Meaningful movement, plainly explained

ADCW Weekly

New records, material evidence, hearings, decisions, and significant project changes. Small site fixes and routine housekeeping stay out of the bulletin.

Current edition

ADCW Weekly

WHAT'S NEW

Carbon: power-plant construction reported complete

Athill’s April 28, 2026 AUC notice reports construction complete for the 5.545 MW second phase. The 4.425 MW first phase was previously reported commissioned on October 30, 2025, within the original 9.97 MW design.

Why it matters: The notice confirms Athill’s construction-completion report, but does not establish Phase 2 commissioning or current mining operation. The listing also adds the County’s original 2.23-acre Bitcoin-mining plan and container layout.

View project →

Wetaskiwin: conditional permit under appeal

Added the 860 ft² data-processing facility covered by County permit D26/169. The County conditionally approved it on August 27, 2026 and confirmed on November 4, 2026 that the permit is under appeal.

Why it matters: The record identifies the permitted development and its noise, water-approval, lighting, and reclamation conditions. Applicant, capacity, construction, and operation remain unconfirmed.

View project →

Hoole: Bigstone Cree Nation requests participation and a hearing

A statement reviewed November 5, 2026 raises consultation and Treaty rights concerns about the proposed 19.8 MW gas facility, including effects on traditional land uses, wildlife, water, and cultural knowledge.

Why it matters: The Nation asks to present oral Indigenous knowledge in its community and to inform mitigation and reclamation. Its submission is not an AUC finding or confirmation that a hearing has been ordered.

View project →

AESO: November grid-request snapshot

The November 2026 list contains 62 data-related connection requests totalling 27,646.29 MW, compared with 53 entries and 26,848.99 MW in October. Ten new entries were added, Balzac Area Load moved to Distribution Load, and Mihta Askiy remains included under Cogen + Data Load.

Why it matters: These are requested grid capacities, not approved connections or electricity currently being used. The homepage starts with the verified monthly list; Refresh data optionally checks for a newer map update.

Explore power requests →

Past editions

ADCW Weekly

WHAT'S NEW

Wonder Valley: two additional court challenges filed

Sturgeon Lake Cree Nation filed applications on September 29 and October 15, 2026 to review the province's decision not to require an environmental impact assessment report and its Level 1 consultation classification. A separate water-licence review was already underway.

View project →

ADCW Weekly

WHAT'S NEW

CAL-3: AUC notice issued for backup generators

The AUC issued Notice of Application 31020-F0005 on November 2, 2026 for the existing emergency standby-generator application in Proceeding 31020.

View project →

Chestermere: subdivision approval does not authorize a data centre

The City confirms conditional subdivision approval, but says no data-centre development-permit application has been submitted and no development permit has been approved for construction, as checked November 3, 2026.

View project →

ADCW Weekly

WHAT'S NEW

Hanna: how the power and ownership proposals have changed

After the earlier 9.9 MW concept and October 1, 2026 grid-plus-gas design, the October 27, 2026 plan makes gas optional and separately specifies 2.4 MW of computing capacity. It also introduces a proposed 51%/49% FingerMotion/Genius Group venture. A separate October 29, 2026 non-binding merger proposal would change FingerMotion’s corporate control.

View project →

Hoole: updated noise evidence and conflicting schedules

The October 16, 2026 noise update retains the predicted sound levels and unresolved low-frequency inconsistency. Its completion targets differ from the schedule in the power-plant application.

View project →

ADCW Weekly

WHAT'S NEW

Boreal: technical information sessions on November 12, 2026

The project team plans sessions from 4:00 to 7:00 p.m. at Keephills Community Hall, with presentations repeating hourly. Topics include community benefits, studies and approvals, water, and the environment.

View project →

Westlock cryptocurrency facility remains stopped without a confirmed gas path

Added a full profile for SAIDI and MAGA's approved 9 MW off-grid cryptocurrency project. Installed generators remain shut down under a County Stop Order, while the late time-extension and transfer applications remain under AUC review.

