Grassland and rolling hills beneath a cloudy blue sky
Evidence profile · County of Newell

FingerMotion Brooks Campus Zone

Brooks Campus #1 near Tilley would be the first of about ten planned data-centre campuses in a program of up to 100 MW. The first site would use 9.9 MW of on-site natural-gas generation to power customers’ computing equipment.

Illustrative landscape · Sevgi Gümüş / Pexels
← Alberta data centre project list
Developer FingerMotion and Genius Group, with BlueFlare Energy Solutions Inc. as the proposed builder and operatorView on project map ↗

Brooks Campus #1, near Tilley, County of Newell · Map precision: Approximate area

The first campus would redevelop an existing industrial site beside a natural-gas facility near Tilley in the County of Newell. On September 29, 2026, FingerMotion announced an agreement to buy Newbit Technology Inc., the company holding the site lease, permits, and infrastructure, for US$2.3 million. Completion of that purchase remains unconfirmed. FingerMotion, Genius Group, and BlueFlare are proposing the wider Brooks Corridor program for artificial intelligence and other demanding computing work. BlueFlare would build and run the campus, while customers would bring their own computing equipment. The November 5, 2026 agreements describe site companies owned 75% by FingerMotion and 25% by Genius Group, following the September 15, 2026 plan for FingerMotion to own them entirely.

First-site generation9.9 MWProposed gas generators; this is not the computing equipment’s power demand [14][15]
Equipment coolingLiquid coolingProposed in the November 4, 2026 customer-interest announcement [2]
Possible first customerUp to 7 MWPower for its computing equipment; no binding customer contract signed [2]
Who would own each site?75% / 25%FingerMotion / Genius Group under the announced plan; transfer not confirmed [1]
Wider programUp to 100 MWAbout ten planned campuses; may overlap the earlier 99 MW plan [1][8][2]
First-site locationNear TilleyCounty of Newell; map marker is approximate [2][14]

Where it stands

Working togetherBinding agreements signedThe November 5, 2026 deal covers the wider program and first site [1]
Buying and funding the siteRequirements still to be metCompletion depends on a customer contract, funding, checks of the deal and site, and other conditions [15][1]
Permission to build and operateApprovals still to verifyExisting permits are reported, but approval for replacement generators and construction are not confirmed [15][1]

Separate approval tracks, not a construction progress bar. Record last verified 2026-11-08.

Want to get involved?

ADCW has not identified a current hearing or deadline for comments on this specific site in the reviewed sources. The County’s wider data-centre rules are separate from permission to build this project. Check County of Newell notices and any future AUC application for opportunities to take part. See the approval and participation record ↓

Check County of Newell public hearings

Power and emissionsCampus demand, electricity supply, and emissions evidence

The plan is to generate electricity at the site using natural gas. Customers would bring their own computing equipment and rent space, power, cooling, and supporting services.

Important distinction: 9.9 MW describes the proposed generators at this first site. Up to 7 MW describes one possible customer’s computing equipment’s power needs. Up to 100 MW describes the wider program of planned campuses. These figures describe different parts of the proposal and should not be added together.

Securing a gas supply: The earlier gas contract ended after the site stopped taking gas. Completing the purchase requires a new supply agreement with Pivotal Energy Partners, consent from Pivotal and the Eastern Irrigation District, and satisfactory completion of the remaining checks of the deal and site.. [15] Proponent statement

Approval for new generators: FingerMotion says it would be responsible for obtaining any required AUC approval for different generators after completing the purchase. Buying the company and its existing rights would not, by itself, mean that the new generators can operate or that a paying computing customer has signed up.. [15] Proponent statement

How the 100 MW and 99 MW plans relate: On September 15, 2026, FingerMotion described ten 9.9 MW sites across Brooks, Coronation, Fox Creek, and Vulcan. Together, they would have 99 MW of generating capacity and about 72 MW available continuously for computing equipment. The company did not say how the ten sites would be divided among those locations. Its November 4, 2026 announcement still placed Brooks in that program. The November 5, 2026 announcement calls the newer plan the Brooks Corridor and describes up to 100 MW. It is not clear which sites the two plans share, so ADCW does not add their capacity figures together.. [8][2][1] Proponent statement

Proposed generation: 9.9 MW of on-site natural-gas power. This is how much electricity the proposed generators could produce. It does not show how much the computing equipment would use or how much electricity the site is producing. [14][15] Proponent statement

Existing generators and replacement units: The old generators are not included in the purchase. The agreement requires the old generators to be removed before the purchase is completed. FingerMotion says it would then be responsible for any AUC approval needed for different generators. [15] Proponent statement

Gas supply: The purchase requires a new gas-supply agreement. The earlier contract ended after the site stopped taking gas. A new agreement with Pivotal Energy Partners and the required consents are needed to complete the purchase. Having gas pipes nearby does not mean the site has a signed supply contract. [15][1] Proponent statement

What remains unresolved

Which sites are shared between the earlier 99 MW plan and the newer plan for up to 100 MW?

