SAIDI / MAGA Westlock Cryptocurrency Facility
An approved 9 MW off-grid cryptocurrency project near Hazelbluff that remains incomplete, shut down, and subject to a County Stop Order.
SAIDI and MAGA hold AUC approval for a 9 MW off-grid natural-gas plant designed to power ten on-site cryptocurrency data-centre units near Hazelbluff. The generating equipment is installed but remains shut down under a Westlock County Stop Order. SAIDI is seeking sole control of the approval and a late construction extension, while operation depends on restoring gas supply through MAGA assets subject to AER abandonment and reclamation requirements.
Where it stands
Separate approval tracks, not a construction progress bar. Record last verified 2026-10-29.
AUC Proceeding 31085 is reviewing the approval-transfer and time-extension applications. The October 29, 2026 responses are now on the record. This review did not identify a current participation deadline; the AUC eFiling System is the complete proceeding record. See the approval and participation record ↓
Power and emissionsCampus demand, electricity supply, and emissions evidence
Ten approved gas generators would serve ten on-site cryptocurrency data-centre units without a grid connection. The sole proposed fuel source is tied to MAGA oil-and-gas assets subject to AER suspension, abandonment, and reclamation requirements.
Important distinction: The generators are installed but shut down. An AUC approval and installed equipment do not establish a lawful, available gas supply or an operating data centre.
Approved configuration: 10 generators and 10 computing units. The AUC approved ten 900 kW Weichai natural-gas generators serving ten cryptocurrency data-centre units. The filing describes an isolated, off-gridNon-grid-connectedThe facility has no electrical connection to Alberta's interconnected grid and relies on supply available to the site.It does not directly draw from or send electricity to that grid. Power-plant approvals and local impacts can still matter.Learn more → arrangement with no electricity sales. [1][3] Public record
Approved generation: 9 MW natural gas. The approved plant consists of ten nominal 900 kW units. This is generation capacity, not a separately verified computing load or measured output. [1] Public record
Proposed gas source: F13447 at 10-33-59-27-W4M. SAIDI confirms that the existing MAGA-related wells, facility, and pipelines remain the only proposed supply. It identifies no alternative gas source. [3][5][8] Proponent statement
Fuel availability: Not established. A separate company, BLACK SEA AI (CANADA) LIMITED, is pursuing the oil-and-gas assets. No updated acquisition agreement has been executed. SAIDI acknowledges that an acquisition would not authorize operations or change the AER requirements. [5][6][7] Proponent statement
AER enforcement: MAGA operations suspended; abandonment ordered. The AER cited unpaid municipal taxes, AER and Orphan Well Association debt, remediation and pipeline issues, and other noncompliance in April 2026. In September 2026, it ordered MAGA to submit plans to abandon its wells, facilities, and pipelines and reclaim associated lands. [6][7] Public record
What remains unresolved
Whether BLACK SEA AI completes an oil-and-gas acquisition and whether the AER permits lawful operation of F13447 and the related supply system.
Final computing demand and cooling design.
Water, cooling, and drainageSupply, demand, wastewater, and servicing
The reviewed record does not quantify computing-unit cooling, initial fill, top-ups, or total site water demand.
Cooling and site water: Not quantified. The reviewed power-plant and proceeding records do not establish the computing units' cooling method or total water demand. No inference is made from the gas-generation design. [1][5] ADCW context
What remains unresolved
Initial fill, top-ups, and total site water demand.
Sound at nearby communitiesAssessment evidence, controls, and remaining questions
The required two-metre berm remains unbuilt. SAIDI says it will complete the berm before operation after municipal permissions allow the work.
Required mitigation: Two-metre berm not constructed. The approval requires an earth berm along three sides of the site and a completion letter before operation. The October 29 response confirms the berm remains unbuilt. [1][5] Public record
Construction sequence: County permission still required. SAIDI reports informal feedback that the berm may follow the building permit while the generators remain off. It expressly says this is not a release from the Stop Order. [5] Proponent statement
What remains unresolved
Measured operating sound and the completed berm's performance.
Land and site layoutSite footprint and the planning information in the record
Contamination and remediation: Assessment incomplete. SAIDI says it is not aware of confirmed contamination in the power-plant footprint, but does not claim the site is contamination-free. PDSA fieldwork, the conservation and reclamation plan, security calculation, and environmental monitoring review remain incomplete. [5] Proponent statement
What remains unresolved
Final contamination findings and any required remediation within or affecting the power-plant footprint.
Indigenous contextTreaty geography, engagement, and consultation evidence
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty geography and consultation: Treaty 6 territory; project-specific positions not established. The legal location falls within Treaty 6 territory. Treaty geography does not establish consultation, consent, or the positions of potentially affected First Nations or Métis communities. The reviewed proceeding documents do not establish those positions on the transfer, extension, gas-asset transaction, or remediation work. [3][5][9] ADCW context
Approvals and participationSeparate decisions, public participation, and the recorded timeline
Proceeding 31085 is reviewing a late time-extension request and removal of MAGA from the power-plant approval. The Stop Order, municipal agreement, permits, security, environmental plans, gas acquisition, and AER requirements remain unresolved.