View project →

ADCW Weekly

WHAT'S NEW

Explore AESO data-related electricity requests

The homepage now separates AESO connection requests from ADCW project-demand and generation figures. Filter the requested load by planning area, connection stage, and AESO status, and inspect the entries behind the total.

Explore power requests →

SunFavor Bashaw: proposed mining and agricultural heat-reuse hub

Added a profile for two proposed 23 MW gas plants supplying on-site data processing and agricultural processing in Camrose County. The AUC has requested further noise, air-quality, environmental, and consultation evidence.

View project →

ADCW Weekly

WHAT'S NEW

Beacon Heartland: County confirms site-preparation permits

Sturgeon County confirms both the topsoil and full grading permits are for Beacon Heartland and required grading approvals have been obtained. The public notice gives November 12, 2026 as the grading permit's effective date and restricted appeal deadline.

View project →

ADCW Weekly

WHAT'S NEW

Edmonton EETP: no replacement eco-industrial policies proposed

The City says Walton's applicant has proposed no replacement eco-industrial policies or guidelines. Stantec's report would also exempt data centres and associated power generation from the plan's design guidelines.

View project →

ADCW Weekly

WHAT'S NEW

Beacon Heartland: 920 MW gas plant approved with conditions

The AUC issued its power-plant decision on October 23, 2026. It approves 200 natural-gas engines intended to supply approximately 800 MW to the proposed data centre, with further design, noise, emergency-response, and reclamation-security requirements.

View project →

ADCW Weekly

WHAT'S NEW

Meta: foundation-piling permit issued

Sturgeon County issued DP-26-0293 on October 20, 2026 for foundation pilings only for Building DCB01 and Mechanical Yard MY01. Its stated effective date and appeal deadline are November 10, 2026.

View project →

ADCW Weekly

WHAT'S NEW

Blindman: project map location corrected

The AHI marker now shows the campus area east of Range Road 271, opposite Hewlett Drive, consistent with the County application maps.

View project →

ADCW Weekly

WHAT'S NEW

Boreal: preliminary water and jobs figures

Boreal has published cooling-water estimates and a projection of 150 Phase 1 operating jobs. The profile also distinguishes the separate Keephills Unit 1 repowering approval from the data centre.

View project →

Emerson Trail: permit appeal hearing scheduled

The County confirms that development permit PLDEV20250629 is under appeal, with a preliminary Land and Property Rights Tribunal hearing scheduled for October 26, 2026.

View project →

ADCW Weekly

WHAT'S NEW

Boreal: larger proposed build-out and open-house update

The project website now describes up to 1.6 GW at full build-out, above the earlier 1 GW disclosure. Boreal confirms its October 7, 2026 open house was held and has posted materials; a feedback-results report was not found on the reviewed pages.

View project →

ADCW Weekly

WHAT'S NEW

Junction 42: public hearing scheduled

Red Deer County will hold a joint public hearing on November 17, 2026 at 1:30 p.m. for the Junction 42 planning amendment and proposed 13.82-acre rezoning. Written submissions received by November 6, 2026 will appear in the agenda.

View project →

ADCW Weekly

WHAT'S NEW

Goldfinch: cooling without process water, but other water needs remain

The final concept plan proposes air-based cooling and estimates about 11,200 L/day for staff facilities, with separate fire-water storage. It targets phase openings in 2029, 2031, and 2033, subject to permits and infrastructure.

View project →

ADCW Weekly

WHAT'S NEW

Emerson Trail: a chance to shape future data centre rules

Grande Prairie County has started a bylaw change that would require future data centres to seek their own zoning designation. Residents can submit feedback now and take part in a public hearing on December 2, 2026.

View project →

ADCW Weekly

WHAT'S NEW

CAL-3: water needs and diesel backup power

The permit identifies 2,560 L/day of water capacity for the property. eStruxture estimates that running 19 backup generators at the loads in its filing would use about 11,920 L of diesel and release 32 tonnes of carbon dioxide per hour.

