Evidence profile · Town of Olds

Synapse Olds Data Centre

A former 1 GW AI-campus proposal in northeast Olds; it will not proceed as proposed.

Illustrative landscape · Sevgi Gümüş / Pexels
← Alberta data centre project list
Developer Synapse Real Estate Corp.View on project map ↗

04-33-1-W5M, at Highway 2A and Highway 27, Olds · Map precision: Exact site

The AUC denied the supporting 1.4 GW gas power plant on August 17, 2026, finding the location unsuitable for that scale. Synapse then said the Olds project would not proceed as proposed. The decision concerned the power plant, not the data centre itself. No replacement design or site is identified in this record.

Former campus proposal1 GWTen proposed 100 MW blocks; not approved or operating [19][20]
Historical water estimate60,000 L/dayDeveloper estimate; conflicting Town breakdown retained below [10][14][8]
Historical sound studyGenerator exceedances75 dBA option exceeded Rule 012 at several receptors [10][8]
Former employment claim1,000+ permanentPlus 2,000 construction jobs; uncommitted projections [18][16]
Annual emissionsNot quantifiedNo complete annual estimate found for the denied design [11][8]
Historical site parcel273 acresAbout 20 acres proposed for the power plant [3][8]

Where it stands

Power-plant applicationDeniedAUC Application 30732-A001; August 17, 2026 [8]
Data-centre proposalWill not proceed as proposedDeveloper response; no replacement design announced [20]
Environmental reviewSeparate application001-510949 recorded in progress at the August 25, 2026 review [1][5]
Municipal applicationNot filed in reviewed recordAny future data-centre permit would be a separate Town decision [1][6]

Separate approval tracks, not a construction progress bar. Record last verified 2026-08-25.

Want to get involved?

The AUC power-plant proceeding ended in denial. The recorded AEPA Statement of Concern deadline was September 3, 2026, which has passed; the notice PDF carried a conflicting August 20, 2026 date. This profile does not establish a current participation window or a later environmental decision. See the approval and participation record ↓

Tiles marked Historical proposal contain details from the 1.4 GW power-plant application the AUC denied on August 17, 2026. Synapse subsequently said the Olds project will not proceed as proposed. The information remains part of the public record, but it is not an approved or current plan. The AUC did not decide whether a differently designed data centre is suitable at this location.

Power and emissionsCampus demand, electricity supply, and emissions evidence

The AUC denied the proposed on-site power plant and emergency generationBackup generationBackup generators provide electricity when the normal supply is unavailable. They may also run for testing or maintenance.Installed capacity does not establish continuous operation, annual fuel use, or emissions. Operating hours and permit conditions are separate evidence.Learn more → on August 17, 2026. Capacity figures below describe the denied application, not approved or operating equipment.

Important distinction: The AUC regulated the proposed power plant, not the data centre. A development-permit application for any replacement data-centre proposal would be decided by the Town of Olds; the Town says no application has been filed. No replacement power design has been announced.

Announced data-centre capacity: 1 GW. Ten proposed 100 MW data-centre blocks at full build. [19] Proponent statement

On-site gas generation: 1.4 GW. Ten proposed 140 MW combined-cycle natural-gas plants would supply the ten data-centre blocks. [7][6][13][8] Public record · Historical proposal

Grid connection: Not proposed. The power plant is proposed as behind-the-meterBehind-the-meter generationGeneration supplies electricity on the customer's side of the meter and can reduce the site's draw from the grid.A facility can have this generation and still be grid-connected. The term does not establish that it is off-grid.Learn more → self-supply and would not connect to the Alberta interconnected electric system. [7][6][8] Public record · Historical proposal

Natural-gas connection: Separate pipeline application expected. The application does not identify final gas suppliers or the pipeline route and capacity. Synapse says the pipeline would be addressed through a future Alberta Energy Regulator application. [5][8] Proponent statement · Historical proposal

Emergency diesel generation: 1.8 GW across 600 generators. The application pairs 60 generators with each of ten modular blocks. These are proposed backup units, not operating equipment. [7][6][9][8] Public record · Historical proposal

