Verified project profile
Malachite One Data Centre
Emerald Energy Technologies, a wholly owned Tourmaline subsidiary, proposes a three-phase AI and high-performance-computing campus on Crown land beside the Banshee Gas Plant. The concept includes up to 7.1 million square feet, 930 MW of on-site natural-gas generation, and a 74.9 MW AESO grid-load request. Yellowhead County has received the concept for information, but project-specific construction approvals have not been confirmed.
Project facts
Core scale, approval, employment, and schedule information, labelled by the type of evidence available.
Full-build concept
Up to 7.1 million sq. ft.A three-phase proponent concept, not approved building area. Phase 1 lists 2.0 million square feet and Phase 2 lists 4.7 million square feet.
Sources [2]Proposed investment
Up to CA$20 billionAlberta Major Projects describes up to CA$15 billion for the data centre and CA$5 billion for associated power generation. These are estimates, not committed or financed expenditures.
Sources [1]Projected operating life
30 yearsA proponent planning assumption. No approved operating term or decommissioning plan was found in the reviewed sources.
Sources [2]Target construction
Beginning in 2027The developer projects first revenue in 2028 and full buildout in 2030. These dates remain dependent on approvals, financing, procurement, a customer, and construction.
Sources [2], [1]Data-centre employment
300 growing to 700 claimedThe presentation's operating estimate conflicts with Alberta Major Projects, which reports 300 to 500 long-term data-centre jobs. Neither source supplies a phase-by-phase staffing plan.
Sources [2], [1]Power-facility employment
40 to 60 full-time positions claimedThe presentation also projects 500 to 1,000 construction workers during shorter power-facility construction bursts. These are proponent estimates, not observed employment.
Sources [2]2032 County tax estimate
Approximately CA$52.4 millionEmerald's projection assumes a CA$15 billion build, 50% assessable assets, and specified building-and-structure and machinery-and-equipment mill rates. It is not a County forecast, tax agreement, or guaranteed payment.
Sources [2]Energy and emissions
The concept combines proposed on-site natural-gas generation with an active AESO grid-load request. Its published phase and equipment figures do not fully reconcile, and none represents measured operating demand.
Proposed on-site generation
930 MW at full buildNatural-gas generation proposed to serve the data centre. This is neither approved generation nor measured data-centre load.
Sources [2], [1]AESO grid request
P3114 at 74.9 MWAESO's August 2026 list identifies Banshee Data MPC Load as active at Stage 2, with a November 1, 2027 in-service date. A queue record is not regulatory approval, a guaranteed connection, or operating demand.
Sources [5]Full-build arithmetic
Published total does not reconcileThe Phase 3 table reports 1,104 MW total, but its listed 930 MW generation and 74 MW grid components add to 1,004 MW. ADCW leaves the extra 100 MW unresolved.
Sources [2], [5]Early generation schedule
Equipment and phase figures need clarificationThe schedule describes eight 30 MW units during 2027 to 2028, which equals 240 MW, without explaining how that equipment plan relates to the Phase 1 table's 100 MW generation figure.
Sources [2]Natural-gas demand
Up to 150 million cubic feet/dayThe developer's Phase 3 full-build estimate, not measured fuel use or a disclosed gas-supply contract.
Sources [2], [1]Optional carbon capture
Up to 2.8 million tonnes CO₂/year claimedEmerald projects carbon capture beginning in 2031 and says it could capture approximately 90% of power-plant carbon dioxide. CCS is not part of initial operation. The presentation says the storage reservoir is permitted but does not identify the permit or establish approval of the Malachite capture, transportation, and injection system.
Sources [2], [1]Project emissions
Complete estimate not publishedThe presentation does not provide a complete annual greenhouse-gas inventory for each operating phase, including years before optional CCS begins, residual emissions after capture, upstream gas emissions, or grid electricity.
Sources [2]Water
Emerald proposes primarily closed-loop air-based cooling, supplementary evaporative cooling, and six possible water sources. Its 0.05 m³/second river figure is a proposed diversion rate, not confirmed consumption or an approved project water supply. [2], [7]
Cooling and process-water design
Primarily air-based; supplementary water cooling proposedEmerald says the data centre would primarily use closed-loop air-based cooling, with evaporative cooling available during warmer conditions. Most proposed water demand is associated with power-plant steam generation rather than routine data-centre cooling. No complete project water balance has been published.
Sources [2]Proposed water supply
Diversion rate published; project authorization not identifiedEmerald proposes the Embarras and McLeod rivers, shallow and deep groundwater, recycled power-plant water, and water recovered through future carbon capture. Its combined river rate is 0.05 m³/second, equivalent to 4.32 million litres per day if continuous, but a diversion rate is not confirmed consumption. Alberta's viewer shows nearby Tourmaline oil-and-gas authorizations, including Embarras River Licence 406533 for 80,000 m³/year; those records do not identify Malachite One or establish its water authorization. Emerald also says about 1.5 litres would return to the atmosphere for each litre withdrawn, but provides no engineering water balance, recovery assumptions, water-quality analysis, or approved return route. Atmospheric release is not the same as returning water to either source watershed.
Sources [2], [7]Noise
Project-specific noise evidence is shown when it is available. A predicted sound level is not a measurement from an operating facility.
