Evidence profile · Municipal District of Greenview No. 16

Wonder Valley AI Data Centre Park

A proposed off-grid AI campus in Greenview, with up to 1 GW of Phase 1 computing load and a larger gas-power system.

Illustrative landscape · Sevgi Gümüş / Pexels
← Alberta data centre project list
Developer O'Leary Digital LimitedView on project map ↗

Greenview Industrial Gateway, approximately 42 km south of Grande Prairie · Map precision: Approximate area

Planning, studies, and regulatory preparation continue. Phase 1 power is now described as up to 2 GW; longer-term figures still conflict between 7.5 GW and 9 GW. Greenview's regional water licence is separate from project approval. Sturgeon Lake Cree Nation has filed three separate judicial reviews concerning the water licence, Alberta's environmental assessment decision, and the Level 1 consultation classification. The filings do not overturn those decisions.

Phase 1 computing targetUp to 1 GWTen approximately 100 MW facilities; up to 2 GW power proposed [12]
Regional water licence6 billion L/yearGateway-wide limit; project demand estimate and actual use are separate [15][8]
Sound assessmentIn preparationNo final receptor predictions or mitigation plan found [13][8]
Binding job commitmentsNot foundNo binding numerical construction or permanent-job commitments
Annual emissionsNot publishedGas generation proposed; capture-ready claim is not a capture commitment [13][8][11]
Proposed areaConflicting figuresAbout 15,850 acres in filing; website says 13,000 acres [13][11]

Where it stands

Project approvalsIncompletePlanning and regulatory preparation; no final investment decision confirmed [8]
Land transactionCouncil authorizationMarch 25, 2025 authorization does not establish closed transfers [5]
Provincial assessmentEIA report not required; challengedMarch 31, 2026 decision subject to September 29 judicial review application; other approvals still required [14][20]
Water-licence challengeJudicial review continuesAugust 13, 2026 ruling did not overturn the licence or decide consultation adequacy [17]
Consultation classificationLevel 1 under court challengeOctober 15, 2026 application challenges the April 15 classification; allegations remain unproven [13][21]

Separate approval tracks, not a construction progress bar. Record last verified 2026-11-04.

Want to get involved?

The record includes the June 4, 2026 open house and three separate judicial reviews: the water licence, the provincial environmental assessment decision, and the Level 1 consultation classification. Neither of the latter filings is a court ruling. No current public comment deadline or open hearing invitation was verified. The Indigenous-context and approvals topics distinguish allegations, decisions, and outstanding processes. See the approval and participation record ↓

Power and emissionsCampus demand, electricity supply, and emissions evidence

O'Leary Digital's current FAQ separately describes planned Phase 1 data centre IT load and the larger on-site power system. Both remain proponent projections, not approved or operating capacity.

Important distinction: The current FAQ says Phase 1 could include up to ten approximately 100 MW data centre facilities supported by up to 2 GW of on-site power. The original announcement used 1.4 GW for Phase 1. Longer-term records still conflict between 7.5 GW and 9 GW.

Phase 1 data centre capacity: Up to 1 GW of IT load. The current FAQ says Phase 1 could support up to ten data centre facilities, each designed for approximately 100 MW of IT load. This is not approved or operating capacity. [12] Proponent projection

Phase 1 power: Up to 2 GW proposed. O'Leary Digital's current FAQ describes up to 2 GW of on-site power. The original 2024 announcement and provincial record used 1.4 GW. [12][7][10] ADCW context

Full-build power: 7.5 GW or 9 GW. The current project website says 7.5 GW, while the March 2026 consultation filing says approximately 9 GW. The reviewed records do not reconcile the difference. [11][13] ADCW context

Power model: Entirely off-gridNon-grid-connectedThe facility has no electrical connection to Alberta's interconnected grid and relies on supply available to the site.It does not directly draw from or send electricity to that grid. Power-plant approvals and local impacts can still matter.Learn more → in current filing. The March 2026 filing describes dedicated generation and says a future connection to Alberta's grid may be considered. [13] Proponent statement

Primary generation: Natural gas. The project is planned around large-scale on-site natural-gas power generation. Final generating equipment and phase-by-phase capacity were not found in the reviewed public record. [7][13] Proponent statement

