Lynx Data Centre Proposal
An early-stage data-centre proposal in Sturgeon County with 3,600 MW requested across two phases. Approximately 134 acres were reportedly acquired beside Greenlight; the full campus footprint and construction approvals remain unconfirmed.
Lynx requests 3,600 MW of electricity for its two proposed data-centre phases. Two associated Sturgeon Gas plants have separate supply requests totalling 3,728 MW; The Logic reports that they are intended to power Lynx. These figures describe electricity demand and proposed supply. The newspaper's November 11, 2026 reporting also identifies a Pembina-linked landowner. The customer and final power arrangement remain unconfirmed, and Lynx's service dates are under review.
Where it stands
Separate approval tracks, not a construction progress bar. Record last verified 2026-11-11.
No Lynx-specific public hearing or submission deadline was identified. This profile will be updated when a municipal notice or regulatory filing establishes the relevant process. Existing Meta and Greenlight processes are separate. See the approval and participation record ↓
Power and emissionsCampus demand, electricity supply, and emissions evidence
Lynx's two electricity-demand requests and the associated generation requests describe different parts of a proposed development. Neither figure is an operating measurement or a construction approval.
Important distinction: 3,600 MW is the requested load across two phases. The separate 3,728 MW figure is requested supply service at the two Sturgeon Gas proposals. These figures must not be added together as campus capacity.
Lynx load requests: P3198 and P3204: 1,800 MW each. AESO records application dates of February 27, 2026 and May 7, 2026. Both November 2026 entries are Stage 1 Connection projects, classified Data Load, in Area 33, Fort Saskatchewan, with in-service dates under review. The 3,600 MW total is requested electricity delivery capacity, not installed computing capacity or guaranteed grid access. [1] Public record
Associated gas-generation requests: P3215 and P3217: 1,864 MW each. AESO lists Sturgeon Gas and Sturgeon Gas 2 as Stage 1, Cluster 3 gas requests in Area 33, filed August 6, 2026. Together they request 3,728 MW of supply service. The Logic reports their connection to Lynx; a final electrical design and supply agreement have not been established. [1][2] Public record
Generation target: June 1, 2031. This date belongs to both Sturgeon Gas requests. Lynx's own in-service dates remain under review, so it is not a confirmed campus opening date. [1] Public record
Relationship to existing Greenlight: Separate proposal and approval records. The Logic distinguishes Lynx and Sturgeon Gas from a potential expansion of the existing Greenlight plant. Pembina's Q3 report describes Greenlight's 932 MW first phase and potential expansion to 1,864 MW. Those figures, ownership shares, and approvals do not establish Lynx's design or permissions. [2][5] ADCW context
Emissions and backup generationBackup generationBackup generators provide electricity when the normal supply is unavailable. They may also run for testing or maintenance.Installed capacity does not establish continuous operation, annual fuel use, or emissions. Operating hours and permit conditions are separate evidence.Learn more →: Project-specific figures not established. No Lynx-specific equipment count, fuel demand, greenhouse-gas inventory, air-quality assessment, or backup-generation plan was identified. These cannot be calculated by scaling neighbouring projects. ADCW context
What remains unresolved
Final electrical connections, gas supply, equipment ratings, backup generation, and emissions are not established by the queue requests.
Water, cooling, and drainageSupply, demand, wastewater, and servicing
No Lynx-specific cooling technology, water source, allocation, demand, wastewater arrangement, or approved drainage design was identified. Neighbouring projects' designs do not establish Lynx's requirements.
What remains unresolved
Cooling technology, water source, allocation, demand, consumption, wastewater, and drainage design remain unconfirmed.
Sound at nearby communitiesAssessment evidence, controls, and remaining questions
The reviewed sources do not establish a Lynx-specific sound assessment, generator configuration, testing schedule, or mitigation plan.
What remains unresolved
No Lynx-specific assessment of sound at nearby communities or mitigation commitments was identified.
Land, wetlands, and wildlifeSite area and the available environmental record
Reported land acquisition: Approximately 134 acres in October 2026. The Logic reports that a newly incorporated Pembina-linked company acquired the land beside Greenlight. ADCW has not independently obtained the current titles; the full campus footprint remains unconfirmed. [2] ADCW context
Map location: Approximate AESO marker. The November 2026 map places both Lynx requests beside the two Sturgeon Gas requests, west of the separate Greenlight and GLDC markers. Early-stage locations may change and do not establish legal parcel boundaries. [1] Public record
What remains unresolved
The complete campus boundary, legal parcels, buildings, and relationship between the reported 134-acre acquisition and the full development footprint remain unverified.
Indigenous contextTreaty geography, engagement, and consultation evidence
Data centre projects sit within treaty territories and places with longstanding First Nations and Métis connections. Treaty boundaries alone cannot tell us which communities may be affected or how they view a project.
Treaty geography: Treaty 6 territory. Sturgeon County's acknowledgement identifies Treaty 6 territory and longstanding First Nations and Métis connections. Geographic context does not establish consultation, consent, ownership, or any community's position on Lynx. [7] Public record
Project-specific engagement: Not established in reviewed sources. No Lynx-specific public record identifying participating Indigenous communities, concerns, consultation outcomes, or accommodation measures was identified. ADCW context
What remains unresolved
Project-specific Indigenous consultation participants, concerns, outcomes, and accommodation measures have not been established.
