes.

Expected electricity and water efficiency, measured performance, and whether waste heat will be reused.

Sound at nearby communitiesAssessment evidence, controls, and remaining questions

Sound during normal operation: 43–45 dBA at four nearby locations. The March 20, 2025 study predicts these levels with the generators off and sound barriers in place. It assessed an earlier design with two buildings and 144 chillers. These are predictions, not measurements of the completed facility. [4] Proponent projection

Sound during generator testing: 47–53 dBA during the day. The study describes testing one generator at a time, although its equipment list also mentions ten per phase. It does not show how loud an outage would be with several generators running together. eStruxture claims the smaller fleet would reduce generator sound by about 5.35 dB, but supplies no updated predictions at nearby locations. [4][12] ADCW context

What remains unresolved

How loud the final design would be at nearby homes, particularly when several generators run together during an outage.

Land and site layoutSite footprint and the planning information in the record

Phase 1 building: 205,000 sq. ft.. The company data sheet lists six data halls with 51,750 square feet of space for computing equipment on a 12.6-acre site. [7] Proponent statement

Indigenous contextTreaty geography, engagement, and consultation evidence

Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.

Treaty geography: Treaty 7 territory. The federal historical treaty-boundary dataset places the project area within Treaty 7. This is geographic context and does not establish project-specific consultation, effects, or community positions. [19] ADCW context

Application notification: Seven First Nations notified. The applicant says it notified Kainai, Piikani, Siksika, Tsuut'ina, and the Bearspaw, Chiniki, and Goodstoney Nations. It reported no questions or comments by August 28, 2026. This is the applicant's participation record, not evidence of consent or an AUC finding on consultation. [12] Proponent statement

What remains unresolved

Any First Nations engagement after the applicant's August 28, 2026 notification record, including concerns and measures to address them.

Approvals and participationSeparate decisions, public participation, and the recorded timeline

County permits allow the development to proceed, subject to their conditions. The diesel backup generators need a separate AUC approval. eStruxture says it installed them before applying. Completion of permit conditions, permission to occupy the building, and the start of commercial service remain unconfirmed.

Development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more → issued: October 17, 2025. The issued permit covers the same property and data centre tenancy as the June 17, 2025 public notice. The documents do not explain the gap between the dates or confirm that all permit conditions have been met. [1][11] Public record

Development approval: PRDP20251314. The County's approved-permit notice covers an office and warehouse building accommodating a data centre at Lot 12, Block 7, Plan 2410651; NE 12-26-29-W4M. [11] Public record

Public notice and appeal: Appeal deadline July 8, 2025. The reviewed County search did not identify a later appeal decision. Subsequent building permits and construction records show the project continued. [11][13][14] ADCW context

New-construction permit: PRBD20255100. The November 2025 County report lists 27,263 m² and an estimated construction value of CA$24.0 million at the CAL-3 address. This permit value is not the project's full capital cost. [13] Public record

Alteration permit: PRBD20258056. The April 2026 County report lists 4,020 m² and an estimated construction value of CA$5.15 million at the same address. It should not be added to company investment claims without a complete cost reconciliation. [14] Public record

County sector research: Report received for information. The County's commissioned report considers infrastructure capacity, agricultural land, water, energy, and municipal policy at a sector level. Council received it on September 22, 2026. It is not a site-specific assessment, adopted policy, or a change to CAL-3's existing permits. [15][16] ADCW context

County policy context: CAL-3 recognized as an East Balzac development. Rocky View County publicly identified CAL-2 and CAL-3 while describing its broader approach to responsible AI data centre development. [17] Public record

Standby-generator application: AUC decision pending. Proceeding 31020 requests approval for the already-installed emergency standby generators. The application asked for a decision by September 29, 2026; that is the applicant's requested date, not a regulator deadline or approval. The filing is not an approval or operating authorization. [12] ADCW context

Participant involvement: No unresolved concerns reported by applicant. The participation program used a 2 km notification radius and 800 m consultation radius. One landowner asked about noise and later reported no concerns. Rocky View County said it had not independently verified the technical, environmental, fuel, emissions, noise, safety, or emergency-response information. [12] Proponent statement

Has the facility opened?: Not yet confirmed. The launch event and tenant announcement do not confirm that testing is complete, occupancy permission has been granted, or customers are operating at the site. [5][8] ADCW context

Recorded timeline

Observed decisions and future dates are kept distinct; projected milestones may change.