Geothermal component: Potential addition. The original announcement described geothermal as a possibility. No committed geothermal capacity, design or schedule was found. [7] ADCW context

Carbon management: Capture-ready design claimed. The current project website describes the design as carbon-capture-ready. It does not identify an approved capture facility, committed capture rate or operating date. [11] ADCW context

Anticipated air releases: Local pollutants and CO₂ identified. The consultation filing identifies potential nitrogen dioxide, carbon monoxide, particulate matter, ammonia and carbon dioxide emissions. Project-specific modelling is still being prepared. [13] Proponent statement

Annual greenhouse-gas emissions: Not published in reviewed primary sources. No project-specific annual CO₂e estimate or natural-gas consumption figure was found in the reviewed municipal, regulatory and proponent records. [13][8] ADCW context

Full-build heat release, preliminary estimate: 16–18 GW under a 9 GW generation scenario. In June 2026, physicist Robert Davies estimated that continuous on-site generation and use of 9 GW of electricity would ultimately release roughly 16–18 GW of energy as heat at the site, including generation losses. This is a first-order estimate for one disputed full-build capacity scenario, not an approved design, measured heat release, or prediction of local temperature rise. The project website separately says 7.5 GW. [22][13][11] ADCW context

What remains unresolved

The reviewed primary records do not reconcile the proposed full-build power figures. O'Leary Digital's current website says 7.5 GW, while its March 2026 consultation filing says 9 GW.

The published Phase 1 IT-load figure is a proponent projectionProponent projectionA forecast, target, estimate, or promised future outcome from the company proposing the project.The label identifies whose projection it is. It does not turn a future claim into an independently verified result or an enforceable approval condition.Learn more →. No committed customer, approved data centre capacity or binding construction commitment was found in the reviewed public record.

Final power-plant equipment, phase-by-phase generating capacity, natural-gas demand, annual greenhouse-gas emissions and any actual carbon-capture commitment have not been published in the reviewed primary sources.

The 2024 announcement mentioned potential geothermal power, but no committed capacity, technology, approval path or schedule has been published.

Water, cooling, and drainageSupply, demand, wastewater, and servicing

Greenview holds the water licence for the wider industrial gateway. Wonder Valley would receive water through that municipal system rather than hold its own Smoky River diversion licence. [15][16]

Licensed annual diversion: Up to 6 million m³ (6 billion L). Greenview's Water Act licence authorizes industrial and commercial use within the Greenview Industrial Gateway. The licence expires April 1, 2035. [15] Public record

Maximum diversion rate: 0.56 m³/second (560 L/second). The licence requires reduced or stopped withdrawals when Smoky River flows fall below specified thresholds. [15] Public record

Estimated project demand: Less than 6 million m³/year (6 billion L/year). The Spring 2026 update says full-build demand is expected to remain below the licensed volume, though its summary table rounds the estimate to 6 million m³/year (6 billion L/year). [8] Proponent projection

Future regional allocation: Up to 24 million m³/year (24 billion L/year) is not licensed. Greenview has taken an early regulatory step toward a possible future allocation of this larger amount, but it cannot withdraw it under the preliminary certificate. Its current licence allows up to 6 million m³/year (6 billion L/year). A separate licence would be needed before the larger volume could be diverted. [8][13][16] ADCW context

Permanent intake works: Application identified. The consultation filing says Greenview submitted Water Act Application DAPP0128310 for permanent Smoky River intake infrastructure. [13] Public record

Water system design: Reuse and recirculation under study. The project update describes storage ponds, treatment, potential reuse and recirculation, stormwater controls and wastewater infrastructure. Final designs and operating balances are not public. [8][13] Proponent projection

Connected waterways: McMillan Creek and Smoky River. The filing maps creeks, wetlands and drainage channels in the project area that connect to McMillan Creek and the Smoky River. It reports 23 fish species in this wider connected water system. [13] Proponent statement

What remains unresolved

The Spring 2026 update describes full-build water demand as both less than 6 million m³/year (6 billion L/year) and, in a summary answer, 6 million m³/year (6 billion L/year). Phase-level withdrawal, consumption and discharge volumes remain unresolved.