Approvals and participationSeparate decisions, public participation, and the recorded timeline
An accepted electricity-system request is an early planning step. It does not establish a development permitDevelopment permitA municipality's approval allows a specified use or development on a particular site, subject to its land-use rules and any conditions.Separate provincial or utility approvals may still be needed. A permit does not establish that construction has begun or that the facility is operating.Learn more →, power-plant approval, final investment decision, or permission to start construction.
Electricity-system stage: Early connection process. Both Lynx entries are Stage 1 with in-service dates under review. Both Sturgeon Gas entries are in Cluster 3. None of these entries establishes a municipal or power-plant construction approval. [1] Public record
Lynx-specific permits: Not established in reviewed sources. ADCW has not identified a Lynx-specific municipal development permit or Alberta Utilities Commission (AUC) power-plant proceeding. This is a gap in the reviewed record, not proof that no application exists. Meta's Project Frost permit and existing Greenlight approvals do not supply that missing evidence. ADCW context
Public participation: No Lynx-specific deadline identified. No current Lynx-specific hearing or submission window was identified. A later municipal notice or regulatory filing may establish the relevant process and participation dates. ADCW context
Recorded timeline
Observed decisions and future dates are kept distinct; projected milestones may change.
February 27, 2026. AESO records the application date for P3198 Lynx Data Load, requesting 1,800 MW. [1] Public record
May 7, 2026. AESO records P3204 Lynx Data Load Phase 2, requesting a further 1,800 MW. [1] Public record
July 30, 2026. Pembina discloses additional land near Greenlight and Redwater for future data-centre power projects, without naming Lynx. [3] Proponent statement
August 6, 2026. AESO records the application dates for P3215 Sturgeon Gas and P3217 Sturgeon Gas 2, each requesting 1,864 MW of supply service. [1] Public record
October 2026. A Pembina-linked company acquires approximately 134 acres, according to The Logic's subsequent reporting. [2] ADCW context
November 5 and 6, 2026. Pembina releases Q3 results and holds its earnings call, discussing a scalable power business and future development on adjacent land. [4][6] Proponent statement
November 11, 2026. The Logic reports the landowner's corporate links and the proposed Lynx and Sturgeon Gas development. ADCW checks the November 2026 AESO workbook and map. [2][1] ADCW context
June 1, 2031 (target). The two Sturgeon Gas requests list this generation-service target. Lynx's load-service dates remain under review. [1] Public record
What remains unresolved
Lynx-specific municipal and power-plant approvals, any public participation dates, a final investment decision, and a construction or operating schedule remain unconfirmed.
Company and commitmentsScale, projected benefits, and delivery commitments
Landowner and corporate links: Pembina connection reported by The Logic. The newspaper identifies Pembina executives Jaret Sprott and Chris Scherman and Morgan Stanley Infrastructure Partners' Daniel Barbosa among directors of the landowning company. Its legal name and ownership shares are not established in the sources reviewed by ADCW. [2] ADCW context
Customer: Not publicly identified. The Logic does not identify a hyperscale customer. A shared regional power-development connection does not identify Lynx's future tenant. [2] ADCW context
Pembina's earlier land disclosure: Additional land disclosed July 30, 2026. Pembina said it had acquired land near Greenlight and Redwater for future gas-to-power data-centre projects. That disclosure predates the October 2026 acquisition reported by The Logic and does not establish that they are the same transaction. [3][2] Proponent statement
Future development strategy: Expansion beyond the first Greenlight phase. Pembina's Q3 release describes data-centre power as a scalable business. In the third-party November 6, 2026 call transcript, management discusses adjacent land and work toward customer agreements in Q4 2026 and Q1 2027. It does not identify a signed Lynx contract or customer. [4][6] Proponent statement
Project overview
Lynx is an early-stage data-centre proposal in Sturgeon County, represented by two 1,800 MW requests in AESO's November 2026 project list. The Logic's November 11, 2026 reporting links the proposal and two Sturgeon Gas power plants to land acquired by a Pembina-linked company. The reported 134-acre purchase does not establish the full campus boundary. The customer, final design, construction approvals, and Lynx opening date remain unconfirmed.
What remains unresolved
The legal landowning company, ownership percentages, campus developer, customer, financing, and signed commercial commitments remain unconfirmed.
Unresolved questions are retained within each relevant topic above.
SourcesOriginal documents and publication details
Source record
Company disclosures establish what the company said, not independent verification of projected outcomes.
- Connection Project Reporting: November 2026 list and project map, P3198, P3204, P3215, and P3217Alberta Electric System Operator · Regulator · Updated November 3, 2026; accessed November 11, 2026
- Another giant data centre is in the works for northern Alberta, right next to Meta's (paywalled)The Logic; Meghan Potkins · News reporting · November 11, 2026
- Pembina Pipeline Reports Results for the Second Quarter of 2026Pembina Pipeline Corporation / U.S. Securities and Exchange Commission · Company disclosure · July 30, 2026
- Pembina Pipeline Reports Results for the Third Quarter of 2026Pembina Pipeline Corporation · Company disclosure · November 5, 2026
- Third Quarter 2026 Interim Report: Greenlight project and ownershipPembina Pipeline Corporation / U.S. Securities and Exchange Commission · Company disclosure · November 5, 2026
- Pembina Q3 2026 earnings call: third-party transcriptThe Motley Fool, reproducing Pembina management remarks · News reporting · November 6, 2026
- Truth & Reconciliation: Sturgeon County land acknowledgementSturgeon County · Municipal record · Accessed November 11, 2026