Active
The accepted request is progressing through assessment or connection work. Some connection phases may already be in service; this is not a statement that the whole facility is operating.

Independent. Publicly sourced. Alberta focused.
Explore verified projects, understand their potential impacts, and follow what has changed.
Use +/− or your keyboard to zoom. Hold Ctrl while scrolling, or use two fingers on touchscreens.
No verified projects match those filters.
ADCW inventory scope: The project-demand, generation, and water summaries above cover 54 proposed, approved, and under-construction projects. The 20 operating facilities and 4 inactive proposals remain in the full directory, but are excluded from those summaries so existing use is not mixed with proposed new demand. The separate AESO explorer below covers its broader connection-request list.

Large data centre campuses create new electricity demand. Meeting it can require dedicated power plants, gas pipelines, substations, cooling systems, and water infrastructure built alongside the server buildings.
Power · AESO connection requests
The Alberta Electric System Operator (AESO) tracks applications for grid connections. This number adds the requested grid capacity of its data-related entries, including projects paired with gas generation or batteries.
Data-related grid connection requests
27.6 GW
62 AESO entries · 27,646.29 MW requested
All included areas, stages, and statuses
Requested capacity, not power currently being used or a total approved for connection. 1 GW = 1,000 MW.
Start with all requests, then narrow by area, connection stage, or status. The number, bars, and entry list update together.
AESO November 2026 project list. Verified November 4, 2026.
Monthly project list verified by ADCW. Use Refresh data to check for a newer map update.
Included: Data Load, Gas + Data Load, Battery + Data Load, and Cogen + Data Load. Recently Cancelled entries are excluded.
Counted: AESO's Total DTS (Demand Transmission Service), the requested addition to grid-load capacity. Supply capacity is excluded. Entries are not a count of distinct campuses; battery hybrids may include charging load.
AESO statuses describe how requests are being handled. They are not consecutive phases or guarantees of approval.
The accepted request is progressing through assessment or connection work. Some connection phases may already be in service; this is not a statement that the whole facility is operating.
AESO is reconsidering the requested in-service date, meaning when the connection would become available. The request has not been cancelled.
The request is in AESO's third group of projects being assessed together. This applies to qualifying generation or storage projects, including data-related hybrids. The 3 identifies the group, not Stage 3.
Status amounts use the selected area and stage, before the status filter. All included statuses are selected on first load. AESO's status definitions ↗
Stage is progress through the grid-connection process. The route varies by project type; these are short summaries, not data-centre approval or construction labels.
| AESO entry | Planning area | Type / status | Stage | Requested MW |
|---|---|---|---|---|
| P2926 Beacon Foothills A.I. Hub Load | High River | Data Load ISD Under Review | 2 | 400 |
| P2927 Beacon Harry Smith A.I. Hub Load | Wabamun | Data Load ISD Under Review | 2 | 400 |
| P2928 Beacon Langdon A.I. Hub Load | Calgary | Data Load ISD Under Review | 2 | 400 |
| P2934 Beacon Heartland A.I. Hub Load | Fort Saskatchewan | Data Load ISD Under Review | 2 | 400 |
| P2935 Beacon Saunders Lake A.I. Hub Load | Edmonton | Data Load ISD Under Review | 2 | 400 |
| P2936 GLDC Load Phase 1.1 | Fort Saskatchewan | Data Load Active | 2 | 970 |
| P2942 Genesee Data Center 1 MPC Load | Wabamun | Data Load ISD Under Review | 2 | 1,000 |
| P2946 Genesee Data Center 2 MPC Load | Wabamun | Data Load ISD Under Review | 2 | 500 |
| P2952 North Calgary One Data Centre MPC Load | Calgary | Data Load Active | 2 | 74.9 |
| P2953 North Calgary Two Data Centre MPC Load | Calgary | Data Load Active | 2 | 74.9 |
| P2970 Beacon Langdon A.I. Hub 2 Load | Calgary | Data Load ISD Under Review | 1 | 1,400 |
