Verified project profile
Sturgeon Data Centre
Meta has announced a CA$13-billion-plus, 1 GW data centre in Alberta's Industrial Heartland. The master site development permit is in effect, but residents are asking the Land and Property Rights Tribunal to let their appeals proceed to a full hearing. Site preparation is reported; the public record reviewed by ADCW does not yet confirm that main facility construction is underway.
Project facts
Core scale, approval, employment, and schedule information, labelled by the type of evidence available.
Announced capacity
1 GWMeta's announced data-centre capacity remains ADCW's headline figure. Clark Builders reports a different figure below.
Sources [5], [17], [18]Different capacity reported by builder
Approx. 1.6 GWClark Builders, a project delivery partner, reports this compute capacity. The sources do not explain how it relates to Meta's 1 GW announcement. A larger build-out is possible, but not confirmed.
Sources [18], [17]Project size reported by builder
2.9 million sq. ft.Clark Builders lists this project size. It does not establish the approved building area or the final campus footprint.
Sources [18], [3]Investment
More than CA$13 billionCompany-announced project investment.
Sources [5]Associated power-plant cost
Approx. CA$4.0 billion capital costGreenlight reports an approximately CA$4.6 billion total project cost after including CA$0.6 billion in interest during construction and other financing costs.
Sources [13]Federal funding
None publicly identifiedADCW found no project-specific federal grant, loan or contribution in the reviewed sources. Meta says it is fully funding the new generation and grid infrastructure.
Sources [5], [4]Municipal permit
DP-26-0028Issued June 16, 2026; effective July 7, 2026. The permit is now the subject of a preliminary appeal proceeding.
Sources [3], [1]Master-permit area
Approx. 1,760 acresThe appellants' September 15, 2026 filing describes the master permit as covering 11 quarter sections. This is a party's description in an unresolved appeal, not a Tribunal finding.
Sources [1]Wetlands identified in appeal
351 wetlands; approx. 85 haThe appellants' filing says the application package identifies 351 wetlands covering about 210 acres and schedules all of them for removal. The Tribunal has not ruled on the allegation or the permit's compliance.
Sources [1]Employment
~3,000 peak construction; 300+ operationalCompany projections, not observed job counts.
Sources [5], [6]Target operation
2028–2029Capital Power expects the initial 250 MW load in the second half of 2028; Sturgeon County lists the data centre as operational in 2029.
Sources [8], [4]General contractor
Frost CollectiveA joint venture of Clark Builders and PCL Construction.
Sources [6], [7]Energy and emissions
Supply agreements and the associated Greenlight power plant are tracked separately from Meta's annual clean-energy matching commitment.
Initial grid supply
250 MWCapital Power disclosed an energy-supply agreement lasting more than 10 years, with service anticipated in the second half of 2028.
Sources [8]Dedicated gas generation
932 MWGreenlight's committed first phase is a combined-cycle natural-gas plant expected in service in the second half of 2030.
Sources [9], [13]Greenlight site-grading permit
DP-26-0216Sturgeon County approved site grading for Phase 1 of the 932 MW power plant at 56126 Range Road 222. The permit was issued September 18, 2026, and takes effect October 9, 2026, unless appealed. It is separate from Meta's data-centre permit.
Sources [2]Backup generators shown in appeal filing
848 diesel unitsThe appellants say drawings in the data-centre application show 848 backup generators and estimate associated on-site diesel storage at more than 1 million litres. They argue that this infrastructure was deferred to a future AUC process. The figures and legal argument have not been adjudicated.
Sources [1]Greenlight ownership
Pembina 47.5%; MSIP 47.5%; Kineticor 5%Pembina leads construction management. Aecon and Técnicas Reunidas hold the fixed-price engineering, procurement, and construction agreements.
Sources [13]Permitted expansion
Up to 1,864 MWThe AUC record describes two stages and full development in 2031.
Sources [9]Natural-gas demand
Approximately 150 million cubic feet/dayPembina's disclosed requirement for the current 932 MW Greenlight project.
Sources [13]Full-build GHG estimate
5.677 million tonnes CO₂e/yearGreenlight's federal filing estimate for the maximum 1,864 MW plant without carbon capture. It is not an estimate for only the current 932 MW phase.