What equipment would be installed, has gas supply been contracted, what emissions are expected, has construction begun, and when could customers start using the site?

Water, cooling, and drainageSupply, demand, wastewater, and servicing

The November 4, 2026 announcement proposes liquid coolingLiquid coolingLiquid carries heat away from computing equipment, for example through cold plates at the chips.This describes how heat leaves the equipment. It does not identify how heat is ultimately released outside, or establish the site's water demand.Learn more → for the computing equipment. It does not say how much water the site would need. [2]

Cooling design: Liquid cooling is proposed for the computing equipment. The November 4, 2026 announcement does not say how much water would be needed to fill the system, keep it topped up, or serve the rest of the site. The water source, wastewater arrangements, and dischargeWithdrawal, consumption, and dischargeWithdrawal is water taken from a source. Consumption is the portion not returned to the same water system. Discharge is water released after use or treatment.These are different quantities. Check which one a water figure describes before comparing projects.Learn more → volumes are also not published in the reviewed material. [2] ADCW context

What remains unresolved

Where would water come from, how much would be needed to fill and top up the cooling system and serve the site, and how would wastewater be handled?

Sound at nearby communitiesAssessment evidence, controls, and remaining questions

ADCW has not reviewed a study showing how loud the generators and cooling equipment would be at nearby communities.

Sound at nearby communities: No reviewed study shows levels at nearby communities. The reviewed announcements do not provide predicted or measured sound levels, or explain what noise controls would be required for the new generators and cooling equipment. [15][2] ADCW context

What remains unresolved

How loud would the site be at nearby communities, and what noise controls would be required?

Land and site layoutSite footprint and the planning information in the record

Buying the site rights: FingerMotion announced on September 29, 2026 that it had agreed to buy 100% of Newbit Technology Inc. for US$2.3 million. The agreement was signed September 23, 2026 and set October 29, 2026 as its deadline for completing the deal. Buying Newbit would give FingerMotion the company and its site rights, not outright ownership of the leased land. The November 5, 2026 announcement still lists conditions to be met. ADCW has not confirmed that the purchase was completed.. [14][15][1] Proponent statement

What is already at the site: The announced purchase includes gas pipes and metering equipment, a Canadian Natural Resources Limited road-use agreement, and existing site improvements. These are assets already associated with the site. Their presence does not show that the proposed data-centre buildings or replacement generators have been built.. [14][15] Proponent statement

Indigenous contextTreaty geography, engagement, and consultation evidence

Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.

Treaty geography: Treaty 7 territory. This describes where the site is, based on ADCW’s existing geographic record. It does not establish which communities were consulted, whether they consented, or their views on the project. ADCW context

What remains unresolved

Which Indigenous communities have been engaged or consulted, and what does the project-specific record show?

Approvals and participationSeparate decisions, public participation, and the recorded timeline

There are several separate steps: buying Newbit and its site rights, putting the site into the partners’ ownership arrangement, securing customers and funding, and obtaining any approvals needed for the new equipment. Signing an agreement to work together does not complete those steps.

Who would build it: The November 5, 2026 announcement says BlueFlare Energy Solutions would develop, build, and run the site. FingerMotion and BlueFlare would arrange power, funding, and customers, while Genius Group would lead community and training programs. Before the first-site deal can be completed, the partners need a signed customer contract backed by financial security, committed funding, the required BlueFlare agreements, satisfactory checks of the deal and site, and regulatory approvals. The company aims to make land with power available in the first quarter of 2027. That is a target, not a confirmed date for customers to start using the data centre.. [1] Proponent statement

Reported permits and land lease: FingerMotion says Newbit holds an Eastern Irrigation District lease allowing use of the land, Development PermitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more → 2022055, building and electrical permits, an environmental approval, and a registration under Alberta Utilities Commission (AUC) Rule 007. ADCW has not reviewed the permits themselves, so their exact conditions and coverage remain unresolved.. [14][15] Proponent statement