| P3066 Leedale Data Load | Caroline | Data Load ISD Under Review | 2 | 1,864 |
| P3077 Calgary Enterprise A.I. Load | Calgary | Data Load Active | 2 | 74.9 |
| P3078 Calgary A.I. Centre Load | Calgary | Data Load Active | 2 | 74.9 |
| P3079 Captus Load | Glenwood | Data Load Active | 3 | 74.9 |
| P3083 Keephills Data Centre Phase 1.1 | Wabamun | Data Load ISD Under Review | 2 | 230 |
| P3095 Keephills Data Centre Phase 2 | Wabamun | Data Load ISD Under Review | 2 | 466 |
| P3101 Carstairs Technology Park MPC Load | Didsbury | Data Load ISD Under Review | 2 | 950 |
| P3102 Goldfinch Technology Park MPC Load | Strathmore/Blackie | Data Load ISD Under Review | 2 | 950 |
| P3106 Alberta South A.I. Load | Lethbridge | Data Load ISD Under Review | 1 | 400 |
| P3107 Chestermere Enterprise A.I. Load | Calgary | Data Load ISD Under Review | 1 | 400 |
| P3108 Wild Rose Power Hub Load | Calgary | Data Load ISD Under Review | 2 | 1,300 |
| P3109 Newell Data Center MPC Load | Brooks | Data Load ISD Under Review | 2 | 1,200 |
| P3110 Mihta Askiy Data Load | Peace River | Cogen + Data Load ISD Under Review | 1 | 300 |
| P3112 North Calgary Three Data Centre MPC Load | Calgary | Data Load ISD Under Review | 1 | 450 |
| P3114 Banshee Data MPC Load | Hinton/Edson | Data Load Active | 3 | 74.9 |
| P3116 Rocky View Data Center MPC Load | Calgary | Data Load ISD Under Review | 2 | 800 |
| P3126 Sollair Load | Airdrie | Data Load Active | 2 | 4.99 |
| P3136 Sundance Data MPC Load | Wabamun | Data Load ISD Under Review | 1 | 401 |
| P3137 Sheerness Data MPC Load | Sheerness | Data Load ISD Under Review | 1 | 800 |
| P3141 Opal Data Load | Fox Creek | Data Load Active | 1 | 0 |
| P3151 GLDC Load Phase 1.2 | Fort Saskatchewan | Data Load ISD Under Review | 2 | 830 |
| P3152 Keephills Data Centre Phase 1.2 | Wabamun | Data Load ISD Under Review | 1 | 165 |
| P3156 High Plains East Industrial Park | Calgary | Data Load ISD Under Review | 1 | 300 |
| P3157 Clearwater Technology Park Data Load | Calgary | Data Load Active | 2 | 74.9 |
| P3174 Sovereign Cloud Data Load | Edmonton | Data Load Active | 2 | 74.9 |
| P3175 Beacon Heartland Data Load | Fort Saskatchewan | Data Load ISD Under Review | 1 | 400 |
| P3198 Lynx Data Load | Fort Saskatchewan | Data Load ISD Under Review | 1 | 1,800 |
| P3204 Lynx Data Load Phase 2 | Fort Saskatchewan | Data Load ISD Under Review | 1 | 1,800 |
| P3211 Black Bear Gas Data Load | Swan Hills | Gas + Data Load Cluster 3 | 1 | 200 |
| P3216 Georgetown Data Load | Strathmore/Blackie | Data Load Active | 1 | 72.9 |
| P3227 Sheerness Data Load | Sheerness | Data Load Active | 1 | 74.9 |
| P3236 AEC Mill 844S Data Load | High Prairie | Data Load Active | 1 | 60 |
| P3248 Banshee MPC Data Load Reliability | Hinton/Edson | Data Load Active | 1 | 0 |
| P3280 Nexus East MPC Gas Data Load | Empress | Gas + Data Load Cluster 3 | 1 | 600 |
| P3281 Rimbey MPC Gas Data Load | Red Deer | Gas + Data Load Cluster 3 | 1 | 600 |
| P3282 Nexus West MPC Gas Data Load | Caroline | Gas + Data Load Cluster 3 | 1 | 600 |
| P3283 BBPI MPC Gas Data Load | Swan Hills | Gas + Data Load Cluster 3 | 1 | 600 |
| P3284 ResiliON MPC Gas Data Load | Wabamun | Gas + Data Load Cluster 3 | 1 | 800 |
| P3285 Wildcat MPC Gas Data Load | Seebe | Gas + Data Load Cluster 3 | 1 | 150 |
| P3312 Travers Battery Data Load | Stavely | Battery + Data Load Cluster 3 | 1 | 300 |
| P3326 Ursa Major Gas Data Load | Swan Hills | Gas + Data Load Cluster 3 | 1 | 466 |
| P3338 Clearwater Area Data Load | Fort McMurray | Data Load Active | 1 | 74.9 |
| P3341 Maple Rose Data Load | Brooks | Data Load ISD Under Review | 1 | 200 |
| P3342 Brooks 121S Data Load | Brooks | Data Load Active | 1 | 18 |
| P3343 West Brooks 28S Data Load | Brooks | Data Load Active | 1 | 12.5 |
| P3347 Brooks Area Data Load | Brooks | Data Load Active | 1 | 40 |
| P3348 Vulcan Data Load | Stavely | Data Load Active | 1 | 74 |
| P3349 High River Data Load | Fort Macleod | Data Load Active | 1 | 74 |
| P3350 Fulton Data Load | High River | Data Load Active | 1 | 74 |
| P3352 Cypress Pine Data Load | Calgary | Data Load ISD Under Review | 1 | 200 |
| P3353 EA Link Data Load | Fort Saskatchewan | Data Load Active | 1 | 74.9 |
No entries match these filters. Reset filters to return to the full total.
