Meta Sturgeon permit appeal
A September 15, 2026 filing asks the Land and Property Rights Tribunal to let challenges to the Project Frost master permit proceed to a full hearing.
Why it matters: The preliminary dispute covers who may appeal and whether the permitted-use approval complied with other planning rules. The appellants cite 848 planned backup generators, large-scale fuel storage, 351 wetlands, and allegedly missing or deferred studies. These are unresolved claims, not Tribunal findings. A separate Greenlight site-grading permit takes effect October 9, 2026, unless appealed.