Normal-operation air modelling: Compliance predicted for assessed pollutants. The revised June 12 assessment predicts that modelledModelled versus measuredA modelled result is a prediction based on inputs and assumptions. A measured result comes from observations or instruments under particular conditions.A prediction is not verified operating performance. Check the location, period, operating scenario, and what the reported number actually represents.Learn more → normal-operation cases would meet the applicable Alberta Ambient Air Quality Objectives for nitrogen dioxide (NO₂), carbon monoxide (CO), formaldehyde and ammonia. These are model results based partly on developer-supplied or estimated inputs, not measured emissions. [11][8] Proponent projection · Historical proposal

Full-diesel emergency scenario: NO₂, PM₂.₅ and eight-hour CO exceedances predicted. Case 4 assumes all ten gas plants shut down and all 600 diesel generators operate. The revised model predicts exceedances of the one-hour nitrogen dioxide, 24-hour fine particulate matter and eight-hour carbon monoxide objectives. The report asks AEPA to exempt temporary, low-frequency exceedances in this scenario. [11][10][8] Proponent projection · Historical proposal

Proposed stack heights: 25.9 m gas; 9 m diesel. Synapse increased the proposed gas-generation stack height to 25.9 metres to improve dispersion and retained nine-metre emergency-diesel stacks. These are proposed maximum heights unless a regulator directs otherwise. [10][11][8] Proponent statement · Historical proposal

Equipment procurement: Not complete. Synapse identified preferred suppliers and configurations, but commercial negotiations, final equipment selection and binding procurement remained unfinished in the July 30 response. [10][8] Proponent statement · Historical proposal

Annual greenhouse-gas emissions: Not found in reviewed public sources. The revised air-quality assessment addresses local pollutants, not a complete annual CO₂e estimate for the 1.4 GW full build. [11][8] ADCW context · Historical proposal

What remains unresolved

Natural-gas suppliers, the pipeline route and capacity, and the fuel-interruption plan were unresolved in the denied application. No replacement power-supply or pipeline plan has been published.

A complete annual greenhouse-gas estimate for the denied 1.4 GW power-plant design was not found in the reviewed public sources. No estimate for a revised design has been published.

The Town's March air-quality peer review assessed the earlier February report for the design that was later denied. ADCW has not located an independent Town review of the revised June 12 assessment.

Water, cooling, and drainageSupply, demand, wastewater, and servicing

The water figures below came from the design accompanying the power-plant application the AUC denied. They are historical developer estimates, not approved allocations, measured use or confirmed demand for a revised project. A separate section of the Town webpage also describes the breakdown differently.

Total normal site demand: Approximately 60 m³/day (60,000 L/day). Synapse's July 30 filing estimates 20 m³/day (20,000 L/day) for plant operations and 40 m³/day (40,000 L/day) for domestic use. These are developer estimates, not approved allocations or measured consumptionWithdrawal, consumption, and dischargeWithdrawal is water taken from a source. Consumption is the portion not returned to the same water system. Discharge is water released after use or treatment.These are different quantities. Check which one a water figure describes before comparing projects.Learn more →. [10][8] Proponent projection · Historical proposal

Power-plant operations: Approximately 20 m³/day (20,000 L/day). Synapse describes this as a current maximum design allowance across all ten power blocks, not a final vendor-guaranteed operating value. [10][8] Proponent projection · Historical proposal

Domestic use: Approximately 40 m³/day (40,000 L/day). The developer estimate covers domestic use by on-site personnel and is separate from the plant-operations allowance. [10][8] Proponent projection · Historical proposal

One-time cooling-system fill: 900 m³ per building (900,000 L). The Town says each proposed building would require an off-site-supplied one-time fill, or 9,000 m³ (9 million L) across ten buildings. [14] Proponent projection