Installed equipment and unfinished work: Generators installed; project incomplete and not operating. SAIDI reports that the generating equipment is installed but shut down. The required noise berm and remaining construction are unbuilt, and work cannot proceed until County conditions and site restrictions are addressed. Installed equipment does not establish an operating power plant or data centre. [1][5] Proponent statement
Applicant schedule: December 31, 2026 construction target. The requested deadline is not an approved completion date. SAIDI separately targets March 31, 2027 for the gas-asset acquisition and April 2027 for operation, subject to regulatory requirements. [5] Proponent projection
Stop Order and DP 25-088: Outstanding. The applicants confirm that the site remains subject to the Stop Order. The draft Development Agreement is unsigned, reclamation security has not been posted, building and electrical permits are unresolved, and environmental plans remain under County review. [2][5] Proponent statement
Late AUC extension: Filed after the April 1, 2026 deadline. SAIDI acknowledges that regulatory responsibilities and deadlines were not adequately tracked or handed over. The September 27 application requests December 31, 2026; the reviewed record does not contain an AUC decision granting it. [3][5] Proponent statement
Approval transfer: Related to MAGA's regulatory and financial problems. SAIDI expressly links the transfer request to MAGA's oil-and-gas compliance issues, abandonment and reclamation requirements, and financial difficulties. The AER and OWA had not been specifically consulted about the power-plant transfer as of October 29, 2026. [5] Proponent statement
Orphan Well Association: Future involvement unresolved. The AER confirms MAGA owed OWA debt. SAIDI says it is not aware that F13447 has been designated for OWA management, but cannot rule out a future designation. OWA status should not be inferred from that qualified statement. [6][5] ADCW context
Recorded timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
June 27, 2025. The AUC approves the 9 MW power plant with a berm requirement and an August 31, 2025 construction deadline. [1] Public record
April 1, 2026. The replacement approval's construction deadline passes without a time-extension application. [3][5] Public record
April 22, 2026. The AER suspends MAGA's oil-and-gas operations until specified compliance requirements are met. [6] Public record
September 4, 2026. The AER issues Order 202609-004 requiring abandonment and reclamation planning for MAGA assets. [7][5] Public record
September 27, 2026. SAIDI and MAGA file the current approval-transfer and time-extension applications after the construction deadline. [5] Public record
October 8, 2026. The AUC requests formal applications and evidence addressing gas supply, MAGA's AER situation, OWA, contamination, County requirements, and SAIDI's advertised Edmonton facility. [3] Public record
October 26, 2026. The AUC grants an extension to October 29, 2026 for the information-request responses. [4] Public record
October 29, 2026. The applicants file responses confirming unresolved municipal requirements, no alternative gas source, an unexecuted gas-asset transaction, incomplete contamination assessment, and that the advertised 15 MW Edmonton project does not exist. [5] Proponent statement
What remains unresolved
The AUC's decisions on the approval transfer and late construction extension.
Release of the Stop Order and completion of DP 25-088, the Development Agreement, permits, security, and environmental plans.
Whether the OWA becomes responsible for relevant MAGA assets.
Construction completion and a lawful operating date.
Company and commitmentsScale, projected benefits, and delivery commitments
Approval ownership: Transfer to SAIDI requested. SAIDI says it funded and owns all power-plant equipment while MAGA owns none of those assets. The approval remains jointly held until the AUC decides whether MAGA may transfer its entire interest to SAIDI. [2][5] Proponent statement
Separate Edmonton claim: SAIDI says the advertised 15 MW project does not exist. After the AUC asked for the location, schedule, and approval, SAIDI said its website contained incorrect test information. No Edmonton legal location or AUC approval was supplied. [3][5] Proponent statement
Project overview
SAIDI and MAGA hold AUC approval for a 9 MW off-grid natural-gas plant designed to power ten on-site cryptocurrency data-centre units near Hazelbluff. The generating equipment is installed but remains shut down under a Westlock County Stop Order. SAIDI is seeking sole control of the approval and a late construction extension, while operation depends on restoring gas supply through MAGA assets subject to AER abandonment and reclamation requirements.
Unresolved questions are retained within each relevant topic above.
SourcesOriginal documents and publication details
Source record
Company disclosures establish what the company said, not independent verification of projected outcomes.
- Decision 30046-D01-2025: nine-megawatt natural-gas-fired power plantAlberta Utilities Commission · Regulator · 2025-06-27
- Proceeding 31085 project progress letter (X0002): Stop Order, Development Permit 25-088, transfer request, and outstanding workSAIDI (Canada) Ltd. · Regulatory filing · 2026-09-25
- Proceeding 31085 information request round 1 (X0007): transfer, late extension, gas supply, abandonment, OWA, contamination, and website questionsAlberta Utilities Commission · Regulator · 2026-10-08
- Proceeding 31085 ruling extending the information-request response deadline to October 29, 2026 (X0009)Alberta Utilities Commission · Regulator · 2026-10-26
- Proceeding 31085 responses to information requests 001-007 (X0011)SAIDI (Canada) Ltd. and MAGA Energy Ltd. · Regulatory filing · 2026-10-29
- AER order suspends MAGA Energy operationsAlberta Energy Regulator · Regulator · 2026-04-23
- AER issues abandonment order to MAGA Energy Ltd.Alberta Energy Regulator · Regulator · 2026-09-09
- Hazelbluff Compressor Station facility record: legal land description and coordinatesEnvironment and Climate Change Canada · Government database · 2016-01-01
- Treaty boundary datasetGovernment of Canada Open Government Portal · Government database · Modified 2026-06-29