Greenview's preliminary certificate for up to 24 million m³/year (24 billion L/year) is not a licence to divert that volume. Whether, when or for whose projects Greenview will seek a larger permanent licence remains unresolved.

Sound at nearby communitiesAssessment evidence, controls, and remaining questions

Project-specific sound work remains in preparation. A June 2026 preliminary assessment prepared for Sturgeon Lake Cree Nation's legal counsel identifies potential cooling-system and low-frequency noise effects on wildlife and traditional land use. Site-specific acoustic modelling and actual equipment specifications are needed to determine impacts.

Noise-impact study: Still in preparation. The March 2026 consultation filing says project-specific noise work is being prepared alongside air, aquatic, wildlife, and vegetation studies. No final noise-impact assessment, predicted receptor level, or mitigation plan was found in the reviewed record. [13][8] Proponent statement

Cooling-system sound and wildlife: Site-specific modelling needed. Davies's June 2026 preliminary assessment flags possible continuous fan and low-frequency sound effects on birds, other wildlife, and traditional land use, drawing on an assumed full-build cooling system and studies from other industrial sites. It does not establish Wonder Valley equipment specifications, receptor sound levels, or actual effects. [22] ADCW context

Land, wetlands, and wildlifeSite area and the available environmental record

Project area: 64.17 km² (6,417 ha) in filing. The March 2026 consultation filing describes about 15,850 acres. The current project website instead says 13,000 acres. [13][11] ADCW context

Land agreement: Council authorization on March 25, 2025. Greenview authorized a Wonder Valley purchase and sale agreement with 2664755 Alberta Ltd. and the purchase of 1,650 acres of Crown land for resale to that company. The public motion does not establish that either land transaction has closed. [5] Public record

Wetland disturbance: Up to 0.91 km² (91 ha) estimated. The consultation filing identifies temporary and permanent disturbance across all phases. It says final impact areas will be determined through later wetland assessments. [13] Proponent projection

Environmental studies: Ongoing. The consultation filing identifies grizzly bear, sensitive bird species, wetlands and other habitat in the broader project area. Project-specific air, noise, aquatic, wildlife and vegetation work is still being prepared. [13][8] Proponent statement

What remains unresolved

The reviewed primary records do not reconcile the proposed site area. The current project website says 13,000 acres, while the consultation filing describes 64.17 km² (6,417 ha), or about 15,850 acres.

The conditions, closing status and completed land transfers under the reported purchase and sale agreement were not established in the reviewed public sources.

The June 2026 Davies assessment is preliminary and assumes continuous generation of 9 GW at full build. Actual cooling equipment, sound at receptors, local thermal effects, and cumulative environmental effects still require project-specific evidence.

The map point is the Alberta Major Projects location for orientation within the Greenview Industrial Gateway. It does not represent the boundaries of the 64.17 km² (6,417 ha) project area.

Indigenous contextTreaty geography, engagement, and consultation evidence

Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.

Treaty geography: Treaty 8 territory. The federal historical treaty-boundary dataset places the project area within Treaty 8. Treaty geography does not by itself identify which communities are affected or establish consultation outcomes. [18] ADCW context

Communities named for consultation: Four communities identified. The Aboriginal Consultation Office recommendation names Gift Lake Métis Settlement, Horse Lake First Nation, Sturgeon Lake Cree Nation and Sucker Creek First Nation for Level 1 consultation. [13] Public record

Water-licence appeal: Sturgeon Lake Cree Nation appeal dismissed on standing. The Environmental Appeals Board did not decide the constitutional consultation questions raised or determine whether consultation was adequate. [16] Public record

Water-licence judicial review: SLCN's challenge will proceed. On August 13, 2026, Alberta Court of King's Bench Justice P.K. Johal dismissed O'Leary Digital's application to strike SLCN's judicial review and refused its alternative requests to participate as an intervener or respondent. This procedural ruling did not overturn Greenview's water licence or decide whether Alberta met its duty to consult. [17] Public record