Company timelines: The September 15, 2026 plan aimed to secure permits by the end of the first quarter of 2027, start supplying electricity in late fourth quarter 2026, and hand over data halls about 18 months after each permit. The November 5, 2026 Brooks announcement targets land with power available in the first quarter of 2027. Supplying electricity, preparing land, and handing over a finished data hall are different milestones. None of these targets proves the work has been completed.. [8][1] Proponent statement

County rules and site approval: The County of Newell held a public hearing on proposed Bylaw 2129-26 on September 10, 2026 and listed a related petition on its September 24, 2026 Council agenda. ADCW has not confirmed whether the bylaw was finally adopted. These proposed rules would apply to future applications across the County. They are not a permit approving this Brooks project.. [10][11][12] Proponent statement

Buying the company and getting permission to build: Buying Newbit would not itself approve the new data centre. FingerMotion reports that Newbit has existing site rights and permits, but ADCW has not reviewed the permits themselves. The November 5, 2026 announcement still lists regulatory approvals among the requirements for completing the deal. [15][1] ADCW context

Recorded timeline

Observed decisions and future dates are kept distinct; projected milestones may change.

September 10, 2026. FingerMotion announced a binding commitment to acquire rights and permitting for the first 9.9 MW County of Newell site. [7] Proponent statement

September 15, 2026. FingerMotion described ten 9.9 MW sites across Brooks, Coronation, Fox Creek, and Vulcan, totalling 99 MW of generating capacity. It said it would fully own the companies holding each site. [8] Proponent statement

September 29, 2026. FingerMotion announced an agreement to buy Newbit for US$2.3 million, subject to conditions. The agreement was dated September 23, 2026 and set October 29, 2026 as the deadline for completing the purchase. [14][15] Proponent statement

October 1, 2026. The Hanna purchase announcement described that site as additional to the earlier 99 MW program; Hanna is tracked separately. [5] Proponent statement

October 15, 2026. FingerMotion reported non-binding Brooks customer interest and separately announced participation in a proposed east-central Alberta energy park. [3] Proponent statement

October 29, 2026. FingerMotion announced a separate preliminary plan to combine its business with BlueFlare Group Holdings. That plan does not commit the companies to completing the merger. [4] Proponent statement

November 4, 2026. FingerMotion said an unnamed customer, represented by Cascadia, was interested in renting space and liquid cooling for computing equipment needing up to 7 MW. No binding customer contract was announced. [2] Proponent statement

November 5, 2026. The partners announced signed, binding agreements for the wider program and its first site. Each site company would be owned 75% by FingerMotion and 25% by Genius Group. Requirements for completing the first-site deal remain. [1] Proponent statement

First quarter of 2027. Company target for making land with power available at Brooks Campus #1. This does not confirm when customers could begin using a completed data centre. [1] Proponent projection

What remains unresolved

What do the municipal and environmental permits allow, what conditions apply, and have the replacement generators been approved?

Company and commitmentsScale, projected benefits, and delivery commitments

The plan for ten sites: On November 5, 2026, FingerMotion, Genius Group, and BlueFlare announced signed, binding agreements for a program of ten data-centre campuses, each about 9.9 MW, with a stated total of up to 100 MW. They also signed an agreement for the first site, Brooks Campus #1. Each site would sit in its own company, owned 75% by FingerMotion and 25% by Genius Group. In its September 15, 2026 plan, FingerMotion had described itself as the sole owner of the site companies. The new agreements do not confirm that the first site has been bought or transferred into the new arrangement.. [8][2][1] Proponent statement

Loans and community commitments: The partners expect loans to cover 60% to 80% of each campus project. Repayment would be tied to that campus rather than general corporate backing, but the funding has not been confirmed. They also say they will use their best commercial efforts to reserve 10% of each campus’s capacity for their GENIUSpark Alberta computing venture and put 10% of net profit into a locally governed community fund. This wording commits them to trying to deliver those benefits; it does not guarantee the capacity or payments.. [1] Proponent statement

A possible first customer: On November 4, 2026, FingerMotion said an unnamed customer was interested in renting space and power for computing equipment needing up to 7 MW, with liquid cooling. This measures power for the computing equipment, not the generators’ output. Cascadia Industries Ltd., trading as Cascadia Power, is representing that customer; Cascadia is not the proposed tenant. The expression of interest does not commit the customer to a purchase, and no final customer contract has been signed. The announcement does not say where water would come from or how much would be used.. [2][1] Proponent statement