Sources [14]Clean-energy matching
100% annual matching promisedMeta says it will add or contract enough clean energy to match annual electricity use. This accounting commitment does not mean the facility's physical electricity supply is fossil-free at all times.
Sources [5], [13]Water
The Meta data centre and the associated Greenlight power plant have separate water evidence. Meta's cooling claims do not quantify the data centre's full site demand. Greenlight estimates 538,000 m³/year for the power plant, subject to a municipal water-use approval or agreement. [5], [6], [10], [11]
Cooling design
Closed-loop liquid cooling with dry coolingMeta says the cooling system will require no operational water. This is a design claim; measured use will not exist until operations begin.
Sources [5], [6]Other on-site use
Still requiredMeta identifies construction, facility/domestic use, fire protection and equipment maintenance as continuing water demands.
Sources [5], [6]Associated power-plant water
538,000 m³/year (538 million L/year)Greenlight estimates this volume for its power plant, averaging about 1,474 m³/day (1.47 million L/day). It is not a Meta data-centre water-use estimate. The proposed supply is a new Capital Region Northeast Water Services Commission pipeline loop along Highway 643, connected to Sturgeon County's municipal system.
Sources [10], [11]Power-plant water approval
Municipal agreement still requiredThe AUC accepted Greenlight's estimate for its decision but did not approve the water use. Greenlight must confirm and summarize its municipal approval or agreement in the final project update.
Sources [11]Associated power-plant cooling
Dry cooling; no cooling towersGreenlight told the AUC it plans to use air-cooled heat exchangers and an air-cooled condenser. It said this design is not expected to cause local fogging or icing.
Sources [10]Associated power-plant wastewater
Municipal sewer proposed; agreement not confirmedGreenlight told AEPA that there would be no on-site wastewater treatment. It proposed sending qualifying wastewater to Sturgeon County's sewer for Arrow Utilities treatment, with up to 61 m³/hour of reverse-osmosis reject routed to an effluent tank first. Wastewater the system cannot accept would be stored and disposed of off-site.
Sources [10]Public infrastructure
Approximately CA$60 millionMeta says this includes roads and water infrastructure; an itemized public breakdown was not found in the reviewed sources.
Sources [5]Noise
The associated Greenlight power plant has a filed noise-impact assessment. It does not establish the sound contribution from Meta's data-centre buildings, cooling equipment, or backup generators. Residents now allege that the data-centre permit record lacked several noise studies; the Tribunal has not ruled on that claim.
Modelled cumulative sound
50.4 dBA day; 43.1 dBA nightGreenlight's filed model applies these values at one residence about 860 metres northwest of the power-plant boundary. The applicable daytime and nighttime limits are 55 dBA and 45 dBA. These are modelled power-plant results, not measurements from an operating facility or an assessment of the full Meta campus.
Sources [12]Data-centre noise
Not separately quantifiedADCW has not identified a public project-specific sound estimate for Meta's data halls, dry-cooling equipment, or backup generators.
Sources [12], [3], [6]Noise evidence challenged on appeal
Several studies alleged missingThe appellants say the public permit package did not include an AUC Rule 012-compliant Noise Impact Assessment, a Noise Mitigation and Monitoring Plan, or a Noise Attenuation Study. They say the submitted Noise and Vibration Strategy did not meet Rule 012. These are unresolved appellant claims.
Sources [1]Indigenous context
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. This section brings together the public record on treaty geography, Indigenous ownership, consultation, and community concerns. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty and Métis geography
Treaty 6 territorySturgeon County identifies the area as Treaty 6 territory, the traditional homelands of Alexander and Michel First Nations, and part of Métis Nation of Alberta Districts 8 and 11. This is geographic context and does not by itself establish project-specific consultation, effects or positions.
Sources [15]Approval and public process
The master permit is in effect, but a preliminary tribunal process will decide who may appeal and whether the challenges can proceed to a full hearing. The appellants' September 15, 2026 submission records their allegations, not findings by the Tribunal.
Preliminary appeal stage
116 appeal filesThe September 15, 2026 submission describes a coalition of approximately 120 people. The October 13, 2026 preliminary hearing is expected to address standing and whether the appeals may proceed, not the final merits of the permit challenge.