Environmental assessment judicial review: Filed September 29, 2026. Sturgeon Lake Cree Nation's originating application, Court of King's Bench file 2603-21528, challenges Alberta's March 31, 2026 decision not to require an environmental impact assessment report. The allegations are not findings, and the filing does not reverse the province's decision. [20][14] Public record

Consultation classification judicial review: Filed October 15, 2026. A separate originating application, Court of King's Bench file 2603-22650, challenges the April 15, 2026 decision to classify consultation as Level 1. The application alleges inadequate consultation; no merits ruling was verified. [21][13] Public record

Potential cumulative effects: Independent assessment calls for further study. Davies's June 2026 assessment, prepared for the Nation's legal counsel, calls for site-specific modelling of heat, sound, air emissions, water, and combined effects on existing industrial activity and traditional land use. This preliminary opinion is not a completed environmental impact assessment or a regulator finding. [22][13] ADCW context

Potential effects: Treaty-rights questions remain unresolved. The consultation filing identifies possible effects on wetlands, wildlife, access and Treaty rights. Final findings, mitigation commitments and consultation outcomes have not been published. [13] ADCW context

What remains unresolved

The consultation filing identifies potential effects on wetlands, wildlife, access and Treaty rights. Final assessment findings, mitigation commitments and consultation outcomes have not been published.

The Environmental Appeals Board decision addressed standing for the water-licence appeal. It did not decide the constitutional consultation questions raised by Sturgeon Lake Cree Nation.

Sturgeon Lake Cree Nation's water-licence judicial review remains before the Court of King's Bench. The August 13, 2026 procedural ruling allowed the case to continue but did not decide whether Alberta met its duty to consult, overturn Greenview's water licence, or stop Wonder Valley.

Approvals and participationSeparate decisions, public participation, and the recorded timeline

Greenview's public record shows that an earlier commercial arrangement preceded the November 2024 land-use hearing; neither the letter of intent nor the amendment was project approval. Sturgeon Lake Cree Nation filed additional judicial review applications on September 29 and October 15, 2026 challenging the environmental assessment and consultation decisions. These are separate from the continuing water-licence judicial review. No ruling on the merits of either new case was verified.

Current stage: Planning and regulatory preparation. The Spring 2026 project update says technical studies, consultation, design work and regulatory preparation are underway. Required approvals are not complete. [8] Proponent statement

Earlier commercial arrangement: LOI preceded the land-use hearing. Greenview's October 22 minutes show that council told staff to proceed with a letter of intent involving potential Greenview Industrial Gateway customers. The public minutes do not name the customer. Canada's National Observer later connected the letter of intent to an O'Leary company. The linked court filing includes the related land agreement. The November 12 hearing and final adoption of Bylaw 24-979 came three weeks later. [3][6][4][2] ADCW context

Data-centre land-use amendment: Six-minute hearing on November 12, 2024. Greenview first read Bylaw 24-979 on October 8 with data-processing centres proposed as a discretionary use in the industrial gateway. No one spoke at the November 12 hearing. Council then made the use permitted and passed second and third readings. A permitted land use is not approval for Wonder Valley, and project-specific requirements still apply. [1][2][4] Public record

Provincial environmental impact assessment: Not required under March 2026 decision; challenged. Alberta Environment and Protected Areas decided not to require an environmental impact assessment report. Sturgeon Lake Cree Nation's September 29, 2026 application seeks judicial review. The decision has not been overturned; other EPEA, Water Act, Public Lands Act, historical-resource, and consultation requirements may apply. [14][20] Public record

Consultation level: Level 1 classification challenged. The Aboriginal Consultation Office recommended Level 1 consultation on April 15, 2026. Sturgeon Lake Cree Nation filed a separate judicial review on October 15, 2026. The filed allegations are not a court finding that consultation was inadequate. [13][21] Public record

Industrial and water-treatment approvals: Applications being prepared. The consultation filing describes two planned EPEA applications, one for the industrial facility and one for centralized water treatment and distribution. [13] Proponent statement

Area structure plan: High-level planning framework in place. Greenview says an approved area structure plan guides future land use but does not replace rezoning, subdivision, development permits or detailed engineering for individual parcels. [19] Public record

Public engagement: Open house held June 4, 2026. The project update describes ongoing Indigenous and stakeholder engagement, information sessions, open houses and technical working sessions. [8][9] Proponent statement

Recorded timeline

Observed decisions and future dates are kept distinct; projected milestones may change.