Town webpage comparison: A conflicting description remains. The Town page now states the July 30 filing's 60 m³/day (60,000 L/day) total, split between plant and domestic use. A separate section still describes up to 60 m³/day (60,000 L/day) from the municipal system plus 20 m³/day (20,000 L/day) of trucked plant water. [14][10][8] ADCW context · Historical proposal

Cooling design: Closed-loopClosed-loop coolingCooling fluid circulates repeatedly through a contained loop instead of being routinely discharged after one pass.That describes the loop, not the whole site's water use. A separate heat-rejection system can still use water, and filling, maintenance, and leaks also matter.Learn more → systems proposed. The proponent says both the data centre and gas plant would use closed-loop cooling. Measured consumption will not exist unless the project is built and operating. [19][8] Proponent projection · Historical proposal

What remains unresolved

The Town webpage gives two conflicting water-demand descriptions tied to the design accompanying the denied application. Neither should be read as an approved allocation or confirmed demand for a revised project.

Sound at nearby communitiesAssessment evidence, controls, and remaining questions

Noise-impact evidence: Assessment and municipal peer review filed. The historical proposal included a noise-impact assessment and a Town-commissioned peer review. The AUC later refused the associated power plant, so these results describe a proposal that will not proceed as reviewed. [13][8] Public record · Historical proposal

Emergency-generator noise choice: 75 dBA option exceeded Rule 012 at several receptors. Synapse proposed 75 dBA emergency generators rather than a quieter, more expensive 65 dBA option. It said it would follow an AUC condition requiring the quieter units, but no such approval condition was issued because the plant was refused. [10][9][8] ADCW context · Historical proposal

Partial-failure scenarios: Not modelled. The noise assessment evaluated defined cases, not every possible mix of gas and diesel generation. Synapse proposed later modelling plus boundary monitoring, alarms, load reduction, and shutdown controls; those measures were not confirmed as enforceable conditions. [10][8] ADCW context · Historical proposal

What remains unresolved

Final equipment selection and binding procurement were incomplete when the AUC denied the application. No revised equipment or emergency-generator noise design has been published.

Land and site layoutSite footprint and the planning information in the record

Proposed campus size: 2 million sq. ft.. Company-announced capacity across the proposed full campus. [19][16] Proponent statement

Site parcel: 273 acres. The AEPA notice says the proposed thermal power plant would occupy about 20 acres, with the remaining land intended for the data centre and supporting infrastructure. [3][8] Public record · Historical proposal

Residential proximity: Approximately 30 m at the nearest point. The AUC decision says the site boundary is about 30 metres from the first row of properties and that more than 700 residences are within 800 metres. [8] Public record

What remains unresolved

The provincial Major Projects map explicitly labels its Olds coordinate a placeholder. ADCW instead uses the site coordinates and legal location published in Synapse's construction emergency response plan.

Indigenous contextTreaty geography, engagement, and consultation evidence

Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.

Treaty and Métis geography: Treaty 7 region. The Town of Olds identifies the area with the Blackfoot Confederacy, Tsuut'ina First Nation, Stoney Nakoda Nations and Métis Nation of Alberta Red Deer Métis District 3. This is geographic context and does not by itself establish project-specific consultation, effects or positions. [17] Public record

Approvals and participationSeparate decisions, public participation, and the recorded timeline

The AUC power-plant review ended with a denial on August 17, 2026, and Synapse says the Olds project will not proceed as proposed. The AEPA environmental review and any future Town development-permit process are legally distinct.

AUC proceedingAUC proceedingA proceeding is the Alberta Utilities Commission's formal record for reviewing an application, including evidence, submissions, and a decision when issued.A proceeding number helps locate the record. The existence of a proceeding does not mean the application has been approved.Learn more →: 30732, application denied. On August 17, 2026, the AUC denied Application 30732-A001 because Synapse did not demonstrate that the proposed location was in the public interest. The decision covers the power plant and emergency generation, not the data centre itself. [8] Public record