View project →

ADCW Weekly

WHAT'S NEW

Slave Lake Pulp / A.E.C. Mill data-load request

Added a verified listing for a 60 MW electricity connection request associated with the existing Slave Lake Pulp / A.E.C. Mill 844S facility in Mitsue. AESO lists P3236 at Stage 1 in its September 2026 report.

View project →

ADCW Weekly

WHAT'S NEW

Junction 42 AI research lab proposed near Penhold

Red Deer County announced a land purchase offer for Lot 24 and a required rezoning process for an estimated $300 million AI research lab.

View project →

Hanna Campus #1 conditional purchase agreement and revised design

FingerMotion announced an agreement executed September 30, 2026, with 60 days of due diligence and closing scheduled after conditions are waived. Its revised concept proposes 3 MW of grid supply and 3 MW of on-site gas generation.

View project →

ADCW Weekly

WHAT'S NEW

Power arrangements and explanations beside project terms

Visit the How It All Works section to understand grid connections, behind-the-meter generation, tethered generation, and temporary bridging. Question-mark help explains relevant power, cooling, water, approval, and evidence terms within profiles and expanded listings.

Visit How It All Works →

Ewing Lake data-processing approval revoked

ADCW corrected the listing after reviewing the August 22, 2025 Tribunal decision, which revoked approval of the Bitcoin-mining use while preserving the power-generation approval with revised conditions.

View project →

FingerMotion Brooks Campus #1 acquisition agreement

FingerMotion disclosed a conditional US$2.3 million acquisition of Newbit, including existing site rights, permits, and fixed infrastructure.

View project →

ADCW Weekly

WHAT'S NEW

Edmonton Energy & Technology Park planning amendment

Edmonton is reviewing Stantec's application for Walton Global Investments to allow data centres and associated power generation in the park's Medium Industrial Precinct and redesignate about 625 acres.

View project →

Armada Nowlit Clive proposal

Lacombe County identifies the application parties and confirms rezoning must come before a development permit. The developer now describes dry cooling, off-site wastewater servicing, and a 36.0 dBA modelled nighttime total at the closest assessed home.

View project →

County of Newell data centre bylaw

The County held a public hearing on proposed Bylaw 2129-26 on September 10, 2026. Its September 24, 2026 Council agenda listed a petition about the bylaw but no third reading.

View project →

ADCW Weekly

WHAT'S NEW

Boreal Technology Hub at Keephills

Parkland County now calls the Keephills proposal Boreal Technology Hub. BGRE will lead development for Brookfield and CPP Investments and host an October 7, 2026 open house.

View project →

ADCW Weekly

WHAT'S NEW

FingerMotion Hanna Campus #1

FingerMotion says its Hanna subsidiary signed a binding letter of intent for land at 409 Pioneer Trail South for a proposed 9.9 MW power-and-compute site.

View project →

ADCW Weekly

WHAT'S NEW

Emerson Trail data centre permit

The County of Grande Prairie issued development permit PLDEV20250629 on September 4, 2026, for a data processing establishment in the Emerson Trail Industrial Area.

View project →

Woodcote cryptocurrency facility

Big Lakes County has approved permit 26-D0053 for a cryptocurrency-mining facility on an existing oil and gas lease north of Lesser Slave Lake Narrows.

View project →

ADCW Weekly

WHAT'S NEW

Alberta power generation map layer

The project map now includes an optional CODERS layer with 210 Alberta generation facilities, their installed capacity, generation source, and snapshot status.

View map →

ADCW Weekly

WHAT'S NEW

Kakwa cryptocurrency project

A new profile documents a proposed data-processing centre of up to 9.9 MW paired with an AUC-approved 8.40 MW isolated natural-gas plant in Greenview.

View project →

ADCW Weekly

WHAT'S NEW

Meta Sturgeon permit appeal

A September 15, 2026 filing asks the Land and Property Rights Tribunal to let challenges to the Project Frost master permit proceed to a full hearing.