The saved figures are checked against AESO's monthly project list and public connection-project map service, linked from its connection project reporting page. AESO publishes its project list monthly. The verified monthly snapshot appears on page load. Refresh data optionally checks the map service for a newer update; if a complete response cannot be verified, the displayed data stays in place. Unfamiliar categories or possible data-related requests outside the selected categories require review before the live total can update.
All included statuses and connection stages are counted by default. Status descriptions follow AESO's project-list guide; stage summaries follow its independent assessment, cluster assessment, and connection processes.
Connection, Cluster, and Behind the Fence (BTF) entries are included where they have a data-related type. Zero-MW entries remain in the entry count. Cogen means combined heat and power. The mixed gas, battery, and cogen types are included to avoid dropping data-related requests simply because they include supply or storage.
This is a source-defined request queue, not ADCW's verified project inventory, approved connections, operating use, or an estimate of every Alberta data centre. Off-grid proposals may be absent. Do not add this total to generation capacity or to ADCW's separately curated project-demand total. AESO's full dashboard opens with its own controls; these filters are not passed to Power BI.
Old scale versus new scale
At their published capacities, Beacon Indus would equal about 480 times Qu Edmonton EDM1's electricity capacity.
≈ 480×the electricity capacity
Each small mark represents the capacity of one Qu Edmonton EDM1 facility. This compares published electricity capacity, not building sizes, actual use, or a count of Indus buildings. Indus is proposed. 1 GW = 1,000 MW.
About 10.5 terawatt-hours (TWh) in one year
If a facility drew 1.2 GW continuously for a year, it would use slightly more electricity than was delivered across Calgary in all of 2025.
This illustrates the proposed maximum at full demand every hour, not the project's expected or actual use. ENMAX reports 9.8 TWh delivered in Calgary in 2025.
One portfolio: 4.5 GW. Beacon's announced six-site Alberta portfolio alone equals about 44% of Alberta's 2025 average demand. Portfolio announcement, not operating demand or a guarantee that every site will be built.
Meeting new data centre demand can require dedicated power plants, gas pipelines, substations, cooling systems, and water infrastructure alongside the server buildings.
Putting water demand in human terms
1 m³1,000 L
13.8 million L/day
Residential water use for about 70,700 Albertans
in a single dayThis total comes from only 5 of 54 active projects.It combines comparable projected or proposed daily water volumes, including water published for related power plants. It is not measured province-wide use.
This comparison uses Alberta's 2021 residential average of 195 litres per person per day, the latest province-wide figure published by Statistics Canada. It compares volume only and does not mean the project water is potable, comes from a municipal system, or is entirely consumed.View the Statistics Canada data.
Read the label, not just the number. Water licensed, withdrawn, consumed, and returned describe different things.
Alberta Data Centre Watch is an independent public-interest project that makes fragmented information about Alberta data centre development easier to find, compare, and understand.
ADCW is not affiliated with any government, regulator, municipality, political party, or project proponent. It tracks material data centre infrastructure across AI, hyperscale, high-performance computing, colocation, cryptocurrency, and other workloads, plus directly related power infrastructure when the connection can be documented. Ordinary internal server rooms fall outside the current scope.
Primary sources come first. Company and government claims are attributed to the people making them. Unknown information stays visible, and every material summary should lead back to an original record.
Read how ADCW verifies Alberta data centre projects →