Environmental application: 001-510949; recorded in progress. Synapse submitted the EPEA application to Alberta Environment and Protected Areas on July 21, 2026. The August 25, 2026 reviewed record reports AEPA review in progress, separately from the AUC power-plant proceeding and any future Town development-permit review. The recorded Statement of Concern deadline was September 3, 2026; that date has passed. [1][5] Public record

Municipal permit: No active application. The Town of Olds says neither proposed Olds data-centre project has filed a development-permit application. [1] Public record

Power-plant application: Denied by the AUC. The AUC denied Application 30732-A001 on August 17, 2026, finding that Synapse had not justified locating a power plant of this scale so close to the surrounding community. [8] Public record

Developer response: Olds project will not proceed as proposed. Synapse confirmed after the AUC decision that the Olds project will not proceed in the form reviewed. It said it would assess other opportunities in Alberta, but did not announce a replacement site or design. [20] Proponent statement

Public participation: About 1,500 statements; 919 granted standing. The AUC described the participation level as unusually high. It did not treat the number alone as determinative, but said it demonstrated significant community concern about the location. [8] Public record

Recorded public-input deadline: September 3, 2026; now past. The reviewed Town page gave September 3, 2026 based on the last notice publication date, while the posted notice PDF showed August 20, 2026. Both dates have passed. No current participation window is established by this record. [1][3] Public record

Data-centre application: Not filed with the Town. No municipal development-permit review or decision can occur until an application is submitted. [1][6] Public record

Municipal land use: Data centre is a discretionary use. The site is in the Light Industrial District, where the Town would decide any data-centre development-permit application as a discretionary use. The denied application treated the self-supply power plant as an accessory use, but the AUC independently refused that plant. [6][1][8] Public record

First AUC filing: Closed for deficiencies. The AUC closed the first application on March 6, 2026 because the submission was incomplete. The Town explicitly distinguishes this from rejection after a full merits review. [1] Public record

Town participation: Support in principle considered. The Town supported the project in principle. The AUC considered that support and the project's potential economic benefits, but found the proposed power-plant location was not in the public interest. [6][8] Public record

Developer engagement: Three rounds reported. The Town records engagement beginning January 26, an April 1 open house attended by about 30 people, and June 10 consultations attended by about 40. [1] Public record

Recorded timeline

Observed decisions and future dates are kept distinct; projected milestones may change.

December 2025. The Town and Synapse began discussing the proposed project; the Town signed a preliminary mutual confidentiality agreement. [6][15] Public record

January 27, 2026. Synapse and Invest Olds publicly announced the proposed CA$10 billion development. [18] Proponent statement

March 6, 2026. The AUC closed Synapse's first power-plant application after identifying filing deficiencies. [1] Public record

April 3, 2026. Synapse filed its second AUC power-plant application, 30732-A001. The AUC later denied it on August 17. [9][8] Public record

May 29, 2026. The Town of Olds filed its Statement of Intent to Participate in Proceeding 30732. [6] Public record

July 9, 2026. The AUC issued its second round of information requests on noise, procurement, siting, diesel generation and other unresolved details. [9] Public record

July 21, 2026. Synapse submitted EPEA Application 001-510949 to Alberta Environment and Protected Areas. [5] Public record

July 30, 2026. Synapse filed its response to the AUC's second round of information requests. [10] Public record

August 17, 2026. The AUC denied the power-plant application, finding the proposed location unsuitable because of the project's scale and proximity to the community. The Commission expressly did not rule on the data centre itself. [8] Public record

August 18, 2026. Synapse confirmed that the Olds project will not proceed as proposed and said it would assess future opportunities elsewhere in Alberta. [20] Proponent statement

September 3, 2026. Deadline to submit a written Statement of Concern to AEPA. The Town corrected this date based on the last public-notice publication. [1][3] Public record

What remains unresolved

Synapse has not announced a replacement Olds proposal, another Alberta site, a revised power design, or whether it will seek permission to appeal the AUC decision.

AEPA has not issued a decision on EPEA Application 001-510949.

No development-permit application, municipal approval or construction authorization for the data-centre campus has been filed or issued.