October 8, 2024. Greenview gave first reading to Bylaw 24-979. The draft added data-processing centres, including digital-currency processing, as a discretionary use in the Greenview Industrial Gateway. [1][2] Public record

October 22, 2024. Council told staff to proceed with a letter of intent involving potential Greenview Industrial Gateway customers. The public minutes did not name the customer. Canada's National Observer later connected the letter of intent to an O'Leary company. The linked court filing includes the related land agreement. [3][6] ADCW context

November 12, 2024. Greenview held a six-minute hearing with no speakers, changed data-processing centres from a discretionary to a permitted use in the industrial gateway, and passed second and third readings of Bylaw 24-979. [4][2] Public record

December 9, 2024. Greenview and O'Leary Ventures announced a letter of intent for land purchase and development, a 1.4 GW first phase and a potential 7.5 GW full build. [7] Proponent statement

March 25, 2025. Greenview authorized a purchase and sale agreement with 2664755 Alberta Ltd. for Wonder Valley and the purchase of 1,650 acres of Crown land for resale to that company. The public motion does not establish that either transfer has closed. [5] Public record

April 7, 2025. Alberta issued Water Act Licence DAUT0021649 to Greenview for up to 6 million m³/year (6 billion L/year) from the Smoky River. [15] Public record

March 31, 2026. Alberta Environment and Protected Areas decided that a provincial environmental impact assessment report was not required for the current project description. [14] Public record

April 15, 2026. The Aboriginal Consultation Office issued its pre-consultation recommendation for the planned EPEA and Water Act activities. [13] Public record

April 17, 2026. The Environmental Appeals Board dismissed Sturgeon Lake Cree Nation's appeal of Greenview's water licence on standing grounds. [16] Public record

May 28, 2026. Greenview published O'Leary Digital's Spring 2026 update stating that planning, studies, consultation and regulatory preparation were continuing. [9][8] Proponent statement

June 4, 2026. The project team held a public open house at the Grovedale Community Hall. [8] Proponent statement

August 13, 2026. The Court of King's Bench dismissed O'Leary Digital's application to strike Sturgeon Lake Cree Nation's judicial review. The underlying consultation challenge remains before the court. [17] Public record

August 2026. O'Leary Digital's current FAQ described Phase 1 as up to 2 GW of on-site power supporting up to ten approximately 100 MW data centre facilities. The original 1.4 GW Phase 1 announcement remains part of the project history. [12][7] Proponent statement

September 29, 2026. Sturgeon Lake Cree Nation filed Court of King's Bench application 2603-21528 seeking judicial review of Alberta's March 31, 2026 decision not to require a provincial environmental impact assessment report. The application has not determined the merits. [20][14] Public record

October 15, 2026. Sturgeon Lake Cree Nation filed separate Court of King's Bench application 2603-22650 seeking judicial review of the April 15, 2026 Level 1 consultation classification. No final outcome was verified. [21][13] Public record

2027. Target for site construction to begin, subject to approvals, technical studies, engagement, commercial requirements and final investment decisions. [8][13] Proponent projection

2028. Target for initial power availability and continued infrastructure development. [8] Proponent projection

2029 onward. Proposed phased development toward full build over approximately ten or more years. [8] Proponent projection

What remains unresolved

The public status, application numbers and supporting studies for every required AUC, EPEA, Water Act, municipal, federal and historical-resource approval are not yet available as one complete record.

The September 29 and October 15, 2026 judicial review applications separately challenge the environmental assessment and Level 1 consultation decisions. Their allegations are unproven and no final merits rulings were verified.