A separate company merger: On October 29, 2026, FingerMotion announced a preliminary, non-binding plan to combine with BlueFlare Group Holdings. BlueFlare shareholders and certain management and advisory parties would own about 80% of the combined company, proposed to be called BlueFlare Inc. and trade under BFLR. The companies still need a final agreement, funding, shareholder approval, and regulatory and market approvals. This 80% figure concerns ownership of the combined business, not a direct stake in the Brooks site.. [4] Proponent statement

How ownership and customer claims changed: On September 15, 2026, FingerMotion described the site companies as entirely its own. Its November 4, 2026 announcement also called Brooks Campus No. 1 Inc. wholly owned. The November 5, 2026 agreements introduce the 75%/25% FingerMotion and Genius Group split, but do not confirm that the site has been transferred into that ownership arrangement. Customer interest reported on September 24, 2026 for the wider program, October 15, 2026 for Brooks, and November 4, 2026 for up to 7 MW at Brooks does not amount to signed customer contracts.. [8][13][3][2][1] Proponent statement

Hanna is a separate project: The October 1, 2026 announcement describes Hanna as additional to the earlier 99 MW program, after earlier material had included it within the Brooks Zone. Hanna has its own purchase agreement, subject to conditions, and the separate GENIUSpark partnership announced October 27, 2026. ADCW has not confirmed that either the Brooks or Hanna purchase has been completed.. [5][6] Proponent statement

Earlier interest in the wider program: On September 24, 2026, FingerMotion reported possible customers interested in up to 52.5 MW across its Alberta program. They had not committed to buying that capacity. The figure is not contracted demand and cannot all be assigned to Brooks.. [13] Proponent statement

Project overview

FingerMotion, Genius Group, and BlueFlare propose a program of about ten data-centre campuses with a stated total of up to 100 MW. The first, Brooks Campus #1 near Tilley, would use 9.9 MW of on-site natural-gas generation to power customers’ computing equipment. The partners have signed agreements to work together, but buying the site, securing customers and funding, and obtaining the required approvals remain separate steps.

What remains unresolved

Has FingerMotion completed the Newbit purchase, has the site been transferred into the partners’ arrangement, and which company now legally owns each part?

Who is the possible customer, has it signed a binding contract, and has funding been secured?

Unresolved questions are retained within each relevant topic above.

SourcesOriginal documents and publication details

Source record

Company disclosures establish what the company said, not independent verification of projected outcomes.

  1. November 5, 2026 Brooks Corridor binding venture and first-site agreementsFingerMotion, Inc. · Company disclosure · 2026-11-05
  2. November 4, 2026 non-binding Brooks customer interest and liquid-cooling designFingerMotion, Inc. · Company disclosure · 2026-11-04
  3. October 15, 2026 Brooks customer-interest update and separate energy-park proposalFingerMotion, Inc. · Company disclosure · 2026-10-15
  4. October 29, 2026 non-binding BlueFlare combination term sheetFingerMotion, Inc. · Company disclosure · 2026-10-29
  5. October 1, 2026 Hanna purchase agreement and program distinctionFingerMotion, Inc. · Company disclosure · 2026-10-01
  6. October 27, 2026 GENIUSpark Alberta agreementsFingerMotion, Inc. · Company disclosure · 2026-10-27
  7. Binding commitment for first 9.9 MW Brooks Campus Zone siteFingerMotion, Inc. · Company disclosure · 2026-09-10
  8. FingerMotion advances 99 MW behind-the-meter power and compute development program in AlbertaFingerMotion, Inc. · Company disclosure · 2026-09-15
  9. September 21, 2026 Hanna Campus #1 binding letter of intentFingerMotion, Inc. · Company disclosure · 2026-09-21
  10. September 10, 2026 Council agenda: proposed data centre bylawCounty of Newell · Municipal record · 2026-09-10
  11. September 24, 2026 Council agenda: bylaw petitionCounty of Newell · Municipal record · 2026-09-24
  12. Public hearing page for proposed Bylaw 2129-26County of Newell · Municipal record · Accessed November 8, 2026
  13. September 24, 2026 Alberta program status updateFingerMotion, Inc. · Company disclosure · 2026-09-24
  14. September 29, 2026 Newbit acquisition announcementFingerMotion, Inc. · Company disclosure · 2026-09-29
  15. September 29, 2026 Form 8-K: Newbit acquisition and site rightsFingerMotion, Inc. · Regulatory filing · 2026-09-29