View project →

ADCW Weekly

WHAT'S NEW

Travers AI Data Centre Campus

A July 22, 2026 judicial review application challenges Vulcan County's rezoning decision and is scheduled for September 29, 2026.

View project →

FingerMotion Alberta program

FingerMotion says it is advancing ten separate 9.9 MW sites across Brooks, Coronation, Fox Creek, and Vulcan, totalling 99 MW of gross generation.

View project →

ADCW Weekly

WHAT'S NEW

Fire Technology Torrington

Kneehill County approved two additional units in April 2026 for the existing 9.5 MW cryptomining facility near Torrington.

View project →

Fire Technology Ewing Lake

County permit DP 24097 conditionally approved nine gas generators totalling 9.9 MW and nine Bitcoin-mining containers.

View project →

Athill Carbon-area data centre

Municipal and AUC records document a data centre paired with 9.97 MW of approved natural-gas generation southwest of Carbon.

View project →

Pathfinder Rocky 5

The 60 MW approved Bitcoin-mining power project is now tracked with Pathfinder and MCK's court-appointed receivership.

View project →

ADCW Weekly

WHAT'S NEW

Armada Nowlit Wabasca / Hoole

A new Rule 007 filing proposes a 19.8 MW on-site natural-gas facility serving nine co-located data-centre units.

View project →

ADCW Weekly

WHAT'S NEW

StratGrid Project Wheatland

An SEC-filed Jet.AI disclosure identifies a proposed Wheatland County campus designed around approximately 200 MW of on-site natural-gas generation.

View project →

Gayford and Clive record correction

Gayford is now a separate proposed record. AUC proceedings 30385, 30476, and 30709 were removed from Clive and assigned to the 19.95 MW Gayford facility.

View project →

eStruxture CAL-3

AUC Proceeding 31020 seeks approval for 21 diesel emergency standby generators totalling 66.75 MW at CAL-3.

View project →

ADCW Weekly

WHAT'S NEW

2661707 Alberta Ltd. Greenview sites

Municipal records show eight effective permits for modular data processing centres on existing gas-well footprints. A ninth application remains deferred.

View project →

FingerMotion Brooks Campus Zone

FingerMotion announced a binding memorandum to acquire land rights and permitting for a first 9.9 MW behind-the-meter site in the County of Newell.

View project →

Data District Bonnyville

Alberta's Phase 1 record names Bonnyville as the expected second of four regional projects in a combined 240 MW program led by Data District and Technologies New Energy.

View project →

ADCW Weekly

WHAT'S NEW

Alberta natural-gas policy

Alberta says industrial proponents have raised concerns about access to large quantities of natural gas and that it is working with industry and infrastructure owners on possible solutions.

View issue →

ADCW Weekly

WHAT'S NEW

Beacon Saunders Lake

New municipal evidence confirms the 160-acre land-use change. The County said on June 26 that it had approved no data-centre development permits.

View project →

Wild Rose Power Hub

A new evidence profile explains the plan under review, developer cooling claims, and conflicting job figures.

View project →

Beacon Foothills

The profile now explains the amended plan’s wetland and wildlife evidence and further checks required before disturbance.

View project →

Prairie Sky Strathmore

The listing now separates the company’s elapsed Q2 2026 opening target and phased roadmap from verified project progress.

View project →

ADCW Weekly

WHAT'S NEW

Beacon Indus

The AUC oral hearing for the proposed 1.494 GW natural-gas power plant has been held, and a decision is still pending.

View project →

Goldfinch Technology Park

Wheatland County's final plan confirms the area concept plan was adopted and places technology centres in a Medium Industrial policy area.

View project →

AESO Bring Your Own Generation

The AESO delayed final rules and application intake for its Bring Your Own Generation process until fall 2026.

View issue →

Prairie Sky Strathmore

Prairie Sky now publishes a staged path from a 2 MW retrofit to 50 MW and says it is designing for direct liquid cooling.

View project →