Company and commitmentsScale, projected benefits, and delivery commitments

Announced investment: CA$10 billion. A proponent estimate repeated in the provincial Major Projects database; no final investment decision was found in the reviewed record. [18][16] Proponent projection

Employment: 2,000 construction; 1,000+ permanent. Proponent projections, not observed job counts or binding commitments. [18][16] Proponent projection

Project overview

Synapse proposed a 1 GW data-centre campus in northeast Olds. On August 17, 2026, the AUC denied the proposed 1.4 GW on-site natural-gas power plant because it found the location unsuitable for a project of that scale. Synapse subsequently confirmed that the Olds project will not proceed as proposed. The AUC ruled on the power plant, not the data centre itself, and no replacement site or design has been announced.

What remains unresolved

A final investment decision, committed hyperscale customer, financing structure and binding construction schedule were not found in the reviewed public record.

The proposed Community Benefits Program has not been publicly defined as a binding amount, formula or governance structure.

The denied application estimated decommissioning costs at approximately CA$290 million and proposed delayed security beginning in year 10. Those terms were not approved, and no revised closure or security plan has been published.

The Town estimates CA$5–7 million in annual municipal property tax at full build, but the taxable assessment will not be known unless facilities are built and operating.

Unresolved questions are retained within each relevant topic above.

SourcesOriginal documents and publication details

Source record

Company disclosures establish what the company said, not independent verification of projected outcomes.

  1. Current Status: Proposed Data Centre DevelopmentsTown of Olds · Municipal record · Updated through 2026-08-15
  2. Synapse Data Center construction emergency response planSynapse Data Center / Town of Olds · Regulatory filing · 2026-03-18
  3. Notice of application: EPEA Application 001-510949Alberta Environment and Protected Areas · Regulator · Accessed 2026-08-15
  4. Cover letter: EPEA Application 001-510949Alberta Environment and Protected Areas · Regulatory filing · Accessed 2026-08-08
  5. EPEA Application 001-510949Synapse Real Estate Corp. · Regulatory filing · 2026-07-21
  6. Town of Olds Statement of Intent to Participate: Proceeding 30732Town of Olds / Alberta Utilities Commission · Regulatory filing · 2026-05-29
  7. Notice of information session and hearing: Proceeding 30732Alberta Utilities Commission · Regulator · 2026-04-29
  8. Decision 30732-D01-2026: Synapse Data Center Power Plant ProjectAlberta Utilities Commission · Regulator · 2026-08-17
  9. Information request round 2 to Synapse Real Estate Corp.Alberta Utilities Commission · Regulator · 2026-07-09
  10. Synapse response to AUC information request round 2Synapse Real Estate Corp. / Alberta Utilities Commission · Regulatory filing · 2026-07-30
  11. Revised Air Quality Dispersion Modelling Assessment: Synapse 1.4 GW Power PlantCalvin Consulting Group Ltd. for Synapse · Regulatory filing · 2026-06-12
  12. Peer Review of the February 12 Synapse Air Quality AssessmentCambium Inc. for the Town of Olds · Municipal record · 2026-03-05
  13. Peer Review: Noise Impact Assessment for Olds Data CenterEnglobe Corp. for the Town of Olds · Municipal record · 2026-03-20
  14. Water, Environment & EmissionsTown of Olds · Municipal record · Accessed 2026-08-11
  15. Transparency & Public TrustTown of Olds · Municipal record · Accessed 2026-07-23
  16. Synapse Olds Data CentreGovernment of Alberta Major Projects · Government database · Accessed 2026-07-23
  17. Recognition of Treaty TerritoriesTown of Olds · Municipal record · Accessed 2026-08-12
  18. Synapse Data Center Inc. announces proposed Olds developmentTown of Olds / Invest Olds · Company disclosure · 2026-01-27
  19. Synapse Data Center and Natural Gas Plant DevelopmentSynapse Data Center · Company disclosure · Accessed 2026-07-23
  20. Synapse confirms the Olds project will not proceed as proposedGlobal News · News reporting · 2026-08-18