October 29, 2024. eStruxture announced CAL-3 as a 90 MW project with more than CA$750 million planned for the full build and a second-half 2026 target. [9] Proponent statement

June 17, 2025. Rocky View County published the approved development-permit notice for PRDP20251314 at 200 High Plains Common. [11] Public record

October 17, 2025. The attached municipal development permit PRDP20251314 was issued with water, wastewater, and other servicing conditions. [1] Public record

November 2025. The County recorded new-construction Building Permit PRBD20255100 at the CAL-3 address. [13] Public record

April 2026. The County recorded alteration Building Permit PRBD20258056 at the same address. [14] Public record

May 14, 2026. eStruxture announced CoreWeave as the Phase 1 anchor tenant and retained a second-half 2026 service target. [8] Proponent statement

August 28, 2026. eStruxture filed Proceeding 31020 for 21 diesel emergency standby generators. It disclosed that the units had already been procured and installed, but said no testing or operation had occurred. [12] Proponent statement

September 30, 2026. Applicant's target for the first 15 MW of Phase 1 data-centre load. This is not a confirmed in-service date. [12] Proponent projection

November 30, 2026. Applicant's target for 30 MW cumulative Phase 1 load. This remains subject to approvals and commissioning. [12] Proponent projection

March 31, 2027. Applicant's target for the full 45 MW Phase 1 load described in the standby-generator filing. [12] Proponent projection

What remains unresolved

Whether commissioning is complete, occupancy permission has been granted, and commercial service has begun.

The AUC decision and any conditions on testing or operating the backup generators.

Company and commitmentsScale, projected benefits, and delivery commitments

Announced investment: More than CA$750 million. eStruxture's CAL-3 full-build estimate, also listed as CA$750 million by Alberta Major Projects. A later company statement describes more than CA$1 billion invested across Alberta's digital infrastructure more broadly, not a revised CAL-3-only cost. [9][10][8] ADCW context

Anchor tenant: CoreWeave. CoreWeave committed to an undisclosed portion of Phase 1 capacity for AI cloud infrastructure. eStruxture does not publish the tenant's contracted MW. [8] Proponent statement

Phase 1 availability: Sold out. An operator claim. The remaining tenants, contracted capacity, and workload mix have not been disclosed. [6] Proponent statement

Target opening: Fall 2026. eStruxture's target depends on testing and bringing systems into service, permission to occupy the building, utility readiness, and customers moving in. An opening date has not been confirmed. [5][8] Proponent projection

Project overview

CAL-3 is under construction at 200 High Plains Common in Rocky View County. eStruxture describes a completed design with 90 MW of total power, including 70 MW for computing equipment, and names CoreWeave as its first-phase anchor tenant. The County has issued development and building permits. A separate application to the Alberta Utilities Commission (AUC) covers 21 diesel backup generators. eStruxture says it installed them before submitting the required application, but had not tested or operated them as of August 28, 2026.

What remains unresolved

How much capacity CoreWeave has contracted, who the other customers are, and what workloads they will run.

Whether planned Tier III and other certifications have been issued.

How the full-project investment estimate relates to the separate building-permit values and the company's broader Alberta investment.

Construction and permanent job numbers, local spending, tax revenue, and any binding community-benefit commitments.

Unresolved questions are retained within each relevant topic above.

SourcesOriginal documents and publication details

Source record

Company disclosures establish what the company said, not independent verification of projected outcomes.

  1. Proceeding 31020, X0001: development and building permitsRocky View County, filed with the Alberta Utilities Commission · Municipal record · Filed 2026-08-28
  2. Proceeding 31020, X0009: submitted standby generator operating policyeStruxture Data Centers, filed with the Alberta Utilities Commission · Regulatory filing · Filed 2026-08-28
  3. Proceeding 31020, X0010: standby generator hourly emissionseStruxture Data Centers, filed with the Alberta Utilities Commission · Regulatory filing · Filed 2026-08-28
  4. Proceeding 31020, X0013: March 20, 2025 sound assessmenteStruxture Data Centers, filed with the Alberta Utilities Commission · Regulatory filing · Filed 2026-08-28
  5. CAL-3 data centreeStruxture Data Centers · Company disclosure · Accessed 2026-08-27
  6. Calgary data centreseStruxture Data Centers · Company disclosure · Accessed 2026-08-27
  7. CAL-3 data sheeteStruxture Data Centers · Company disclosure · Accessed 2026-08-27
  8. CoreWeave announced as CAL-3 anchor tenanteStruxture Data Centers · Company disclosure · 2026-05-14
  9. CAL-3 investment announcementeStruxture Data Centers · Company disclosure · 2024-10-29
  10. eStruxture CAL-3 Data CentreGovernment of Alberta Major Projects · Government database · Accessed 2026-08-27
  11. Approved development permits: June 17, 2025Rocky View County · Municipal record · 2025-06-17
  12. Proceeding 31020: CAL-3 emergency standby generator facility application and attachmentsAlberta Utilities Commission · Regulator · 2026-08-28
  13. November 2025 major construction permitsRocky View County · Municipal record · 2025-12-04
  14. April 2026 major construction permitsRocky View County · Municipal record · 2026-05-05
  15. Emerging Sector Strategy: Data Centre Technology, Impacts, and Municipal Policy ConsiderationsEXP Services and Urbanics for Rocky View County · Municipal record · 2026-08-14
  16. Council Decisions: September 22, 2026Rocky View County · Municipal record · 2026-09-23
  17. Responsible AI data centre developmentRocky View County · Municipal record · 2025-09-18
  18. The New Homesteaders of the Digital WesteStruxture Data Centers · Company disclosure · 2026-05-07
  19. Treaty Boundary datasetGovernment of Canada Open Government Portal · Government database · Modified 2026-06-29