Project-specific noise evidence
Not publicly disclosedADCW's noise-specific review on August 29, 2026 did not identify a project-specific noise-impact assessment, predicted sound level at the nearest residence, or detailed mitigation plan in public sources.
Indigenous context
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. This section brings together the public record on treaty geography, Indigenous ownership, consultation, and community concerns. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty geography
Treaty 6 territoryThe federal historical treaty-boundary dataset places the approximate project area within Treaty 6. This is geographic context and does not establish project-specific consultation, effects, consent, or community positions.
Sources [8]Project-specific consultation
Public record not identifiedEmerald lists First Nation consultation adequacy as a required process but does not identify the communities consulted, the Crown's consultation file, issues raised, accommodation measures, or an adequacy decision.
Sources [2]Approval and public process
Council received the concept for information only. The presentation identifies utility, environmental, Crown-land, consultation, rezoning, and development approvals as required steps, but it does not provide project-specific approval numbers.
County stage
Presentation received as informationCouncil unanimously accepted the June 23 presentation as information. This was not rezoning, a development permit, or an expression of project approval.
Sources [3], [4]Pecuniary-interest declarations
Two Council members left for the itemMayor Wade Williams and Councillor Shallen Erickson declared pecuniary interests due to family and left during the presentation. The minutes provide no further explanation. The declarations are recorded for transparency and do not, by themselves, establish misconduct.
Sources [4]AUC status
No active project-specific application identifiedNo active application under Malachite One, Emerald Energy Technologies, or a clearly project-specific Banshee power-generation description was identified in the AUC current-applications list as of August 27, 2026.
Sources [6]Environmental approvals
Project-specific records not identifiedThe presentation lists EPEA and Water Act approvals as required. ADCW did not identify an Emerald or Malachite-specific authorization in the reviewed provincial viewers. Existing Tourmaline oil-and-gas records near Banshee cannot be treated as Malachite approvals.
Sources [2], [7]Crown-land tenure
Required; disposition number not publishedThe province and developer place the concept on Crown land. The presentation lists a public-lands lease as required but supplies no issued Malachite disposition or lease number.
Sources [1], [2]Municipal approvals
Rezoning and development permit still requiredThe presentation says forestry-to-industrial rezoning and a development permit would be needed before the proposed buildings, setbacks, access, and related works could be authorized.
Sources [2]Timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
- Public record
The application date shown for AESO Project P3114 Banshee Data MPC Load. AESO's August 2026 list classifies the 74.9 MW request as active at Stage 2. [5]
- Public record
AESO's current in-service date for the P3114 grid-load request. Queue dates can change and do not establish commercial operation. [5]
- Proponent projection
Emerald's projected first-revenue year and start of operating employment. [2]
- Proponent projection
Emerald's projected start for optional carbon capture and sequestration. [2]
What we still don't know
Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.
- The customer, tenant, data-centre operator, final workload mix, and binding compute commitments have not been publicly identified.
- The actual compute load behind the proposed generation and grid figures has not been disclosed.
- The Phase 3 total is 100 MW higher than the sum of its displayed generation and grid components, and the early turbine schedule is not reconciled with the Phase 1 generation table.
- The final legal lands, site boundary, Crown-land disposition, access routes, and total disturbed area are not published in the reviewed sources.
- Project-specific AUC, EPEA, Water Act, Crown-land, rezoning, and development-permit application numbers and outcomes remain unconfirmed.
- The communities consulted, issues raised, accommodation measures, and consultation-adequacy outcome are not public in the reviewed sources.
- A complete phase-by-phase water balance, diversion schedule, consumption estimate, return or discharge route, water quality, and drought restrictions have not been published.
- The basis for the claim that approximately 1.5 litres would return to the atmosphere for each litre withdrawn has not been independently substantiated.
- Noise modelling, air-emissions modelling, complete greenhouse-gas estimates, emergency planning, wildlife and wetland effects, and mitigation commitments have not been published.
- The capture facility, transportation system, injection approvals, storage permit number, monitoring plan, long-term liability, and timing for optional CCS are not established in the reviewed record.
- The employment estimates, workforce percentages, local procurement, property-tax assumptions, and community-benefit commitments have not been independently verified.
- Financing, gas and electricity contracts, equipment procurement, construction commitments, decommissioning, reclamation, and financial assurance are not confirmed.
Source record
Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.
- Malachite One Data Centre
Government of Alberta Major Projects · Government database · Accessed 2026-08-27
- Malachite One Data Centre presentation
Emerald Energy Technologies / Yellowhead County · Company disclosure · 2026-06-23
- June 23, 2026 Council meeting record
Yellowhead County · Municipal record · 2026-06-23
- June 23, 2026 Council meeting minutes
Yellowhead County · Municipal record · 2026-06-23
- Connection Project Reporting
Alberta Electric System Operator · Regulator · Updated 2026-08-05
- Current applications
Alberta Utilities Commission · Regulator · Accessed 2026-08-27
- Authorizations issued under the Water Act or EPEA
Government of Alberta · Government database · Accessed 2026-08-27
- Treaty Boundary dataset
Government of Canada Open Government Portal · Government database · Modified 2026-06-29