Company and commitmentsScale, projected benefits, and delivery commitments

Phase 1 estimated cost: $12 billion. The provincial Major Projects database estimate does not label the currency on the project page. The original announcement separately described about US$2 billion for the first-phase power system. [10][7] ADCW context

Full-build investment: More than $70 billion claimed. The 2024 announcement does not identify the currency in the quoted total. No final investment decision was found in the reviewed record. [7][10] Proponent projection

Target construction start: 2027, subject to approvals. The project update and consultation filing describe a target, not an authorized construction date. [8][13] Proponent projection

Project overview

O'Leary Digital proposes a multi-phase AI data centre industrial park with dedicated natural-gas generation in the Greenview Industrial Gateway. Required approvals, customers, financing and a final investment decision remain unconfirmed. Sturgeon Lake Cree Nation has filed three distinct judicial reviews concerning the regional water licence, the province's decision not to require an environmental impact assessment report, and the Level 1 consultation classification. The filings do not overturn those decisions or establish an approval for Wonder Valley.

What remains unresolved

A final investment decision, committed customer, financing structure and binding construction schedule were not found in the reviewed public record.

No binding numerical commitments for construction jobs, permanent jobs, municipal tax revenue, local procurement or Indigenous benefits were found in the reviewed primary sources.

Unresolved questions are retained within each relevant topic above.

SourcesOriginal documents and publication details

Source record

Company disclosures establish what the company said, not independent verification of projected outcomes.

  1. October 8, 2024 Regular Council meeting minutesMunicipal District of Greenview No. 16 · Municipal record · 2024-10-08
  2. Bylaw 24-979: Greenview Industrial Gateway land-use amendmentMunicipal District of Greenview No. 16 · Municipal record · Passed 2024-11-12
  3. October 22, 2024 Regular Council meeting minutesMunicipal District of Greenview No. 16 · Municipal record · 2024-10-22
  4. November 12, 2024 Regular Council meeting minutesMunicipal District of Greenview No. 16 · Municipal record · 2024-11-12
  5. March 25, 2025 Regular Council meeting minutesMunicipal District of Greenview No. 16 · Municipal record · 2025-03-25
  6. Affidavit of Paul Palandjian with attached Wonder Valley land agreementCourt of King's Bench of Alberta · Court filing · Filed 2026
  7. World's largest AI Data Centre Industrial Park 'Wonder Valley' coming to the Greenview Industrial GatewayMunicipal District of Greenview No. 16 · Municipal record · 2024-12-09
  8. Wonder Valley Project Update Newsletter, Spring 2026O'Leary Digital / Municipal District of Greenview No. 16 · Company disclosure · 2026-05
  9. Wonder Valley NewsletterMunicipal District of Greenview No. 16 · Municipal record · 2026-05-28
  10. Wonder Valley AI Data Centre Park, Phase 1Government of Alberta Major Projects · Government database · Accessed 2026-07-26
  11. Wonder Valley project websiteO'Leary Digital · Company disclosure · Accessed 2026-07-26
  12. Wonder Valley project FAQO'Leary Digital · Company disclosure · Accessed 2026-08-20
  13. Wonder Valley Project pre-consultation assessment, FNC202650876O'Leary Digital / Alberta Aboriginal Consultation Office · Regulatory filing · Recommendation issued 2026-04-15
  14. Decision that no environmental impact assessment report is requiredAlberta Environment and Protected Areas · Regulator · 2026-03-31
  15. Water Act Licence DAUT0021649Alberta Environment and Protected Areas · Regulator · 2025-04-07
  16. Standing Decision: Sturgeon Lake Cree Nation v Designated Director under the Water ActAlberta Environmental Appeals Board · Regulator · 2026-04-17
  17. Sturgeon Lake Cree Nation v Alberta (Minister of Indigenous Relations), 2026 ABKB 569Court of King's Bench of Alberta · Court decision · 2026-08-13
  18. Treaty Boundary datasetGovernment of Canada Open Government Portal · Government database · Modified 2026-06-29
  19. Area Structure PlansMunicipal District of Greenview No. 16 · Municipal record · Accessed 2026-07-26
  20. Originating application 2603-21528: provincial environmental assessment decisionCourt of King's Bench of Alberta · Court filing · Filed 2026-09-29
  21. Originating application 2603-22650: Level 1 consultation classificationCourt of King's Bench of Alberta · Court filing · Filed 2026-10-15
  22. Preliminary technical assessment: environmental considerations of Wonder ValleyRobert Davies, PhD; prepared for Sturgeon Lake Cree Nation's legal counsel · Independent assessment · 2026-06