Sources [1]Affected-person dispute
County's proposed 3 km radius challengedThe appellants oppose a blanket distance cutoff and seek evidence-based standing tied to possible noise, light, emissions, traffic, emergency-route, drainage, and hydrological effects. The Tribunal directed production of maps showing 3 km, 5 km, and 10 km radii; it has not adopted the appellants' requested 10 km scope.
Sources [1]Permitted use and bylaw compliance
Separate questions before the TribunalFor the preliminary argument, the appellants accept that a major data-processing facility is a permitted use in the Heavy Industrial district. They argue that this does not resolve compliance with the Land Use Bylaw, Municipal Development Plan, and Alberta's Industrial Heartland Area Structure Plan. No ruling has been made.
Sources [1]Application-package audit
Missing, partial, or deferred studies allegedThe appellants say their review of the 4,386-page package found gaps involving noise, groundwater, landscaping, parking, topography, off-site drainage, emergency response, geotechnical work, biophysical effects, air emissions, cumulative effects, health, and reclamation. Some listed reports were discretionary, and the Tribunal has not determined whether the County's review complied with the governing plans and bylaw.
Sources [1]Land-use approval
Permitted use in Heavy Industrial zoningThe master site development permit establishes the framework for a major data-processing facility across the listed parcels.
Sources [3]Public notice and appeal
Notice posted June 16; deadline July 7, 2026Because this was a permitted-use approval, public appeal rights were narrower than for a discretionary use or variance.
Sources [3]Project open house
Not required by the CountySturgeon County states that data centres are permitted in the applicable industrial zone and a public open house is not required for approval.
Sources [4]County development principles
Seven guiding principles publishedSturgeon County's principles call for dedicated power, minimized water use, no municipal incentives, developer-funded infrastructure, heavy-industrial locations, reduced community impacts, and annual public reporting. They mix County decisions, developer obligations, and broader expectations; the page does not identify every principle as a condition of this project's permit.
Sources [4]Annual public reporting
Expected by Sturgeon CountyThe County says operators are expected to report water use, noise levels, and nitrogen oxide emissions each year. This is a published expectation, not confirmation that the reports exist or that it is an enforceable condition of this project's permit.
Sources [4]Greenlight Water Act approval
DAUT0024959AEPA's November 26, 2025 approval covers permanent wetland disturbance and construction of a stormwater management system for the power plant. It is not approval of Greenlight's municipal water use or Meta's data-centre water demand.
Sources [10], [11]Timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
- Public record
Sturgeon County issued a grading permit for site preparation. [4]
- Public record
Master site development permit DP-26-0028 issued. [3]
- Public record
The AUC approved the associated Greenlight Electricity Centre, subject to conditions including confirmation of a municipal water-use approval or agreement in Greenlight's final project update. [11]
- Proponent statement
Greenlight's partners announced a positive final investment decision for the 932 MW first phase, an approximately CA$4.0 billion capital-cost estimate, and an approximately CA$4.6 billion total project cost including financing costs. [13]
- Public record
Municipal development permit became effective after the notification period. [3]
- Proponent statement
Meta publicly announced the Sturgeon Data Centre. [5]
- Proponent statement
Clark Builders reports early planning, purchasing, crew and equipment mobilization, and site preparation underway. Its page does not confirm that main facility construction has begun. [18]
- Proponent projection
Main data-centre construction expected to begin, according to Sturgeon County's published timeline. [4]
- Public record
Residents filed preliminary written submissions asking the Land and Property Rights Tribunal to reject a blanket 3 km standing cutoff and allow the permit challenge to proceed to a full merits hearing. The filing's allegations have not been adjudicated. [1]
- Public record
Sturgeon County issued DP-26-0216 for site grading associated with Phase 1 of the separate 932 MW Greenlight Electricity Centre at 56126 Range Road 222. [2]
- Public record
Greenlight site-grading permit DP-26-0216 is scheduled to take effect unless appealed; appeals are due the same day. [2]
- Public record
Preliminary LPRT hearing referenced in the appellants' filing. [1]
- Proponent projection
Capital Power expects the initial 250 MW data-centre load to enter service. [8]
- Proponent projection
Sturgeon County expects the data centre to be operational. [4]
- Proponent projection
Committed 932 MW Greenlight gas-generation phase expected in service. [13]
What we still don't know
Some details have not been made public or remain unresolved. We keep those gaps visible and update them when reliable information becomes available.
