Evidence profile · Municipal District of Greenview No. 16

Kakwa Data Processing Centre

A proposed cryptocurrency data-processing centre at an existing industrial lease in Kakwa.

Illustrative landscape · Sevgi Gümüş / Pexels
← Alberta data centre project list
Developer New West Data Acquisition Corp.View on project map ↗

SE-23-63-5-W6M, Kakwa area, M.D. of Greenview · Map precision: Approximate area

The 8.40 MW isolated gas plant and a Crown disposition are approved. Greenview's September 9, 2026 agenda recommends a municipal permit for up to 9.9 MW of data processing, but the reviewed record does not establish an issued permit, completed construction, or operation.

Proposed processing limitUp to 9.9 MWRecommended municipal ceiling, not approved or measured load [1]
Water demandNot quantifiedCooling, withdrawal, consumption, and discharge unconfirmed [1]
Cumulative sound39.7 dBAApplicant model at most affected receptor; 40.0 dBA limit [1]
Approved generation8.40 MWFive gas engines; separate from the data-processing ceiling [3][4]
Annual emissionsNot quantifiedFuel use and greenhouse-gas emissions remain unresolved
Lease site≈3.26 acresCryptocurrency activity area is a smaller 0.248 ha [1]

Where it stands

Municipal permitApproval recommendedD26-087; Commission decision and issued permit not reviewed [1]
Power plantAUC approval issuedFebruary 12, 2026; other required authorizations remain separate [3][4]
Crown landDisposition issuedDLO260092 effective June 15, 2026; other permits still required [1]

Separate approval tracks, not a construction progress bar. Record last verified 2026-09-21.

Want to get involved?

The municipal application was scheduled for September 9, 2026. The agenda says an approved discretionary-use permit must be circulated for at least 21 days after the decision is issued. This record does not verify that decision or establish that a notice or appeal window is currently open. See the approval and participation record ↓

Power and emissionsCampus demand, electricity supply, and emissions evidence

The 9.9 MW municipal limit and the 8.40 MW AUC-approved power plant describe different things. ADCW reports the proposed data-centre ceiling and purpose-specific generation separately and does not add them together.

Important distinction: The approved power plant is isolated from the Alberta grid. Approval of the power plant does not establish that the data centre received its municipal permit, completed construction, or began operating.

Proposed municipal limit: Up to 9.9 MW. The recommended motion applies this ceiling to the data-processing centre. It is not a measured load or evidence of approval. [1] Public record

Approved generation: 8.40 MW. Five Caterpillar G3520 natural-gas reciprocating engines. [3][4] Public record

Grid relationship: Isolated and off-gridNon-grid-connectedThe facility has no electrical connection to Alberta's interconnected grid and relies on supply available to the site.It does not directly draw from or send electricity to that grid. Power-plant approvals and local impacts can still matter.Learn more →. The AUC application says the plant would not connect to the Alberta Interconnected Electric System. The Crown disposition also requires standalone power. [2][1] Public record

AUC construction deadline: June 30, 2026. The approval required completion by this date unless otherwise authorized. The date passing does not prove construction was completed. [4] Public record

Environmental approval dependency: Status not confirmed. The AUC said construction could not begin until the Environmental Protection and Enhancement Act industrial application was approved. The reviewed records do not confirm the later decision. [3] Public record

AER facility licence: F53063 amendment cited. Greenview staff list an Alberta Energy Regulator facility licence amendment among the supporting records. The amendment itself was not included in the four documents reviewed by ADCW. [1] Public record

What remains unresolved

The reviewed sources do not confirm whether the power plant met its June 30, 2026 construction deadline, received an extension, was completed, or entered service.

The relationship between the proposed 9.9 MW municipal ceiling and the approved 8.40 MW generation capacity is not explained.

Fuel use and greenhouse-gas emissions are not publicly quantified in the reviewed records.

Water, cooling, and drainageSupply, demand, wastewater, and servicing

Cooling and routine water demand: Not publicly quantified. The reviewed records do not identify a cooling design or quantify operational water withdrawalWithdrawal, consumption, and dischargeWithdrawal is water taken from a source. Consumption is the portion not returned to the same water system. Discharge is water released after use or treatment.These are different quantities. Check which one a water figure describes before comparing projects.Learn more →, consumption, or discharge for the data centre. [1] ADCW context

Recommended municipal safeguards: Runoff and watercourse protections. If adopted, the recommended permit conditions would require runoff not to exceed pre-development flows and would restrict impacts to groundwater, drainage, and watercourses. These are recommended conditions, not a verified issued permit. [1] Public record

What remains unresolved

Cooling technology, routine water demand, wastewater, and fire-protection water are not publicly quantified in the reviewed records.

Sound at nearby communitiesAssessment evidence, controls, and remaining questions

Highest modelledModelled versus measuredA modelled result is a prediction based on inputs and assumptions. A measured result comes from observations or instruments under particular conditions.A prediction is not verified operating performance. Check the location, period, operating scenario, and what the reported number actually represents.Learn more → cumulative sound: 39.7 dBA. Greenview staff report 39.7 dBA at the most affected receptor against a 40.0 dBA permissible level. This is applicant modelling, not an operating measurement. [1] Proponent projection

Nearby residences: None known within 1.5 km. The municipal report and survey state that no residence was known within 1.5 kilometres. This does not establish measured operating sound. [1] Public record

What remains unresolved

Measured operating sound is not publicly quantified in the reviewed records.