- The difference between Meta's 1 GW announcement and Clark Builders' approximately 1.6 GW compute-capacity figure remains unresolved. The sources do not establish whether the figures describe different phases, designs, or definitions of capacity.
- Clark Builders reports a project size of 2.9 million sq. ft., but the approved building area, final campus footprint, and phased build schedule remain unconfirmed in the reviewed municipal records.
- Expected annual facility electricity consumption has not been publicly quantified beyond the announced 1 GW capacity and supply agreements.
- Meta's expected annual water withdrawal, consumption and wastewater volumes have not been published; Meta promises annual disclosure after operations begin.
- Greenlight must still confirm its municipal water-use approval or agreement in its final AUC project update. The reviewed record also does not establish that Greenlight completed its proposed wastewater-acceptance agreement with Sturgeon County and Arrow Utilities.
- A project-specific estimate of operational greenhouse-gas emissions has not been published. The available 5.677 Mt CO₂e/year estimate is for Greenlight's maximum 1,864 MW power-plant buildout.
- The projects Meta will use for its clean-energy matching commitment have not yet been identified publicly.
- An itemized breakdown of the CA$60 million in local infrastructure spending and expected municipal tax revenue was not found in the reviewed sources. General tax treatment and any future public support have not been exhaustively confirmed.
- The public sources give two early service milestones: Capital Power's second-half 2028 load date and Sturgeon County's 2029 operational date. The relationship between those milestones is not yet explained.
- The Tribunal has not decided which appellants qualify as affected persons, whether the appeals will proceed to a full merits hearing, or whether any alleged bylaw, planning, assessment, or deferral issue affected the validity of DP-26-0028.
- The public record reviewed by ADCW does not establish the final AUC approval path, equipment specifications, operating limits, fuel-storage design, or cumulative effects for the 848 backup generators described in the appellants' filing.
Source record
Primary and official sources reviewed for this profile. Company disclosures support what the company said, not independent verification of future outcomes.
- Appellants' Written Submissions on Preliminary Issues: DP-26-0028, Project Frost
Sturgeon County Appeals Group / Land and Property Rights Tribunal · Tribunal filing · 2026-09-15
- Development permit approval notice for 56126 Rge Rd 222
Sturgeon County · Municipal record · 2026-09-18
- Development permit approval notice for 56111 Rge Rd 223
Sturgeon County · Municipal record · 2026-06-16
- Data Centre Development
Sturgeon County · Municipal record · Updated through 2026-09-04
- Breaking Ground on Meta's First Data Center in Canada
Meta · Company disclosure · 2026-07-08
- Meta Sturgeon Data Centre fact sheet
Meta / Sturgeon County · Company disclosure · 2026-07
- Sturgeon Data Centre project site
Sturgeon Data Centre · Company disclosure · Accessed 2026-07-22
- Capital Power Enters Long-term Energy Supply Agreement with Meta in Alberta
Capital Power · Company disclosure · 2026-07-08
- Greenlight Electricity Centre: Proceeding 30261
Alberta Utilities Commission · Regulator · Decision issued 2026-06-25
- Proceeding 30261 filings X0089, X0093 and X0094
Alberta Utilities Commission · Regulatory filing · Accessed 2026-08-17
- Decision 30261-D02-2026: Greenlight Electricity Centre Project
Alberta Utilities Commission · Regulator · 2026-06-25
- Greenlight Electricity Center Noise Impact Assessment
Stantec for Greenlight Electricity Centre GP Ltd. / Alberta Utilities Commission · Regulatory filing · 2025-08-20
- Greenlight Electricity Centre final investment decision
Pembina Pipeline Corporation · Company disclosure · 2026-07-02
- Greenlight Electricity Centre Initial Project Description
Impact Assessment Agency of Canada · Federal filing · 2025-07-30
- Truth & Reconciliation
Sturgeon County · Municipal record · Accessed 2026-08-12
- Meta Data Center
Government of Alberta Major Projects · Government database · Accessed 2026-07-22
- Hello, Sturgeon County!
Meta Data Centers · Company disclosure · 2026-07-08; accessed 2026-08-31
- Sturgeon Data Centre
Clark Builders · Company disclosure · Undated; accessed 2026-08-31