Land and site layoutSite footprint and the planning information in the record

Subject property: Approx. 1.32 ha. The municipal report describes the Crown-land lease site as approximately 3.26 acres. The survey identifies a smaller 0.248-hectare cryptocurrency activity area. [1] Public record

Indigenous contextTreaty geography, engagement, and consultation evidence

Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.

Consultation geography: Crown land within the consultation radii. The applicant reported no First Nations reserve or Métis Settlement within the consultation radii. That statement does not establish whether Indigenous rights or interests may be affected. [2][3] Proponent statement

Consultation path: No Crown consultation directed for the AUC filing. The applicant said its land agent advised that the filing did not trigger Crown consultation notice. The AUC recorded that the applicant would follow Alberta Energy Regulator direction for the separate Environmental Protection and Enhancement Act process. These records do not establish consultation, consent, or any community's position. [2][3] Public record

What remains unresolved

Treaty geography and project-specific Indigenous consultation outcomes or community positions are not established in the reviewed sources.

Approvals and participationSeparate decisions, public participation, and the recorded timeline

The power plant approval, Crown disposition, Alberta Energy Regulator licence, environmental authorization, and municipal development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more → are separate decisions. The municipal record reviewed by ADCW contains an approval recommendation, not the Commission's recorded vote or an issued permit.

Municipal file: D26-087. Discretionary-use development-permit application scheduled for the September 9, 2026 Municipal Planning Commission meeting. [1] Public record

AUC proceedingAUC proceedingA proceeding is the Alberta Utilities Commission's formal record for reviewing an application, including evidence, submissions, and a decision when issued.A proceeding number helps locate the record. The existence of a proceeding does not mean the application has been approved.Learn more →: 30521. Application 30521-A001 resulted in Decision 30521-D01-2026 and Approval 30521-D02-2026. [2][3][4] Public record

Crown disposition: DLO260092. Effective June 15, 2026 and expiring January 22, 2044, or earlier with the primary disposition. [1] Public record

Municipal status: Approval recommended, decision not reviewed. Greenview administration recommended approval at the September 9, 2026 meeting. An agenda recommendation is not the Municipal Planning Commission's decision. [1] Public record

Land-use classification: Discretionary use. A Data Processing Centre is discretionary in the Crown Land District under Land Use Bylaw 25-1000. [1] Public record

Post-decision notice: Minimum 21-day circulation. The agenda says an approved discretionary-use permit must be circulated for at least 21 days after the decision is issued. [1] Public record

Provincial land authorization: DLO260092 issued. The disposition authorizes cryptocurrency-related commercial activity but requires compliance with all other applicable permits and approvals. [1] Public record

Other permits: Still separate. The recommended municipal conditions require safety-code permits and a roadside development permit before development begins. [1] Public record

Recorded timeline

Observed decisions and future dates are kept distinct; projected milestones may change.

December 22, 2025. New West Data Acquisition Corp. registers Application 30521-A001 for the 8.40 MW Kakwa Isolated Power Plant. [2][3] Public record

February 12, 2026. The AUC approves construction and operation of the isolated natural-gas power plant, subject to its terms and other required authorizations. [3][4] Public record

June 15, 2026. Crown disposition DLO260092 takes effect for overlapping rural commercial cryptocurrency activity. [1] Public record

September 9, 2026. Greenview's Municipal Planning Commission agenda presents D26-087 with an administrative recommendation to approve the data-processing centre. The reviewed package does not record the Commission's decision. [1] Public record

January 22, 2044. Crown disposition DLO260092 is scheduled to expire, unless it ends earlier with the primary disposition or changes under applicable law. [1] Public record

What remains unresolved

The reviewed agenda package does not establish whether the Municipal Planning Commission approved, refused, or tabled D26-087, or whether an issued permit became effective after notice and appeal.

The Environmental Protection and Enhancement Act industrial-approval status is not confirmed in the reviewed records.

Company and commitmentsScale, projected benefits, and delivery commitments

Workload: Cryptocurrency mining. Greenview's agenda and Crown disposition identify the proposed activity as cryptocurrency data processing. [1] Public record

Project overview

New West Data Acquisition Corp. proposes multiple cryptocurrency data-processing pods at an existing industrial lease site in the Kakwa area. The AUC approved an 8.40 MW isolated gas plant in February 2026, and a Crown disposition for cryptocurrency activity took effect in June 2026. Greenview's September 9, 2026 agenda recommends approval of D26-087, but the reviewed package is not an issued municipal permit or meeting decision.

What remains unresolved

The number, design, operator, computing equipment, and operating status of the data-processing pods are not fully established.

Unresolved questions are retained within each relevant topic above.

SourcesOriginal documents and publication details

Source record

Company disclosures establish what the company said, not independent verification of projected outcomes.

  1. September 9, 2026 Municipal Planning Commission meeting page: D26-087 is item 6.1, pages 44–72 of the agenda packageMunicipal District of Greenview No. 16 · Municipal record · 2026-09-09
  2. Proceeding 30521: Rule 007 application for the Kakwa Isolated Power PlantNew West Data Acquisition Corp. / Alberta Utilities Commission · Regulatory filing · 2025-12-22
  3. Decision 30521-D01-2026: 8.40-Megawatt Kakwa Isolated Power PlantAlberta Utilities Commission · Regulator · 2026-02-12
  4. Approval 30521-D02-2026: 8.40-Megawatt Kakwa Isolated Power PlantAlberta Utilities Commission · Regulator · 2026-02-12